Walton Croft Cavendish Avenue Sudbury Harrow

Awaiting decision Old Oak and Park Royal Development Corporation 264138CONS Consultation by Other Boroughs

Works: New dwelling Extension

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Construction of two storey upward extension to provide six additional self-contained residential flats (Class C3) 2 x 1 bed; 2 x 2 beds; 1 x 3 beds; 1 x 4 beds); associated parking, cycle storage and refuse facilities (out of borough)

As published by the council, reference 264138CONS

Application record

Reference
264138CONS
Type
Consultation by Other Boroughs
Status
Pending Consideration
Received
9 Nov 2026
Validated
9 Nov 2026
Ward
Out Of Borough

Timeline

Dates from the published record

  1. 9 Nov 2026

    Received by Old Oak and Park Royal Development Corporation

  2. 24 Nov 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 4 January 2027, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Old Oak and Park Royal Development Corporation took a median of 56 days over the applications it decided in the last year.

What happens while it is decided

This application is with Old Oak and Park Royal Development Corporation for determination, against a statutory target of eight weeks. Over the last year Old Oak and Park Royal Development Corporation decided outline applications in a median of 23 days. More in our guide to how long planning decisions take.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

In Old Oak and Park Royal Development Corporation

  • 264200CONS Awaiting decision

    Chiswick Roundabout Chiswick London W4 3AA

    Redevelopment of the site to provide a mixed-use building with a maximum height of 27 storeys comprising of 496 Purpose-Built Shared Living units (Sui Generis); 60 residential units (Use Class C3); retail and office (Class E); amenity space; public realm improvements, landscaping, and other associated works (out of borough)

    Received 18 Nov, published by the council 21 Nov 2026 Outline
  • 264176OPDCOB Awaiting decision

    Communication Station On Roof Black Arrow House 2 Chandos Road Park Royal NW10 6NF

    Application for Prior Approval under Schedule 2, Part 11, Class B of the Town and Country Planning (General Permitted Development) (England) Order 2015 (as amended) for the demolition of the existing building and associated concrete slab and foundations (out of borough)

    Received 17 Nov, published by the council 21 Nov 2026 Outline
  • 264171CONS Awaiting decision

    21 Craneswater Park Southall UB2 5RW

    Single storey rear extension with flat roof and 3x skylights (out of borough)

    Received 16 Nov, published by the council 24 Nov 2026 Outline
  • 262500PAPV Granted

    Cygnet Hospital 22 Corfton Road Ealing W5 2HT

    Installation of Solar PV panels to roof (Class J, 56 days Prior Approval Process)

    Received 22 Jun, published by the council 27 Jul 2026 Outline
  • 264170OPDCOB Awaiting decision

    Renault London West Site Of Renault Retail Group Ltd Western Avenue Acton W3 0RZ

    Partial discharge of condition 5 (Materials - data centre building only) pursuant to planning permission reference 24/0141/VAROPDC dated 20/12/2024 for 'Section 73 application to vary Conditions 2 (approved plans and documents), 3 (development parameters), 5 (contaminated land site investigation), 6 (Construction and Environmental Management Plan), 7 (Construction Logistics Plan), 8 (circular economy details), 10 (Secured by Design), 11 (hard and soft landscaping), 12 (cycle parking), 13 (Fire Strategy), 19 (external lighting), 20 (green roofs), 21 (vehicular access), 22 (car parking implementation), 27 (vehicular access restriction), and 30 (energy statement) of planning permission 22/0059/FUMOPDC for 'Redevelopment of the site to provide a data centre (Use Class B8) with associated energy and electrical infrastructure, visitor reception building, security gatehouse, plant, boundary enclosures, car and cycle parking, hard and soft landscaping; and associated alterations to vehicular access arrangements including creation of new access from Concord Road and new access from Western Avenue service road; and associated external works.' Amendments are proposed primarily to replace the approved sub-station/ancillary office building with a standalone sub station building, and to increase the size of the pocket park ( out of borough)

    Received 13 Nov, published by the council 24 Nov 2026 Outline