Planning application
Hexham, Halton Northumberland
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Comments within 2 months. Upgrade the supply at the above property to 60kVA 3-phase from 40kVA Split in order to provide a 3 phase supply. In order to facilitate the request, it is proposed to rebuild an existing overhead high voltage line with 50mm conductors increasing the conductors from 2 to 3 across 9 spans. The transformer is to be replaced with a new 20,000/433V 3ph 100kVA unit. A new short leg H-Pole will be required for the new transformer shown at grid reference E391336 N56919 on the plan. This will be upgrading the existing single pole into a short leg double pole. Reference: TS/ENQ23249603
As published by the council, reference 26/03647/MISC
Application record
- Reference
- 26/03647/MISC
- Status
- Registered
- Received
- 14 Oct 2026
- Validated
- 14 Oct 2026
Timeline
Dates from the published record
-
14 Oct 2026
Received by Northumberland
-
15 Oct 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 9 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Northumberland took a median of 50 days over the applications it decided in the last year.
What happens while it is decided
This application is with Northumberland for determination, against a statutory target of eight weeks. Over the last year Northumberland's median decision took 50 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Northumberland's portal will say. Our guide explains the common types.