Planning application

Land North West Of High Brocklands Brock Lane West Sleekburn Northumberland

Awaiting decision Northumberland 26/02160/OUTES

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Outline planning permission, with all matters reserved except access, for a Data Centre facility (Use Class B8) totalling up to 356,500sqm gross internal area with ancillary power generation (up to 49.9MW), including Data Centre buildings, ancillary offices, substations, power plant, emergency generators, and associated site infrastructure, landscape, engineering and drainage works.

As published by the council, reference 26/02160/OUTES

Application record

Reference
26/02160/OUTES
Status
Registered
Received
17 Jun 2026
Validated
17 Jun 2026
Ward
Sleekburn
Parish
East Bedlington
Decision by
Delegated Decision

Timeline

Dates from the published record

  1. 17 Jun 2026

    Received by Northumberland

  2. 9 Aug 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 12 August 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Northumberland took a median of 45 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

Lichfields Agent, registered in Newbury

Active · incorporated 2006 · Newbury

1,653 applications on PlanIndex · across 160 councils · 93% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

150 documents on file for this application

  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 13 Sep 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 09 Sep 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 20 Aug 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 07 Aug 2026
  • 85 RINGWAY Objection · 03 Aug 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 02 Aug 2026
  • LANDSCAPE ARCHITECT Consultee Response · 31 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 28 Jul 2026
  • ECONOMIC DEVELOPMENT Consultee Response · 28 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 28 Jul 2026
  • COMMENT (NEUTRAL) SUBMITTED ONLINE General Comment · 27 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 26 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 26 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 26 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 26 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 26 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 26 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 25 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 25 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 25 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 25 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 25 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 24 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 24 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 24 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 24 Jul 2026
  • NATIONAL HIGHWAYS Consultee Response · 24 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 24 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 24 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 24 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 23 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 23 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 23 Jul 2026
  • COMMENT (NEUTRAL) SUBMITTED ONLINE General Comment · 22 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 22 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 22 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 22 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 17 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 17 Jul 2026
  • COMMENT (NEUTRAL) SUBMITTED ONLINE General Comment · 17 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 17 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 16 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 16 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 15 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 15 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 14 Jul 2026
  • NATURAL ENGLAND Consultee Response · 13 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 13 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 13 Jul 2026
  • 3 MENDIP CLOSE Objection · 13 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 13 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 12 Jul 2026
  • 13 WANSBECK TERRACE Objection · 10 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 09 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 09 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 08 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 08 Jul 2026
  • 13 WANSBECK TERRACE Objection · 08 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 05 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 05 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 02 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 02 Jul 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 02 Jul 2026
  • THE COAL AUTHORITY RESPONSE Consultee Response · 01 Jul 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 30 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 30 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 30 Jun 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 29 Jun 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 29 Jun 2026
  • NATIONAL GAS TRANSMISSION Consultee Response · 29 Jun 2026
  • HSE Consultee Response · 29 Jun 2026
  • COMMENT (SUPPORT) SUBMITTED ONLINE Support Comment · 28 Jun 2026
  • ACTIVE TRAVEL Consultee Response · 26 Jun 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 25 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 24 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 23 Jun 2026
  • CONSULTEE COMMENT SUBMITTED ONLINE Consultee Comment · 23 Jun 2026
  • ACTIVE TRAVEL ENGLAND Consultee Response · 23 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 23 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 23 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 22 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 22 Jun 2026
  • 3 MENDIP CLOSE Objection · 22 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 22 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 22 Jun 2026
  • COMMENT (OBJECTION) SUBMITTED ONLINE Objection Comment · 19 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER A - INTRODUCTION AND BACKGROUND Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER B - SCOPE AND METHODOLOGY Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER C - SITE AND SCHEME DESCRIPTION Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER D - LANDSCAPE & VISUAL Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER E - AIR QUALITY Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER F - NOISE AND VIBRATION Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER G - CLIMATE CHANGE Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER H - ECOLOGY Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER I - TRANSPORT AND ACCESS Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER J - WATER RESOURCES AND FLOOD RISK Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER K - SOCIO-ECONOMICS Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER L - BELOW GROUND HERITAGE Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER M - MAJOR ACCIDENTS AND DISASTERS Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER N - CUMULATIVE EFFECTS Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: CHAPTER O - MITIGATION AND MONITORING Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX B - SCOPE AND METHODOLOGY Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX C - SITE AND SCHEME DESCRIPTION Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX E - AIR QUALITY Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX F - NOISE AND VIBRATION Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX G - CLIMATE CHANGE Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX H - ECOLOGY Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX L - BELOW GROUND HERITAGE Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX M - MAJOR ACCIDENTS AND DISASTERS Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX N - CUMULATIVE EFFECTS Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX A - INTRODUCTION AND BACKGROUND Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX I - TRANSPORT AND ACCESS Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX J - WATER RESOURCES AND FLOOD RISK Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 3 - NON TECHNICAL SUMMARY Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX D - LANDSCAPE AND VISUAL PART 1 Report/ Statement · 17 Jun 2026
  • ENVIRONMENTAL STATEMENT: VOL 2 - APPENDIX D - LANDSCAPE AND VISUAL PART 2 Report/ Statement · 17 Jun 2026
  • APPLICATION FORM REDACTED Application Form · 16 Jun 2026
  • SITE LOCATION PLAN Location Plan · 16 Jun 2026
  • APPLICATION BOUNDARY PLAN Plan · 16 Jun 2026
  • EXISTING SITE CONSTRAINTS AND OPPORTUNITIES PLAN Plan · 16 Jun 2026
  • EXISTING SITE ASSESSMENT Plan · 16 Jun 2026
  • PARAMETERS PLAN LAND USE Plan · 16 Jun 2026
  • PARAMETERS PLAN HEIGHTS PLAN Plan · 16 Jun 2026
  • PARAMETERS PLAN SITE LEVELS Plan · 16 Jun 2026
  • PARAMETERS PLAN ACCESS Plan · 16 Jun 2026
  • OUTLINE APPLICATION SITE PLAN Plan · 16 Jun 2026
  • HIGHWAY WORKS GENERAL ARRANGEMENT NORTHERN SITE PRIMARY ACCESS Plan · 16 Jun 2026
  • HIGHWAY WORKS GENERAL ARRANGEMENT SOUTHERN SITE PRIMARY ACCESS Plan · 16 Jun 2026
  • HIGHWAY WORKS GENERAL ARRANGEMENT SOUTHERN SITE EMERGENCY ACCESS Plan · 16 Jun 2026
  • HIGHWAY WORKS GENERAL ARRANGEMENT OFF SITE BUS STOP IMPROVEMENTS Plan · 16 Jun 2026
  • HIGHWAY WORKS GENERAL ARRANGEMENT OFF SITE FOOTWAY IMPROVEMENTS Plan · 16 Jun 2026
  • ARBORICULTURAL REPORTS Report/ Statement · 16 Jun 2026
  • BNG FEASIBILITY REPORT Report/ Statement · 16 Jun 2026
  • COAL MINING RISK ASSESSMENT Report/ Statement · 16 Jun 2026
  • DESIGN AND ACCESS STATEMENT Report/ Statement · 16 Jun 2026
  • DESIGN CODE Report/ Statement · 16 Jun 2026
  • HEALTH IMPACT ASSESSMENT Report/ Statement · 16 Jun 2026
  • MINERAL RESOURCE ASSESSMENT Report/ Statement · 16 Jun 2026
  • PHASE 1 DESK STUDY PART 1 Report/ Statement · 16 Jun 2026
  • PHASE 1 DESK STUDY PART 2 Report/ Statement · 16 Jun 2026
  • PHASE 1 DESK STUDY PART 3 Report/ Statement · 16 Jun 2026
  • PHASE 1 DESK STUDY PART 4 Report/ Statement · 16 Jun 2026
  • PLANNING STATEMENT Report/ Statement · 16 Jun 2026
  • SOIL RESOURCE MANAGEMENT STRATEGY Report/ Statement · 16 Jun 2026
  • STATEMENT OF COMMUNITY INVOLVEMENT Report/ Statement · 16 Jun 2026
  • EXISTING SITE PLAN Plan · 16 Jun 2026
  • SITE 3DS Plan · 16 Jun 2026
  • SITE 3DS Plan · 16 Jun 2026
  • COVERING LETTER Correspondence · 16 Jun 2026
  • HIGHWAY WORKS LOCATION PLAN Plan · 16 Jun 2026

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Northumberland for determination, against a statutory target of eight weeks. Over the last year Northumberland's median decision took 45 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Northumberland's portal will say. Our guide explains the common types.