St Wilfrids Community Centre Coltsgate Hill Ripon North Yorkshire HG4 2AB

Granted North Yorkshire 26/01884/FUL Full permission

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

To install 10 x Solar PV panels on the 1st floor flat roof of St Wilfrid's Community Centre Ripon

As published by the council, reference 26/01884/FUL

Application record

Reference
26/01884/FUL
Type
Full permission
Status
Decided
Decision
Application Permitted
Received
14 Apr 2026
Validated
14 Apr 2026
Decided
9 Jun 2026
Ward
Ripon Ure Bank & Spa
Parish
Ripon
Decision by
Chief Planner
Postcode
HG4 2AB

Timeline

Dates from the published record

  1. 14 Apr 2026

    Received by North Yorkshire

  2. 9 Jun 2026

    Decision issued: Application Permitted

  3. 4 Aug 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

Agent on file

3 applications on PlanIndex · across 3 councils

Trade members see who it is, their full track record, and every application they have filed.

See who's behind it

Documents

Plans, drawings, consultee responses and the officer's report

17 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What a grant of permission means

The process from here

Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.

Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.

About full applications applications

How this application type works

A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.

More on full applications applications in our guide

Nearby applications

Within 500 metres

  • St Wilfrids Community Centre Coltsgate Hill Ripon North Yorkshire HG4 2AB

    26/01884/FUL Submitted 14 Apr 2026 0m away

    To install 10 x Solar PV panels on the 1st floor flat roof of St Wilfrid's Community Centre Ripon

    Granted Full applications 17 docs
  • St Wilfrids Community Centre Coltsgate Hill Ripon North Yorkshire HG4 2AB

    26/01884/FUL Submitted 14 Apr 2026 0m away

    To install 10 x Solar PV panels on the 1st floor flat roof of St Wilfrid's Community Centre Ripon

    Granted Full applications 17 docs
  • North Yorkshire Timber Company Limited Trinity Lane Ripon North Yorkshire HG4 2AL

    26/02205/DVCMAJ Submitted 30 Apr 2026 50m away

    Section 73 application to allow alterations to ground floor frontages and installation of PV panels to rear roofslopes through the variation of Condition 2 (Approved drawings) of Planning Permission HGTZC23/02034/FULMAJ for the demolition of existing buildings and erection of thirteen dwellings, realigned access onto Trinity Lane, and associated parking and landscaping.

    Granted Conditions Demolition 12 docs
    Major scheme
  • North Yorkshire Timber Company Limited Trinity Lane Ripon North Yorkshire HG4 2AL

    26/00620/AMENDS Submitted 5 Feb 2026 50m away

    Non-material amendment to allow alterations to approved plans of planning permission ZC23/02034/FULMAJ Full planning application for the demolition of existing buildings and erection of thirteen dwellings realigned access onto Trinity Lane, and associated parking and landscaping.

    Granted Amendments Demolition 14 docs
  • North Yorkshire Timber Company Limited Trinity Lane Ripon North Yorkshire HG4 2AL

    26/00392/DISCON Submitted 26 Jan 2026 50m away

    Approval of details under condition 14 (Energy statement) condition 17 (landscaping scheme) condition 18 (external wall and roof materials) and condition 19 (sound insulation scheme) of planning permission ZC23/02034/FULMAJ Full planning application for the demolition of existing buildings and erection of thirteen dwellings realigned access onto Trinity Lane, and associated parking and landscaping

    Decided Conditions Demolition 24 docs
  • North Yorkshire Timber Company Limited Trinity Lane Ripon North Yorkshire HG4 2AL

    26/00392/DISCON Submitted 26 Jan 2026 50m away

    Approval of details under condition 14 (Energy statement) condition 17 (landscaping scheme) condition 18 (external wall and roof materials) and condition 19 (sound insulation scheme) of planning permission ZC23/02034/FULMAJ Full planning application for the demolition of existing buildings and erection of thirteen dwellings realigned access onto Trinity Lane, and associated parking and landscaping

    Decided Conditions Demolition 24 docs

In North Yorkshire

  • 26/01023/FUL Granted

    26 Rossett Green Lane Harrogate North Yorkshire HG2 9LH

    Demolition of existing Garage. Erection of first floor side extension, part two-storey, part single-storey rear extension, two-storey front extension, loft conversion and new detached garage with studio over. Alterations to fenestration. Widening of existing highway crossing and erection entrance gates, gate posts and railings. Widening of existing driveway.

    27 Feb 2026 Full applications
  • ZE26/00152/MFUL Granted

    Land At 477211 470238 York Road Malton North Yorkshire

    Erection of factory and energy centre with all associated works

    23 Feb 2026 Full applications
  • ZD25/00633/FULL Granted

    Greystones Market Place Middleham Leyburn North Yorkshire DL8 4NR

    Householder application for rooftop solar PV and ground mounted air source heat pump installation

    11 Nov 2025 Full applications
  • 25/04211/FUL Refused

    41 Gap Road Hunmanby Gap Filey North Yorkshire YO14 9QP

    Erection of 1 no. dwelling following demolition of existing dwelling

    28 Nov 2025 Full applications
  • ZE26/00730/MFUL Awaiting decision

    Land West Of Outgang Lane Pickering North Yorkshire

    Erection of 92 dwellings and associated infrastructure, landscaping and open space

    25 Aug 2026 Full applications