Land off Drax Power Station (PML Ltd PFA Plant), Barlow Road East, Selby, YO8 8TE
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Proposed construction of 7 no. silos, 2 no. LPG storage tanks, 1 no. bunded diesel tank with external lighting
As published by the council, reference NY/2026/0130/FUL
Application record
- Reference
- NY/2026/0130/FUL
- Category
- Full applications
- Status
- Valid
- Received
- 12 Jun 2026
- Validated
- 1 Sep 2026
- Ward
- Brayton & Barlow
- Parish
- Barlow
- Decision by
- D
- Postcode
- YO8 8TE
Timeline
Dates from the published record
-
12 Jun 2026
Received by North York Moors National Park
-
1 Sep 2026
Validated
Checked as complete and ready for consideration.
-
2 Sep 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 27 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
North York Moors National Park took a median of 57 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
18 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat happens while it is decided
The process from here
This application is with North York Moors National Park for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
Drax Power Station New Road Drax Selby North Yorkshire YO8 8PH
Removal of hedgerow notice for removal of 50 metres of hedgerow
Granted Trees 14 docs -
Drax Power Station New Road Drax Selby North Yorkshire YO8 8PH
Removal of hedgerow notice for removal of 50 metres of hedgerow
Granted Trees 14 docs -
Drax Power Station New Road Drax Selby North Yorkshire YO8 8PH
Removal of hedgerow notice for removal of 50 metres of hedgerow
Granted Trees 14 docs
Other full applications applications
In North York Moors National Park
-
26/01023/FUL Granted
26 Rossett Green Lane Harrogate North Yorkshire HG2 9LH
Demolition of existing Garage. Erection of first floor side extension, part two-storey, part single-storey rear extension, two-storey front extension, loft conversion and new detached garage with studio over. Alterations to fenestration. Widening of existing highway crossing and erection entrance gates, gate posts and railings. Widening of existing driveway.
-
ZE26/00152/MFUL Granted
Land At 477211 470238 York Road Malton North Yorkshire
Erection of factory and energy centre with all associated works
-
ZE26/00477/FUL Refused
Land At E470268 N485490 Wits End Kirkby Mills Industrial Estate Kirkbymoorside North Yorkshire
Erection of new industrial unit
-
ZD26/00422/FULL Granted
Ulshaw Grange Middleham Leyburn North Yorkshire DL8 4PU
Full planning permission for outdoor swimming pool and pool room
-
26/03448/FUL Granted
3 Ure Bank Terrace Ripon North Yorkshire HG4 1JG
Loft conversion including the installation of side and rear rooflights and a new window opening within the front gable elevation.