Proposal
Hybrid planning application (full and outline elements) with Environmental Statement for the expansion of Bristol Airport to enable a throughput of 15 million passengers per annum, operating within a rolling 12 month cap of 99,931 air transport movements and 4,974 night flights between the hours of 23:30 and 06:00. Full application elements comprising: extension of western apron for additional aircraft stands; reconfiguration of central and eastern aprons; construction of a passenger surface level car park for approximately 2,000 vehicles; eastern extension of existing runway by approximately 170m, with repositioned and additional aircraft approach lighting within Felton Common; taxiway and fillet widening to Taxiway GOLF with a realignment at the western runway end; construction of two new taxiways; extension of surface level car rental parking area; expansion of existing Silver Zone car park to provide an additional circa 1,960 block parked vehicle spaces; construction of new surface level staff car park for approximately 1,720 vehicles; highway improvements to the A38, including upgrades to northern access roundabout, construction of a new southern roundabout and widening of the road to accommodate an additional bus lane with dedicated access onto the A38. Outline application elements comprising of 3no. extensions to terminal building on west, north and east sides; construction of new piers to the west and east of the terminal including an underground walkway; construction of ancillary support buildings; relocated and expanded aviation fuel farm; a pedestrian bridge link; erection of a new baggage building; erection of a maintenance repair and overhaul hangar and ground run up pen; construction of parking decks within Silver Zone car park and car rental facility; minor works within Silver Zone car park; construction of a bus maintenance and washing facility; site wide landscaping, drainage, lighting and other associated infrastructure.
As published by the council, reference 26/P/0686/OU2
Application record
- Reference
- 26/P/0686/OU2
- Type
- Outline planning permission and EIA
- Status
- Registered
- Received
- 26 Mar 2026
- Validated
- 20 Apr 2026
- Ward
- Wrington
- Parish
- Wrington
- Postcode
- BS48 3DY
Site history
Applications at this address on the North Somerset register
This site has had 10 applications since 2023.
-
26/P/1726/AIN Decided
Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for the installation of five containers and reconfiguration of the existing Service Yard. THIS IS NOT A PLANNING APPLICATION.
-
26/P/1705/AIN Decided
Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for the installation of a canopy structure over the existing terminal forecourt on the north side of Bristol Airport. THIS IS NOT A PLANNING APPLICATION
-
26/P/1544/AIN Decided
Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for a small Coffee Kiosk adjacent to the Silver Zone Car Park Reception building. THIS IS NOT A PLANNING APPLICATION.
-
26/P/1012/AIN Decided
Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for emergency water supply tanks THIS IS NOT A PLANNING APPLICATION.
-
25/P/2384/AIN Decided
Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for the proposed installation of a bus wash facility within the existing bus holding yard on the southside of Bristol Airport. THIS IS NOT A PLANNING APPLICATION.
-
25/P/2226/AIN Decided
Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for the proposed construction of an energy centre to heat/cool the terminal building. THIS IS NOT A PLANNING APPLICATION.
-
25/P/2099/AIN Decided
Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for the proposed installation of new lighting columns within an existing area of the Silver Zone block parking area. THIS IS NOT A PLANNING APPLICATION.
-
23/P/0766/AIN Decided
Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for a proposed new intake electricity substation. THIS IS NOT A PLANNING APPLICATION
-
23/P/0369/AIN Decided
Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for proposed new cabins, toilet facility and smoking shelter, plus relocation of existing cabin and container, all to be located to an area east of the main terminal. THIS IS NOT A PLANNING APPLICATION
Timeline
Dates from the published record
-
26 Mar 2026
Received by North Somerset
-
20 Apr 2026
Validated
Checked as complete and ready for consideration.
-
26 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 15 June 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
North Somerset took a median of 55 days over the applications it decided in the last year.
Who's behind it
Company information only, from the register and Companies House
WSP UK Limited Agent, registered in London
Active · incorporated 1978 · London
67 applications on PlanIndex · across 34 councils · 86% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordBristol Airport Ltd Applicant, registered in Bristol
Active · incorporated 1986 · Bristol
7 applications on PlanIndex · across 2 councils
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
602 documents on file for this application
- CITY OF BRISTOL COLLEGE
- ENVIRONMENTAL LAW FOUNDATION
- KINGSTON SEYMOUR PARISH COUNCIL
- SOUTH GLOUCESTERSHIRE COUNCIL
- BARROW GURNEY PARISH COUNCIL
- OBJECTION COMMENT
- SAVE FELTON COMMON RESPONSE 3
- ENVIRONMENT AGENCY COMMENTS
- ENVIRONMENT AGENCY
- SAVE FELTON COMMON RESPONSE 2
- BRISTOL AIRPORT ACTION NETWORK (BAAN)
- BAAN EXPERT REPORT: LEGAL
- BAAN: AIR QUALITY REPORT
- BAAN: SAFETY REPORT
- BAAN: TRANSPORT REPORT
- BAAN: SURVEY OF LOCAL RESIDENTS RE: BRISTOL AIRPORT
- PETITION - RECEIVED 25 JUNE 2026
- NATURAL ENGLAND
- NATURAL ENGLAND - ANNEX A
- MENDIP HILLS NATIONAL LANDSCAPE
- BARROW GURNEY PARISH COUNCIL COMMENTS
- CPRE AVON & BRISTOL COMMENTS
- AVON WILDLIFE TRUST
- PARISH COUNCIL?S AIRPORT ASSOCIATION
- VULCAN ASSOCIATES LTD
- VULCAN ASSOCIATES LTD - ATTACHMENT 1
- VULCAN ASSOCIATES LTD - ATTACHMENT 2
- VULCAN ASSOCIATES LTD - ATTACHMENT 3
- TIMSBURY PARISH COUNCIL
- NAILSEA TOWN COUNCIL COMMENTS
- NATIONAL HIGHWAYS COMMENTS
- BRISTOL CITY COUNCIL COMMENTS
- OBJECTION LETTER
- CAMPAIGN FOR THE PROTECTION OF RURAL ENGLAND
- WESTERN GATEWAY SUB-NATIONAL TRANSPORT BODY
- BACKWELL PARISH COUNCIL
- SOMERSET COUNCIL
- COMPTON MARTIN PARISH COUNCIL
- SAVE FELTON COMMON
- SAVE FELTON COMMON - APPENDIX A - ECOLOGICAL PLANNING REPORT
- BRISTOL CITY COUNCIL
- OBJECTION LETTER
- BARROW GURNEY PARISH COUNCIL
- AVON AND SOMERSET POLICE
- NATURAL RESOURCES WALES
- BUTCOMBE PARISH COUNCIL
- FLAX BOURTON PARISH COUNCIL
- UKINBOUND
- BATH AND NORTH EAST SOMERSET COUNCIL
- WRINGTON PARISH COUNCIL
- NORTH SOMERSET LOCAL ACCESS FORUM
- ANCIENT MONUMENTS - HISTORIC ENGLAND SOUTH WEST (DORSET AND SOMERSET)
- BATH & NE SOMERSET COUNCIL
- DUNDRY PARISH COUNCIL
- BROCKLEY PARISH COUNCIL
- CLEEVE PARISH COUNCIL
- WINFORD PARISH COUNCIL - PART 1
- WINFORD PARISH COUNCIL - PART 2
- WINFORD PARISH COUNCIL - APPENDIX A - RH_ ECOLOGICAL PLANNING REPORT_JUNE 2026
- PUBLIC OBJECTION
- EAST HARPTREE PARISH COUNCIL
- BRISTOL WATER
- GARDENS TRUST
- NEMPNETT THRUBWELL PARISH COUNCIL
- OBJECTION LETTER
- VISIT WEST
- PUBLOW WITH PENSFORD PC
- OBJECTION LETTER 08/06/26
- CHEW MAGNA PARISH COUNCIL
- CHURCHILL PARISH COUNCIL
- CHEW MAGNA PARISH COUNCIL
- HEP CALCULATION - GREATER HORSESHOE OPTION 1 V2
- HEP CALCULATION - GREATER HORSESHOE OPTION 2 V2
- HEP CALCULATION - GREATER HORSESHOE OPTION 3 V2
- HEP CALCULATION - GREATER HORSESHOE OPTION 4 V2
- HEP CALCULATION - LESSER HORSESHOE OPTION 1 V2
- HEP CALCULATION - LESSER HORSESHOE OPTION 2 V2
- HEP CALCULATION - LESSER HORSESHOE OPTION 3 V2
- HEP CALCULATION - LESSER HORSESHOE OPTION 4 V2
- PUXTON PARISH COUNCIL
- CORSTON PARISH COUNCIL
- BRISTOL BUSINESS IMPROVEMENT DISTRICT
- SALTFORD PC COMMENTS
- STOWEY SUTTON PC
- EPIC
- MOD - DEFENCE INFRASTRUCTURE ORGANISATION (DIO) SAFEGUARDING TEAM
- KENN PARISH COUNCIL COMMENTS
- OBJECTION LETTER 20/5/26
- ACTIVE TRAVEL ENGLAND
- BANWELL PARISH COUNCIL
- PILL AND EASTON GORDANO PARISH COUNCIL COMMENTS 19.5.26
- OFFICE FOR NUCLEAR REGULATION
- NETWORK RAIL COMMENTS
- OBJECTION LETTER 13/05/26
- YATTON PARISH COUNCIL COMMENTS
- ES VOL III - APPENDIX - 8.1 PART 3 APPENDIX E (I)
- ES VOL III - APPENDIX - 8.1 PART 3 APPENDIX E (II)
- ES VOL III - APPENDIX - 8.1 PART 3 APPENDIX E (III)
- ES VOL III - APPENDIX - 8.1 PART 3 APPENDIX E (IVI)
- BRISTOL TREE FORUM - CONSOLIDATED COMMENTS
- BRISTOL PORT COMPANY
- SPORT ENGLAND
- NATS
- BRISTOL TREE FORUM - PRELIMINARY COMMENTS ? 27 APRIL 2026
- BRISTOL TREE FORUM - EMAIL 27/4/26
- SOMERSET CHAMBER OF COMMERCE
- UK HEALTH SECURITY AGENCY
- DEMAND FORECASTS - CORE CASE ENVIRONMENTAL OUTPUTS
- DEMAND FORECASTS - FASTER CASE ENVIRONMENTAL OUTPUTS
- DEMAND FORECASTS -SLOWER CASE ENVIRONMENTAL OUTPUTS
- THE COAL AUTHORITY COMMENTS
- PRESS ADVERT FOR 29/04/26
- PRESS ADVERT FOR 30/04/26
- BIODIVERSITY NET GAIN METRIC CALCULATION TOOL
- PROPOSED APPROACH LIGHTING SYSTEM STANDARD DETAILS
- EXISTING SITE PLANS - APPLICATION SITE DETAILED ZONES
- EXISTING SITE PLAN - APPLICATION SITE DETAILED ZONES 1-10
- OVERALL PROPOSED GENERAL ARRANGEMENT
- OVERALL PROPOSED GENERAL ARRANGEMENT KEY PLAN
- PROPOSED APRON WORKS SHEET 1
- PROPOSED APRON WORKS SHEET 2
- PROPOSED APRON WORKS SHEET 3
- PROPOSED APRON WORKS SHEET 4
- PROPOSED APRON WORKS SHEET 5
- PROPOSED APRON WORKS SHEET 6
- PROPOSED APRON WORKS SHEET 7
- PROPOSED APRON WORKS SHEET 8
- PROPOSED TAXIWAY WORKS SHEET 9
- PROPOSED TAXIWAY WORKS SHEET 10
- PROPOSED TAXIWAY WORKS SHEET 11
- PROPOSED TAXIWAY WORKS SHEET 12
- PROPOSED HANGAR B20 SHEET 13
- PROPOSED HANGAR B20 SHEET 14
- PROPOSED GROUND LEVELS - KEY PLAN
- PROPOSED GROUND LEVELS SHEET 1
- PROPOSED GROUND LEVELS SHEET 2
- PROPOSED GROUND LEVELS SHEET 3
- PROPOSED GROUND LEVELS SHEET 4
- PROPOSED GROUND LEVELS SHEET 5
- PROPOSED GROUND LEVELS SHEET 6
- PROPOSED GROUND LEVELS SHEET 7
- PROPOSED GROUND LEVELS SHEET 8
- PROPOSED GROUND LEVELS SHEET 9
- PROPOSED GROUND LEVELS SHEET 10
- PROPOSED GROUND LEVELS SHEET 11
- PROPOSED GROUND LEVELS SHEET 12
- PROPOSED GROUND LEVELS SHEET 13
- PROPOSED GROUND LEVELS SHEET 14
- RUNWAY 27 PROPOSED APPROACH LIGHTING SYSTEM
- RUNWAY 27 PROPOSED APPROACH LIGHTING SYSTEM STANDARD DETAILS
- ENGINE RUN UP BAY STANDARD DETAILS
- BUILDING B2 B4, B6, B29 AND B30 - GROUND FLOOR PLAN
- BUILDING B2 B4, B6, B29 AND B30 - FIRST FLOOR PLAN
- BUILDING B2 B4, B6, B29 AND B30 - SECOND FLOOR PLAN
- BUILDING B2 B4, B6, B29 AND B30 - ELEVATIONS
- BUILDING B2 B4, B6, B29 AND B30 - SECTIONS
- BUILDING B2 B4, B6, B29 AND B30 - 3D VIEW
- BUILDING B3 AND B30 - GROUND FLOOR PLAN
- BUILDING B3 AND B30 - FIRST FLOOR PLAN
- BUILDING B3 AND B30 - ELEVATIONS
- BUILDING B3 AND B30 - SECTIONS
- BUILDING B3 AND B30 - 3D VIEW
- BUILDING B7 - GROUND FLOOR PLAN
- BUILDING B7 - ELEVATIONS
- BUILDING B7 - 3D VIEWS
- BUILDING B9 - SITE PLAN
- BUILDING B9 - FLOOR PLANS
- BUILDING B9 - ELEVATIONS
- BUILDING B9 - SECTIONS
- BUILDING B9 - 3D VIEWS
- BUILDING B11 - GROUND FLOOR PLAN
- BUILDING B11 - TUNNEL, FIRST FLOOR AND ROOF FLOOR PLAN
- BUILDING B11 - ELEVATIONS
- BUILDING B11 - SECTIONS
- BUILDING B11 - 3D VIEWS
- BUILDING B12 - GROUND FLOOR PLAN
- BUILDING B12 - FIRST FLOOR PLAN
- BUILDING B12 - TUNNEL PLAN
- BUILDING B12 - ROOF PLAN
- BUILDING B12 - ELEVATIONS
- BUILDING B12 - SECTIONS
- BUILDING B12 - 3D VIEWS
- BUILDING B13 - FLOOR PLANS
- BUILDING B13 - ELEVATIONS
- BUILDING B13 - 3D VIEWS
- BUILDING B17 - GROUND FLOOR PLAN
- BUILDING B17 - FIRST AND SECOND FLOOR PLAN
- BUILDING B17 - ELEVATIONS
- BUILDING B17 - SECTIONS
- BUILDING B17 - 3D VIEWS
- BUILDING B20 - 3D VIEWS
- BUILDING B20 - SECTIONS
- BUILDING B20 - ELEVATIONS
- BUILDING B20 - ROOF PLANS
- BUILDING B20 - MEZZANINE FLOOR PLAN
- BUILDING B20 - GROUND FLOOR PLAN
- BUILDING B20 - GROUND FLOOR AND ROOF PLANS
- BUILDING B21 - ELEVATIONS
- BUILDING B21 - SECTIONS
- BUILDING B21 - 3D VIEWS
- BUILDING B23 - 3D VIEWS
- BUILDING B23 - SECTIONS
- BUILDING B23 - ELEVATIONS
- BUILDING B23 - TUNNEL, FIRST FLOOR AND ROOF PLANS
- BUILDING B23 - GROUND FLOOR PLAN
- BUILDING B24 - GROUND FLOOR PLAN
- BUILDING B24 - FIRST FLOOR AND ROOF PLAN
- BUILDING B24 - ELEVATIONS
- BUILDING B24 - SECTIONS
- BUILDING B24 - 3D VIEWS
- BUILDING B31 - 3D VIEWS
- BUILDING B31 - SECTIONS
- BUILDING B31 - ELEVATIONS
- BUILDING B31 - GROUND AND MEZZANINE FLOOR PLANS
- BUILDING B32 - FLOOR PLANS
- BUILDING B32 - ELEVATIONS
- BUILDING B32 - SECTIONS
- BUILDING B32 - 3D VIEWS
- SITE LOCATION PLAN
- PROPOSED SITE PLAN
- PROPOSED OPERATIONAL BOUNDARY
- PROPOSED FENCING PLAN
- PROPOSED TERMINAL BASEMENT FLOOR PLAN
- PROPOSED TERMINAL GROUND FLOOR PLAN
- PROPOSED TERMINAL APRON LEVEL FLOOR PLAN
- PROPOSED TERMINAL MEZZANINE LEVEL FLOOR PLAN
- PROPOSED SITE SECTION A-A
- PROPOSED SITE SECTION A-A
- PROPOSED SITE SECTION B-B
- PROPOSED SITE SECTION C-C
- PROPOSED SITE SECTION D-D
- MASTERPLAN LANDSCAPE LAYOUT
- DRAFT PLANTING STRATEGY PLAN
- COOKS FARM - GENERAL ARRANGEMENT SHEET 1 OF 5
- COOKS FARM - GENERAL ARRANGEMENT SHEET 2 OF 5
- COOKS FARM - GENERAL ARRANGEMENT SHEET 3 OF 5
- COOKS FARM - GENERAL ARRANGEMENT SHEET 4 OF 5
- COOKS FARM - GENERAL ARRANGEMENT SHEET 5 OF 5
- COOKS FARM - LEVELS & CONTOURS SHEET 1 OF 5
- COOKS FARM - LEVELS & CONTOURS SHEET 2 OF 5
- COOKS FARM - LEVELS & CONTOURS SHEET 3 OF 5
- COOKS FARM - LEVELS & CONTOURS SHEET 4 OF 5
- COOKS FARM - LEVELS & CONTOURS SHEET 5 OF 5
- COOKS FARM - SURFACE FINISHES SHEET 1 OF 5
- COOKS FARM - SURFACE FINISHES SHEET 2 OF 5
- COOKS FARM - SURFACE FINISHES SHEET 3 OF 5
- COOKS FARM - SURFACE FINISHES SHEET 4 OF 5
- COOKS FARM - SURFACE FINISHES SHEET 5 OF 5
- COOKS FARM - KERBING SHEET 1 OF 5
- COOKS FARM - KERBING SHEET 2 OF 5
- COOKS FARM - KERBING SHEET 3 OF 5
- COOKS FARM - KERBING SHEET 4 OF 5
- COOKS FARM - KERBING SHEET 5 OF 5
- COOKS FARM - VEHICLE SWEPT PATH ANALYSIS COOKS FARM ROUNDABOUT
- COOKS FARM - VEHICLE SWEPT PATH ANALYSIS AIRSIDE ACCESS GATE
- COOKS FARM - VEHICLE SWEPT PATH ANALYSIS AIRSIDE BUS TO MOTOR TRANSPORT
- COOKS FARM - VEHICLE SWEPT PATH ANALYSIS MLA 16.5M SHEET 1 OF 5
- COOKS FARM - VEHICLE SWEPT PATH ANALYSIS MLA 16.5M SHEET 2 OF 5
- COOKS FARM - VEHICLE SWEPT PATH ANALYSIS MLA 16.5M SHEET 3 OF 5
- COOKS FARM - VEHICLE SWEPT PATH ANALYSIS MLA 16.5M SHEET 4 OF 5
- COOKS FARM - VEHICLE SWEPT PATH ANALYSIS MLA 16.5M SHEET 5 OF 5
- COOKS FARM - ROAD LONGITUDINAL SECTIONS SHEET 1 OF 7
- COOKS FARM - ROAD LONGITUDINAL SECTIONS SHEET 2 OF 7
- COOKS FARM - ROAD LONGITUDINAL SECTIONS SHEET 3 OF 7
- COOKS FARM - ROAD LONGITUDINAL SECTIONS SHEET 4 OF 7
- COOKS FARM - ROAD LONGITUDINAL SECTIONS SHEET 5 OF 7
- COOKS FARM - ROAD LONGITUDINAL SECTIONS SHEET 6 OF 7
- COOKS FARM - ROAD LONGITUDINAL SECTIONS SHEET 7 OF 7
- COOKS FARM - ROAD CROSS SECTIONS SHEET 1 OF 4
- COOKS FARM - ROAD CROSS SECTIONS SHEET 2 OF 4
- COOKS FARM - ROAD CROSS SECTIONS SHEET 3 OF 4
- COOKS FARM - ROAD CROSS SECTIONS SHEET 4 OF 4
- COOKS FARM - VEHICLE SWEPT PATH ANALYSIS SERVICE YARD IN
- COOKS FARM - VEHICLE SWEPT PATH ANALYSIS SERVICE YARD OUT
- COOKS FARM - DRAINAGE LAYOUT SHEET 1 OF 5
- COOKS FARM - DRAINAGE LAYOUT SHEET 2 OF 5
- COOKS FARM - DRAINAGE LAYOUT SHEET 3 OF 5
- COOKS FARM - DRAINAGE LAYOUT SHEET 4 OF 5
- COOKS FARM - DRAINAGE LAYOUT SHEET 5 OF 5
- SITE WIDE - DRAWING SHEET SET
- SITE WIDE - PAVEMENT CONSTRUCTION DETAILS
- SITE WIDE - KERB CONSTRUCTION DETAILS
- SITE WIDE - DRAINAGE CONSTRUCTION DETAILS SHEET 1 OF 2
- SITE WIDE - DRAINAGE CONSTRUCTION DETAILS SHEET 2 OF 2
- ES VOL I - CHAPTER 5 - BIODIVERSITY
- ES VOL I - CHAPTER 6 - AIR QUALITY AND ODOUR
- ES VOL I - CHAPTER 7 - NOISE AND VIBRATION
- ES VOL I - CHAPTER 8 - TRANSPORT AND SURFACE ACCESS
- ES VOL I - CHAPTER 9 - LANDSCAPE AND VISUAL
- ES VOL I - CHAPTER 10 - HISTORIC ENVIRONMENT
- ES VOL I - CHAPTER 11 - SOCIO-ECONOMICS
- ES VOL I - CHAPTER 12 - POPULATION AND HUMAN HEALTH
- ES VOL I - CHAPTER 13 - GREENHOUSE GASES
- ES VOL I - CHAPTER 14: MAJOR ACCIDENTS AND DISASTERS
- ES VOL I - CHAPTER 15 - LAND QUALITY
- ES VOL I - CHAPTER 16 - GROUNDWATER
- ES VOL I - CHAPTER 17 - SURFACE WATER AND FLOOD RISK
- ES VOL II - FIGS FOR CHAPTERS 1 AND 2 - 1.1, 1.2, 2.1 TO 2.5
- ES VOL II - FIGS FOR CHAPTER 5 - 5.1 TO 5.8
- ES VOL II - FIGS FOR CHAPTER 5 AND 6 - 5.9, 6.1 TO 6.15
- ES VOL II - FIGS FOR CHAPTER 7 - 7.1, 7.2
- ES VOL II - FIGS FOR CHAPTER 7 - 7.3 TO 7.8
- ES VOL II - FIGS FOR CHAPTER 7 - 7.9 TO 7.14
- ES VOL II - FIGS FOR CHAPTER 7 - 7.15 TO 7.19
- ES VOL II - FIGS FOR CHAPTER 7 & 8 - 7.20 TO 7.24, 8.1 TO 8.3
- ES VOL II - FIGS FOR CHAPTER 9 - 9.1, 9.2, 9.3
- ES VOL II - FIGS FOR CHAPTER 9 - 9.4 TO 9.6
- ES VOL II - FIGS FOR CHAPTER 9 - 9.7 TO 9.10
- ES VOL II - FIGS FOR CHAPTERS 9 & 10 - 9.11, 10.1 TO 10.2H
- ES VOL II - FIGS FOR CHAPTER 10 - 10.3 TO 10.8
- ES VOL II - FIGS FOR CHAPTERS 11, 12 AND 14 - 11.1, 12.1, 12.2, 14.1
- ES VOL II - FIGS FOR CHAPTER 15 - 15.1 TO 15.4
- ES VOL II - FIGS FOR CHAPTER 16 - 16.1 TO 16.4
- ES VOL II - FIGS FOR CHAPTER 16 & 17 - 16.5, 17.1, 17.2
- ES VOL III - APPS - CHAPTER 5 - 5.12, 5.13
- ES VOL III - APPENDIX 9.5 PART 1
- ES VOL III - APPENDIX 9.5 PART 2
- ES VOL III - APPENDIX 9.5 PART 3
- ES VOL III - APPENDIX 9.5 PART 4
- ES VOL III - APPENDIX 9.5 PART 5
- ES VOL III - APPENDIX 9.5 PART 6
- ES VOL III - APPENDIX 9.5 PART 7
- ES VOL III - APPENDIX 9.5 PART 8
- ES VOL III - APPENDIX 9.5 PART 9
- ES VOL III - APPENDIX 9.5 PART 10
- NORTHERN CAR PARK - GENERAL ARRANGEMENT SHEET 4 OF 5
- ES VOL III - APPENDIX 9.5 PART 11
- ES VOL III - APPENDIX 9.5 PART 12
- ES VOL III - APPENDIX 9.5 PART 13
- ES VOL III - APPENDIX 9.5 PART 14
- ES VOL III - APPENDIX 9.5 PART 15
- NORTHERN CAR PARK - GENERAL ARRANGEMENT SHEET 5 OF 5
- ES VOL III - APPENDIX 9.6
- ES VOL III - APPENDICES 10.1 TO 10.6
- NORTHERN CAR PARK - LEVELS & CONTOURS SHEET 4 OF 5
- ES VOL III - APPENDIX 11.1
- ES VOL III - APPENDIX 12.1
- NORTHERN CAR PARK - LEVELS & CONTOURS SHEET 5 OF 5
- ES VOL III - APPENDIX 13.1 TO 13.5
- ES VOL III - APPENDICES - 14.1 TO 14.3
- NORTHERN CAR PARK - SURFACE FINISHES SHEET 4 OF 5
- NORTHERN CAR PARK - SURFACE FINISHES SHEET 5 OF 5
- ES VOL III - APPENDIX - 15.1 PART 1
- ES VOL III - APPENDIX - 15.1 PART 2
- ES VOL III - APPENDIX - 15.1 PART 3
- ES VOL III - APPENDICES - 15.2 AND 15.3
- NORTHERN CAR PARK - KERBING SHEET 4 OF 5
- ES VOL III - APPENDIX - 17.1
- NORTHERN CAR PARK - KERBING SHEET 5 OF 5
- NORTHERN CAR PARK - VEHICLE SWEPT PATH ANALYSIS - MLA (16.5M)
- NORTHERN CAR PARK - VEHICLE SWEPT PATH ANALYSIS - WRIGHTBUS STREETCAR
- NORTHERN CAR PARK - DRAINAGE LAYOUT SHEET 4 OF 5
- NORTHERN CAR PARK - DRAINAGE LAYOUT SHEET 5 OF 5
- ES VOL III - APPENDIX - 17.2 PART 1
- ES VOL III - APPENDIX - 17.2 PART 2
- NORTHERN CAR PARK - ROAD LONGITUDINAL SECTIONS - SHEET 1 OF 4
- ES VOL III - APPENDIX - 17.2 PART 3
- ES VOL III - APPENDIX - 17.2 PART 4
- ES VOL III - APPENDIX - 17.2 PART 5
- NORTHERN CAR PARK - ROAD LONGITUDINAL SECTIONS - SHEET 2 OF 4
- ES VOL III - APPENDIX - 17.2 PART 6
- ES VOL III - APPENDIX - 17.2 PART 7
- NORTHERN CAR PARK - ROAD LONGITUDINAL SECTIONS - SHEET 3 OF 4
- NORTHERN CAR PARK - ROAD LONGITUDINAL SECTIONS - SHEET 4 OF 4
- ES VOL III - APPENDICES - 17.3, 17.4, 17.5
- NORTHERN CAR PARK - ROAD CROSS SECTIONS - SHEET 1 OF 2
- NORTHERN CAR PARK - ROAD CROSS SECTIONS - SHEET 2 OF 2
- ES VOL III - APPENDICES - 5.1, 5.2, 5.3
- ES VOL III - APPENDICES - 5.4, 5.5, 5.6
- ES VOL III - APPENDIX - 5.7 PART 1
- ES VOL III - APPENDIX - 5.7 PART 2
- ES VOL III - APPENDIX - 5.8 PART 1
- ES VOL III - APPENDIX - 5.8 PART 2
- ES VOL III - APPENDIX - 5.8 PART 3
- ES VOL III - APPENDIX - 5.8 PART 4
- ES VOL III - APPENDIX - 5.8 PART 5
- ES VOL III - APPENDIX - 5.8 PART 6
- ES VOL III - APPENDIX - 5.9 PART 1
- ES VOL III - APPENDIX - 5.9 PART 2
- ES VOL III - APPENDIX - 5.14 PART 1
- ES VOL III - APPENDIX - 5.14 PART 2
- ES VOL III - APPENDIX - 5.14 PART 3
- ES VOL III - APPENDIX - 5.14 PART 4
- ES VOL III - APPENDIX - 5.14 PART 5
- ES VOL III - APPENDIX - 5.14 PART 6
- ES VOL III - APPENDIX - 5.14 PART 7
- ES VOL III - APPENDIX - 5.14 PART 8
- ES VOL III - APPENDIX - 5.14 PART 9
- ES VOL III - APPENDIX - 5.14 PART 10
- ES VOL III - APPENDICES - 5.15, 5.16, 5.17
- ES VOL III - APPENDICES FOR CHAPTER 6
- ES VOL III - APPENDIX - 7.1
- ES VOL III - APPENDIX - 7.2 PART 1
- ES VOL III - APPENDIX - 7.2 PART 2
- ES VOL III - APPENDIX - 7.2 PART 3
- ES VOL III - APPENDIX - 7.2 PART 4
- ES VOL III - APPENDIX - 7.2 PART 5
- ES VOL III - APPENDIX - 7.2 PART 6
- ES VOL III - APPENDIX - 7.2 PART 7
- ES VOL III - APPENDIX - 7.2 PART 8
- ES VOL III - APPENDIX - 7.2 PART 9
- ES VOL III - APPENDIX - 7.2 PART 10
- ES VOL III - APPENDIX - 7.2 PART 11
- ES VOL III - APPENDIX - 7.2 PART 12
- ES VOL III - APPENDIX - 7.2 PART 13
- ES VOL III - APPENDIX - 7.2 PART 14
- ES VOL III - APPENDIX - 7.2 PART 15
- ES VOL III - APPENDIX - 7.2 PART 16
- ES VOL III - APPENDIX - 7.2 PART 17
- ES VOL III - APPENDIX - 8.1 PART 1
- ES VOL III - APPENDIX - 8.1 PART 2
- ES VOL III - APPENDIX - 8.1 PART 3
- ES VOL III - APPENDIX - 8.1 PART 4
- ES VOL III - APPENDIX - 8.2
- NON-TECHNICAL SUMMARY
- CONSTRUCTION TRAFFIC MANAGEMENT PLAN
- WORKPLACE TRAVEL PLAN
- SKILLS AND EMPLOYMENT PLAN
- DRAFT SURFACE ACCESS STRATEGY
- BREEAM NEW CONSTRUCTION V7: PRE-ASSESSMENT REPORT
- GREEN BELT ASSESSMENT
- CONSULTATION REPORT
- ECOLOGICAL CHECKLIST
- CIL ADDITIONAL INFO FORM 1
- OUTLINE CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
- PROVISION OF ROAD RESTRAINT SYSTEMS ON LOCAL AUTHORITY ROADS ASSESSMENT
- DEMAND FORECASTS TO INFORM THE PROPOSED DEVELOPMENT TO 15 MPPA
- SOCIO-ECONOMIC IMPACT ASSESSMENT
- A38 - GENERAL ARRANGEMENT SHEET 1 OF 4
- A38 - GENERAL ARRANGEMENT SHEET 2 OF 4
- A38 - GENERAL ARRANGEMENT SHEET 3 OF 4
- A38 - GENERAL ARRANGEMENT SHEET 4 OF 4
- A38 - LEVELS & CONTOUR SHEET 1 OF 4
- A38 - LEVELS & CONTOUR SHEET 2 OF 4
- A38 - LEVELS & CONTOUR SHEET 3 OF 4
- A38 - LEVELS & CONTOUR SHEET 4 OF 4
- A38 - SURFACE FINISHES SHEET 1 OF 4.
- A38 - SURFACE FINISHES SHEET 2 OF 4.
- A38 - SURFACE FINISHES SHEET 3 OF 4.
- A38 - SURFACE FINISHES SHEET 4 OF 4.
- A38 - KERBING SHEET 1 OF 4
- A38 - KERBING SHEET 2 OF 4
- A38 - KERBING SHEET 3 OF 4
- A38 - KERBING SHEET 4 OF 4
- A38 - DRAINAGE LAYOUT SHEET 1 OF 4
- A38 - DRAINAGE LAYOUT SHEET 2 OF 4
- A38 - DRAINAGE LAYOUT SHEET 3 OF 4
- A38 - DRAINAGE LAYOUT SHEET 4 OF 4
- A38 - TRAFFIC SIGNS ROAD MARKINGS SHEET 1 OF 4
- A38 - TRAFFIC SIGNS ROAD MARKINGS SHEET 2 OF 4
- A38 - TRAFFIC SIGNS ROAD MARKINGS SHEET 3 OF 4
- A38 - TRAFFIC SIGNS ROAD MARKINGS SHEET 4 OF 4
- A38 - VEHICLE SWEPT PATH-MLA 16.5M SHEET 1 OF 8
- A38 - VEHICLE SWEPT PATH-MLA 16.5M SHEET 2 OF 8
- A38 - VEHICLE SWEPT PATH-MLA 16.5M SHEET 3 OF 8
- A38 - VEHICLE SWEPT PATH-MLA 16.5M SHEET 4 OF 8
- A38 - VEHICLE SWEPT PATH-MLA 16.5M SHEET 5 OF 8
- A38 - VEHICLE SWEPT PATH-MLA 16.5M SHEET 6 OF 8
- A38 - VEHICLE SWEPT PATH-MLA 16.5M SHEET 7 OF 8
- A38 - VEHICLE SWEPT PATH-MLA 16.5M SHEET 8 OF 8
- A38 - VEHICLE SWEPT PATH - WRIGHTBUS SHEET 1 OF 3
- A38 - VEHICLE SWEPT PATH - WRIGHTBUS SHEET 2 OF 3
- A38 - VEHICLE SWEPT PATH - WRIGHTBUS SHEET 3 OF 3
- A38 - ROAD LONGITUDINAL SECTIONS SHEET 1 OF 4.
- A38 - ROAD LONGITUDINAL SECTIONS SHEET 2 OF 4
- A38 - ROAD LONGITUDINAL SECTIONS SHEET 3 OF 4
- A38 - ROAD LONGITUDINAL SECTIONS SHEET 4 OF 4
- A38 - ROAD CROSS SECTIONS SHEET 1 OF 4
- A38 - ROAD CROSS SECTIONS SHEET 2 OF 4
- A38 - ROAD CROSS SECTIONS SHEET 3 OF 4
- A38 - ROAD CROSS SECTIONS SHEET 4 OF 4
- A38 -VEHICLE SWEPT PATH ANALYSIS -SPRINTER VAN
- A38 - TRAFFIC SIGNAL LAYOUT SHEET 1 OF 2
- A38 - TRAFFIC SIGNAL LAYOUT SHEET 2 OF 2
- STAFF PARKING & HIRE CAR - GENERAL ARRANGEMENT SHEET 1 OF 3
- STAFF PARKING & HIRE CAR - GENERAL ARRANGEMENT SHEET 2 OF 3
- STAFF PARKING & HIRE CAR - GENERAL ARRANGEMENT SHEET 3 OF 3
- STAFF PARKING & HIRE CAR - LEVELS & CONTOUR SHEET 1 OF 3
- STAFF PARKING & HIRE CAR - LEVELS & CONTOUR SHEET 2 OF 3
- STAFF PARKING & HIRE CAR - LEVELS & CONTOUR SHEET 3 OF 3
- STAFF PARKING & HIRE CAR - SURFACE FINISHES SHEET 1 OF 3
- STAFF PARKING & HIRE CAR - SURFACE FINISHES SHEET 2 OF 3
- STAFF PARKING & HIRE CAR - SURFACE FINISHES SHEET 3 OF 3
- STAFF PARKING & HIRE CAR - KERBING SHEET 1 OF 3
- STAFF PARKING & HIRE CAR - KERBING SHEET 2 OF 3
- STAFF PARKING & HIRE CAR - KERBING SHEET 3 OF 3
- STAFF PARKING & HIRE CAR - DRAINAGE LAYOUT SHEET 1 OF 3
- STAFF PARKING & HIRE CAR - DRAINAGE LAYOUT SHEET 2 OF 3
- STAFF PARKING & HIRE CAR - DRAINAGE LAYOUT SHEET 3 OF 3
- STAFF PARKING & HIRE CAR - VEHICLE SWEPT PATHS ANALYSIS - CAR TRANSPORTER
- STAFF PARKING & HIRE CAR - VEHICLE SWEPT PATHS ANALYSIS - WRIGHT BUS SHEET 1 OF
- STAFF PARKING & HIRE CAR - VEHICLE SWEPT PATHS ANALYSIS - WRIGHT BUS SHEET 2 OF
- STAFF PARKING & HIRE CAR - ROAD LONGITUDINAL SECTIONS SHEET 1 OF 4
- STAFF PARKING & HIRE CAR - ROAD LONGITUDINAL SECTIONS SHEET 2 OF 4
- STAFF PARKING & HIRE CAR - ROAD LONGITUDINAL SECTIONS SHEET 3 OF 4
- STAFF PARKING & HIRE CAR - ROAD LONGITUDINAL SECTIONS SHEET 4 OF 4
- STAFF PARKING & HIRE CAR - ROAD CROSS SECTIONS SHEET 1 OF 4
- STAFF PARKING & HIRE CAR - ROAD CROSS SECTIONS SHEET 2 OF 4
- STAFF PARKING & HIRE CAR - ROAD CROSS SECTIONS SHEET 3 OF 4
- STAFF PARKING & HIRE CAR - ROAD CROSS SECTIONS SHEET 4 OF 4
- PART 1
- PART 2
- SILVER ZONE - GENERAL ARRANGEMENT SHEET 1 OF 8
- LIGHTING IMPACT ASSESSMENT REPORT
- SILVER ZONE - GENERAL ARRANGEMENT SHEET 2 OF 8
- SILVER ZONE - GENERAL ARRANGEMENT SHEET 3 OF 8
- LIGHTING IMPACT ASSESSMENT REPORT - APPENDIX A
- LIGHTING IMPACT ASSESSMENT REPORT - APPENDIX B
- LIGHTING IMPACT ASSESSMENT REPORT - APPENDIX C
- LIGHTING IMPACT ASSESSMENT REPORT - APPENDIX D
- LIGHTING IMPACT ASSESSMENT REPORT - APPENDIX E PART 1
- LIGHTING IMPACT ASSESSMENT REPORT - APPENDIX E PART 2
- LIGHTING IMPACT ASSESSMENT REPORT - APPENDIX E PART 3
- SILVER ZONE - GENERAL ARRANGEMENT SHEET 4 OF 8
- LIGHTING IMPACT ASSESSMENT REPORT - APPENDIX F
- SILVER ZONE - GENERAL ARRANGEMENT SHEET 5 OF 8
- SILVER ZONE - GENERAL ARRANGEMENT SHEET 6 OF 8
- SILVER ZONE - GENERAL ARRANGEMENT SHEET 7 OF 8
- PAVEMENT DESIGN REPORT
- SILVER ZONE - GENERAL ARRANGEMENT SHEET 8 OF 8
- PAVEMENT DESIGN REPORT - APPENDIX A
- PAVEMENT DESIGN REPORT - APPENDIX B
- PAVEMENT DESIGN REPORT - APPENDIX C PART 1
- PAVEMENT DESIGN REPORT - APPENDIX C PART 2
- PAVEMENT DESIGN REPORT - APPENDIX C PART 3
- PAVEMENT DESIGN REPORT - APPENDIX D
- SILVER ZONE - LEVELS & CONTOURS LAYOUT SHEET 1 OF 8
- SILVER ZONE - LEVELS & CONTOURS LAYOUT SHEET 2 OF 8
- SILVER ZONE - LEVELS & CONTOURS LAYOUT SHEET 3 OF 8
- SILVER ZONE - LEVELS & CONTOURS LAYOUT SHEET 4 OF 8
- SILVER ZONE - LEVELS & CONTOURS LAYOUT SHEET 5 OF 8
- SILVER ZONE - LEVELS & CONTOURS LAYOUT SHEET 6 OF 8
- SILVER ZONE - LEVELS & CONTOURS LAYOUT SHEET 7 OF 8
- SILVER ZONE - LEVELS & CONTOURS LAYOUT SHEET 8 OF 8
- SILVER ZONE - PROPOSED DRAINAGE LAYOUT SHEET 1 OF 8
- SILVER ZONE - PROPOSED DRAINAGE LAYOUT SHEET 2 OF 8
- ES VOL III - APPENDICES 5.10, 5.11
- SILVER ZONE - PROPOSED DRAINAGE LAYOUT SHEET 3 OF 8
- ES VOL III - APPENDICES 7.3 TO 7.8
- ES VOL III - APPENDICES 9.1 TO 9.4
- SILVER ZONE - PROPOSED DRAINAGE LAYOUT SHEET 4 OF 8
- SILVER ZONE - PROPOSED DRAINAGE LAYOUT SHEET 5 OF 8
- SILVER ZONE - PROPOSED DRAINAGE LAYOUT SHEET 6 OF 8
- SILVER ZONE - PROPOSED DRAINAGE LAYOUT SHEET 7 OF 8
- SILVER ZONE - PROPOSED DRAINAGE LAYOUT SHEET 8 OF 8
- SILVER ZONE - SURFACE FINISHES SHEET 1 OF 8
- SILVER ZONE - SURFACE FINISHES SHEET 2 OF 8
- APPLICATIONFORMREDACTED
- SILVER ZONE - SURFACE FINISHES SHEET 3 OF 8
- SILVER ZONE - SURFACE FINISHES SHEET 4 OF 8
- SILVER ZONE - SURFACE FINISHES SHEET 5 OF 8
- SILVER ZONE - SURFACE FINISHES SHEET 6 OF 8
- SILVER ZONE - SURFACE FINISHES SHEET 7 OF 8
- SILVER ZONE - SURFACE FINISHES SHEET 8 OF 8
- SILVER ZONE - KERBING SHEET 1 OF 8
- SILVER ZONE - KERBING SHEET 2 OF 8
- SILVER ZONE - KERBING SHEET 3 OF 8
- SILVER ZONE - KERBING SHEET 4 OF 8
- SILVER ZONE - KERBING SHEET 5 OF 8
- SILVER ZONE - KERBING SHEET 6 OF 8
- SILVER ZONE - KERBING SHEET 7 OF 8
- SILVER ZONE - KERBING SHEET 8 OF 8
- SILVER ZONE - VEHICLE SWEPT PATHS ANALYSIS -MLA 16.5M
- SILVER ZONE - VEHICLE SWEPT PATHS ANALYSIS - WRIGHTBUS SHEET 1 OF 2
- SILVER ZONE - VEHICLE SWEPT PATHS ANALYSIS - WRIGHTBUS SHEET 2 OF 2
- SILVER ZONE - ROAD LONGITUDINAL SECTIONS SHEET 1 OF 2
- SILVER ZONE - ROAD LONGITUDINAL SECTIONS SHEET 2 OF 2
- SILVER ZONE - ROAD CROSS SECTIONS SHEET 1 OF 1
- FUEL FARM CONCEPT LAYOUT
- ES VOL II - FIGS FOR CHAPTER 9 - 9.1, 9.2, 9.3
- ES VOL I - CHAPTERS 1 TO 4
- ES VOL III - APPENDICES FOR CHAPTERS 1 TO 4
- FUEL FARM BASIS OF SAFETY REPORT
- FUEL FARM DRAINAGE PHILOSOPHY
- FUEL FARM DRAINAGE PHILOSOPHY - APPENDIX 1 SHEET 1
- FUEL FARM DRAINAGE PHILOSOPHY - APPENDIX 1 SHEET 2
- FUEL FARM DRAINAGE PHILOSOPHY - APPENDIX 2 - TYPICAL DRAINAGE DETAILS
- FUEL FARM DRAINAGE PHILOSOPHY - APPENDIX 2 - ATTENUATION & DRAINAGE DETAILS
- FUEL FARM DRAINAGE PHILOSOPHY - APPENDIX 2 - INTERCEPTOR & DRAINAGE DETAILS
- FUEL FARM RIBA STAGE 3 REPORT
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.1 - PRELIMINARY FUEL STORAGE
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.2 - CONTROL ROOM LAYOUT
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.3 - ELECTRICAL ROOM LAYOUT
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.4 - EQUIPMENT LIST
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.5 - HYDRANT CONCEPT SYSTEM
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.6 - HYDRANT CONCEPT SYSTEM - SECTION
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.7 - AIRSIDE / LANDSLIDE SINGLE LINE D
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.8 - ELECTRICAL CABLE SCHEDULE
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.9 - PROJECT RISK WORKBOOK
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.10 - ANCILLARY BUILDINGS FLOOR PLAN
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.11 - AIRSIDE ANCILLARY BUILDING FLOOR
- FUEL FARM RIBA STAGE 3 REPORT - APPENDIX 5.12 - ELECTRICAL LOAD SCHEDULE
- LAND OWNERSHIP PLAN
- PROPOSED SITE SECTION E-E - PROPOSED GROUND LEVELS
- SUPPORTING INFORMATION TO THE APPLICATION FORM
- PROPOSED SITE SECTION EE PROPOSED GROUND LEVELS
- ES VOL II - FIGS FOR CHP 3 AND 4 - 3.1 TO 3.5, 4.1
- DEMAND FORECASTS - DETAILED PASSENGER OUTPUTS AND MACRO ASSUMPTIONS
- DEMAND FORECASTS - CORE CASE ENVIRONMENTAL AND PLANNING OUTPUTS - SUPERSEDED
- DEMAND FORECASTS - FASTER CASE ENVIRONMENTAL AND PLANNING OUTPUTS - SUPERSEDED
- DEMAND FORECASTS - SLOWER CASE ENVIRONMENTAL AND PLANNING OUTPUTS - SUPERSEDED
- LIST OF APPLICATION DOCUMENTS
Trade members open them from here.
Open the documentsWhat happens while it is decided
This application is with North Somerset for determination, against a statutory target of eight weeks. Over the last year North Somerset decided outline applications in a median of 57 days. More in our guide to how long planning decisions take.
About outline applications
An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
Departure Concourse Bristol Airport North Side Road Felton Wrington BS48 3DY
Two-storey slot-in extensions to the south of the existing Bristol Airport terminal at the first floor and mezzanine levels.
Granted Full applications Extension 30 docs -
Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for a small Coffee Kiosk adjacent to the Silver Zone Car Park Reception building. THIS IS NOT A PLANNING APPLICATION.
Decided 4 docs -
Departure Concourse Bristol Airport North Side Road Felton Wrington BS48 3DY
Two-storey slot-in extensions to the south of the existing Bristol Airport terminal at the first floor and mezzanine levels.
Granted Full applications Extension 30 docs -
Land At Silver Zone Car Park Bristol Airport North Side Road Felton Wrington BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for a proposed new Visual Damage Recognition (VDR) shed along with an access and egress route for vehicles. THIS IS NOT A PLANNING APPLICATION
Decided 9 docsSmall domestic -
Bristol International Airport North Side Road Felton BS48 3DY
Consultation request under the provisions of Part 8 (Class F) of The Town And Country Planning (General Permitted Development) (Amendment) (England) Order 2015 for a proposed new aircraft stand - THIS IS NOT A PLANNING APPLICATION.
Decided 6 docs -
Departure Concourse Bristol Airport North Side Road Felton Wrington BS48 3DY
Large removable vinyl advert displayed on the front of the airport terminal glass frontage. The advert would be stuck to the inside of the terminal glass, but on display to those outside of the terminal. A generic advertisement consent is sought to enable the adverts within the space to be replaced from time to time dependent on the commercial agreements in place between the Airport and companies.
Granted Advertising 8 docs
Other outline applications
In North Somerset
-
26/P/1738/OUT Awaiting decision
Heath Cottage Old Weston Road Congresbury BS49 5ED
Outline planning permission for the removal of an existing outbuilding and erection of a detached two storey dwelling, with access for approval (Appearance, landscaping, layout and scale reserved for subsequent approval)
-
26/P/0750/PIP Refused
F Sweeting And Sons Station Road Sandford Winscombe BS25 5RQ
Permission in principle for the demolition of existing industrial buildings and erection of 9no. dwellings
-
26/P/0881/CM2A Granted
Lloyds Tsb Bank Plc Combe Road Portishead BS20 6BJ
Application to determine if prior approval is required for the change of use of former bank staff room and toilets to 1no. one bedroom self contained flat
-
26/P/0256/CM2A Granted
2 North Lane Weston-super-Mare BS23 1QR
Determination as to whether Prior Approval is required for the change of use of part of property from Use Class E (g)(i) offices to 1no. dwelling (Use Class C3)
-
26/P/0930/AGA Granted
Seawall Farm Lower Strode Road Clevedon BS21 6UX