Planning application
Land At Scottow Business Park Lamas Road Scottow Norfolk
Works: Demolition
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Construction of new engine test stand, manufacturing facility, and Research and development lab including new fencing. Construction of a compound to house buildings for the manufacture and storage of energetics, including solar array and fencing. Change of use of existing buildings on site (including partial or complete demolition and rebuild where required) to uses including Class B2, B8 and Class E (g) Construction of containers for testing and storage and associated fencing. Construction of new substations, masts and associated infrastructure. Erection of palisade fencing
As published by the council, reference PF/26/1764
Application record
- Reference
- PF/26/1764
- Status
- Awaiting decision
- Received
- 18 Aug 2026
- Validated
- 3 Sep 2026
Timeline
Dates from the published record
-
18 Aug 2026
Received by North Norfolk
-
2 Sep 2026
Added to PlanIndex
-
3 Sep 2026
Validated
Checked as complete and ready for consideration.
-
11 Sep 2026
Status changed to Awaiting decision
Previously Pending Consideration.
-
Decision
Awaiting decision
Decision expected by 29 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
North Norfolk took a median of 57 days over the applications it decided in the last year.
What happens while it is decided
This application is with North Norfolk for determination, against a statutory target of eight weeks. Over the last year North Norfolk's median decision took 57 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on North Norfolk's portal will say. Our guide explains the common types.