Planning application
IP5 Celtic Way Celtic Lakes Newport South Wales NP10 8BE
Permission granted. Work must normally begin within five years of the decision or the permission lapses.
Proposal
INSTALLATION OF EXTERNAL BUILDING EXTRACT DUCTS, AIR INTAKE/EXTRACT LOUVRES, CONDENSER UNITS AND ENCLOSURES AND ASSOCIATED WORKS
As published by the council, reference 26/0458
Application record
- Reference
- 26/0458
- Status
- Decided
- Decision
- Granted with Conditions
- Received
- 17 Jun 2026
- Validated
- 17 Jul 2026
- Decided
- 10 Sep 2026
- Ward
- Tredegar Park And Marshfield
- Parish
- Coedkernew Community Council
- Postcode
- NP10 8BE
Site history
Applications at this address on the Newport register
This site has had 3 applications since 2024: 3 approved, 0 refused.
-
25/1067 Granted
IP5 Celtic Way Celtic Lakes Newport South Wales NP10 8BE
INSTALLATION OF 1NO. GENERATOR AND ASSOCIATED FLUES & WORKS
-
24/0611 Granted
IP5 Celtic Way Celtic Lakes Newport South Wales NP10 8BE
PROPOSED PARTIAL CHANGE OF USE OF BUILDING IP5 FROM B8 STORAGE TO B1 LABORATORY USE AND ANCILLARY SPACES AND ASSOCIATED MINOR EXTERNAL WORKS
Timeline
Dates from the published record
-
17 Jun 2026
Received by Newport
-
17 Jul 2026
Validated
Checked as complete and ready for consideration.
-
28 Jul 2026
Added to PlanIndex
-
10 Sep 2026
Decision issued: Granted with Conditions
-
10 Sep 2026
Status changed to Decided
Previously Awaiting decision.
What this grant of permission means
Newport granted permission on 10 September 2026, subject to any conditions on the decision notice. Work must normally begin within five years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Newport's portal will say. Our guide explains the common types.
Nearby applications
Within 500 metres
-
Celtic Technology Centre Celtic Way Celtic Lakes Newport South Wales NP10 8BE
PARTIAL DISCHARGE OF CONDITIONS 10 (SERVICE TESTING AND MAINTENANCE PLAN), 16 (EXTERNAL LIGHTING), 20 (CYCLE PARKING DETAILS), 21 (EV CHARGING), 22 (TRAVEL PLAN) AND 23 (PEDESTRIAN CROSSING AND FOOTWAY) OF 25/0711 S73 APPLICATION TO VARY CONDITIONS 1 (APPROVED PLANS), 7 (LANDSCAPING AND PLANTING SCHEME), 10 (NOISE ASSESSMENT) AND 11 (NOISE SURVEY) OF 20/0039 ERECTION OF 4NO. THREE-STOREY DATA CENTRE BUILDINGS COMPRISING B8 USE AND ANCILLARY B1 USE, PROVISION OF EMERGENCY GENERATORS, SECURITY LODGE, HARD AND SOFT LANDSCAPING, INTERNAL ACCESS ROADS, CAR PARKING AND SUSTAINABLE DRAINAGE. AMENDMENTS INCLUDE CHANGES TO BUILDING FOOTPRINTS AND DESIGN, LOCATION OF GENERATORS, CHANGES TO DRAINAGE STRATEGY AND LANDSCAPING AND OTHER LAYOUT CHANGES
Granted -
Celtic Technology Centre Celtic Way Celtic Lakes Newport South Wales NP10 8BE
NMA APPLICATION TO VARY CONDITION 2 (NOISE) OF 24/0747 CONSTRUCTION OF AN ELECTRICITY SUBSTATION COMPOUND COMPRISING TRANSFORMERS, SWITCHGEARS AND ELECTRICAL EQUIPMENT, SURFACE WATER DRAINAGE, MEANS OF ACCESS, LANDSCAPING, THE INSTALLATION OF BURIED ELECTRICITY TRANSMISSION CIRCUITS, CREATION OF A HABITAT COMPENSATION SITE AND ASSOCIATED WORKS
Granted -
IP5 Celtic Way Celtic Lakes Newport South Wales NP10 8BE
INSTALLATION OF 1NO. GENERATOR AND ASSOCIATED FLUES & WORKS
Granted -
IP5 Celtic Way Celtic Lakes Newport South Wales NP10 8BE
PROPOSED PARTIAL CHANGE OF USE OF BUILDING IP5 FROM B8 STORAGE TO B1 LABORATORY USE AND ANCILLARY SPACES AND ASSOCIATED MINOR EXTERNAL WORKS
Granted Full applications 27 docs -
Land On The West Side Of Celtic Way Celtic Lakes Newport South Wales
CONSTRUCTION OF 2NO. UNITS UNDER USE CLASS B1, B2 & B8
Granted Full applications 46 docsMajor scheme -
Quinn Radiators Celtic Way Celtic Lakes Newport NP10 8FS
80% historically approved · decision due ~19 Oct
PARTIAL DISCHARGE OF CONDITION 12 (TRAVEL PLAN) OF 26/0379 S73 APPLICATION TO VARY CONDITIONS 1 (APPROVED PLANS), 3 (LANDSCAPING), 4 (LEMP), 15 (PARKING), 16 (CYCLE STORAGE DETAILS), 17 (FOUL DRAINAGE) AND TO REMOVE CONDITION 6 (DORMICE METHOD STATEMENT) OF 24/0006 DEMOLITION OF REMAINDER OF EXISTING PRINCIPAL BUILDING AND REMAINING STRUCTURES AND CONSTRUCTION OF NEW DATA CENTRE (USE CLASS B8) ACROSS TWO MAIN BUILDINGS PLUS ANCILLARY STRUCTURES ANDS OTHER ASSOCIATED WORKS. AMENDMENTS INCLUDE CHANGES TO LAYOUT AND LANDSCAPING TO ACCOMMODATE SAB REQUIREMENTS, AMENDMENTS AND ADDITIONS TO ADMIN AND DATA HALL BUILDINGS, DESIGN AND SPECIFICATION OF GENERATORS, REVISIONS TO EXTERNAL LIGHTING AND REVISED DETAILS OF ANCILLARY STRUCTURES INCLUDING NEW CONDITION FOR FUTURE PRIMARY SUBSTATION
Awaiting decision Demolition