IP5 Celtic Way Celtic Lakes Newport South Wales NP10 8BE

Granted Newport 24/0611 Full

Permission granted. Work must normally begin within five years of the decision or the permission lapses.

Proposal

PROPOSED PARTIAL CHANGE OF USE OF BUILDING IP5 FROM B8 STORAGE TO B1 LABORATORY USE AND ANCILLARY SPACES AND ASSOCIATED MINOR EXTERNAL WORKS

As published by the council, reference 24/0611

Application record

Reference
24/0611
Type
Full
Status
Decided
Decision
Granted with Conditions
Received
12 Jul 2024
Validated
19 Jul 2024
Decided
28 Nov 2024
Ward
Tredegar Park And Marshfield
Parish
Coedkernew Community Council
Decision by
Delegated
Postcode
NP10 8BE

Timeline

Dates from the published record

  1. 12 Jul 2024

    Received by Newport

  2. 19 Jul 2024

    Validated

    Checked as complete and ready for consideration.

  3. 28 Nov 2024

    Decision issued: Granted with Conditions

  4. 14 Aug 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

Agent on file, a planning consultancy registered in Bridgend

853 applications on PlanIndex · across 21 councils · 97% granted

Trade members see who it is, their full track record, and every application they have filed.

See who's behind it

Documents

Plans, drawings, consultee responses and the officer's report

27 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What a grant of permission means

The process from here

Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.

Work must normally begin within five years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.

About full applications applications

How this application type works

A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.

More on full applications applications in our guide

Nearby applications

Within 500 metres

  • IP5 Celtic Way Celtic Lakes Newport South Wales NP10 8BE

    26/0458 Submitted 17 Jun 2026 168m away

    81% historically approved · decision due ~11 Sep

    INSTALLATION OF EXTERNAL BUILDING EXTRACT DUCTS, AIR INTAKE/EXTRACT LOUVRES, CONDENSER UNITS AND ENCLOSURES AND ASSOCIATED WORKS

    Awaiting decision
  • Celtic Technology Centre Celtic Way Celtic Lakes Newport South Wales NP10 8BE

    26/0586 Submitted 30 Jul 2026 168m away

    81% historically approved · decision due ~24 Sep

    PARTIAL DISCHARGE OF CONDITIONS 10 (SERVICE TESTING AND MAINTENANCE PLAN), 16 (EXTERNAL LIGHTING), 20 (CYCLE PARKING DETAILS), 21 (EV CHARGING), 22 (TRAVEL PLAN) AND 23 (PEDESTRIAN CROSSING AND FOOTWAY) OF 25/0711 S73 APPLICATION TO VARY CONDITIONS 1 (APPROVED PLANS), 7 (LANDSCAPING AND PLANTING SCHEME), 10 (NOISE ASSESSMENT) AND 11 (NOISE SURVEY) OF 20/0039 ERECTION OF 4NO. THREE-STOREY DATA CENTRE BUILDINGS COMPRISING B8 USE AND ANCILLARY B1 USE, PROVISION OF EMERGENCY GENERATORS, SECURITY LODGE, HARD AND SOFT LANDSCAPING, INTERNAL ACCESS ROADS, CAR PARKING AND SUSTAINABLE DRAINAGE. AMENDMENTS INCLUDE CHANGES TO BUILDING FOOTPRINTS AND DESIGN, LOCATION OF GENERATORS, CHANGES TO DRAINAGE STRATEGY AND LANDSCAPING AND OTHER LAYOUT CHANGES

    Awaiting decision
  • Celtic Technology Centre Celtic Way Celtic Lakes Newport South Wales NP10 8BE

    26/0585 Submitted 30 Jul 2026 168m away

    81% historically approved · decision due ~24 Sep

    NMA APPLICATION TO VARY CONDITION 2 (NOISE) OF 24/0747 CONSTRUCTION OF AN ELECTRICITY SUBSTATION COMPOUND COMPRISING TRANSFORMERS, SWITCHGEARS AND ELECTRICAL EQUIPMENT, SURFACE WATER DRAINAGE, MEANS OF ACCESS, LANDSCAPING, THE INSTALLATION OF BURIED ELECTRICITY TRANSMISSION CIRCUITS, CREATION OF A HABITAT COMPENSATION SITE AND ASSOCIATED WORKS

    Decided
  • IP5 Celtic Way Celtic Lakes Newport South Wales NP10 8BE

    25/1067 Submitted 10 Dec 2025 168m away

    81% historically approved · decision due ~12 Aug

    INSTALLATION OF 1NO. GENERATOR AND ASSOCIATED FLUES & WORKS

    Decided
  • Quinn Radiators Celtic Way Celtic Lakes Newport South Wales NP10 8FS

    25/0616 Submitted 31 Jul 2025 277m away

    PARTIAL DISCHARGE OF CONDITION 11 (MATERIALS) OF 24/0006 DEMOLITION OF REMAINDER OF EXISTING PRINCIPAL BUILDING AND REMAINING STRUCTURES AND CONSTRUCTION OF NEW DATA CENTRE (USE CLASS B8) ACROSS TWO MAIN BUILDINGS PLUS ANCILLARY STRUCTURES ANDS OTHER ASSOCIATED WORKS

    Granted Conditions Demolition 10 docs
  • Quinn Radiators Celtic Way Celtic Lakes Newport NP10 8FS

    26/0661 Submitted 24 Aug 2026 277m away

    81% historically approved · decision due ~19 Oct

    PARTIAL DISCHARGE OF CONDITION 12 (TRAVEL PLAN) OF 26/0379 S73 APPLICATION TO VARY CONDITIONS 1 (APPROVED PLANS), 3 (LANDSCAPING), 4 (LEMP), 15 (PARKING), 16 (CYCLE STORAGE DETAILS), 17 (FOUL DRAINAGE) AND TO REMOVE CONDITION 6 (DORMICE METHOD STATEMENT) OF 24/0006 DEMOLITION OF REMAINDER OF EXISTING PRINCIPAL BUILDING AND REMAINING STRUCTURES AND CONSTRUCTION OF NEW DATA CENTRE (USE CLASS B8) ACROSS TWO MAIN BUILDINGS PLUS ANCILLARY STRUCTURES ANDS OTHER ASSOCIATED WORKS. AMENDMENTS INCLUDE CHANGES TO LAYOUT AND LANDSCAPING TO ACCOMMODATE SAB REQUIREMENTS, AMENDMENTS AND ADDITIONS TO ADMIN AND DATA HALL BUILDINGS, DESIGN AND SPECIFICATION OF GENERATORS, REVISIONS TO EXTERNAL LIGHTING AND REVISED DETAILS OF ANCILLARY STRUCTURES INCLUDING NEW CONDITION FOR FUTURE PRIMARY SUBSTATION

    Awaiting decision Demolition

In Newport

  • 26/0397 Granted

    Glen View Ponthir Road Newport South Wales NP18 3NW

    DEMOLITION OF EXISTING GARAGE AND REAR EXTENSION AND ERECTION OF SINGLE STOREY SIDE AND REAR EXTENSION

    18 May 2026 Full applications
  • 26/0368 Granted

    Streethub Unit On Footpath Outside Monmouthshire House John Frost Square Newport South Wales

    PROPOSED INSTALLATION OF 1NO. NEW BT STREET HUB, INCORPORATING 2NO. DIGITAL 75" LCD ADVERT SCREENS, AND ASSOCIATED BT PHONE KIOSK REMOVAL

    14 May 2026 Full applications
  • 26/0216 Refused

    Land Adjacent To Unit 3 Esperanto Way Newport South Wales

    PROPOSED CHANGE OF USE FROM OFFICE (B1) TO EVENTS VENUE AND ASSOCIATED WORKS

    20 Mar 2026 Full applications
  • 26/0010 Granted

    The Grove Bowdens Lane Penhow Newport NP26 3AA

    DEMOLITION OF AN EXISTING SEMI-DETACHED DWELLING AND CONSTRUCTION OF A REPLACEMENT TWO-STOREY DETACHED DWELLING, TOGETHER WITH ASSOCIATED WORKS AND USE OF DETACHED HOLIDAY ACCOMMODATION OUTBUILDING AS PRIMARY RESIDENCE FOR DURATION OF CONSTRUCTION PERIOD

    7 Jan 2026 Full applications
  • 26/0241 Granted

    Liberty Steel Corporation Road Newport NP19 4XE

    ENGINEERING WORKS TO CONSTRUCT RAISED BUND AND ACCESS RAMP AROUND APPROVED DATA CENTRE TO A CREST OF APPROXIMATELY 9.75M AOD, PARTIAL DEMOLITION OF A BUILDING, THE IMPORTATION OF FILL MATERIAL TO CREATE THE BUND & RAMP, SURFACING WORKS AND ALTERATIONS TO BUILDING ELEVATIONS TO ACCOMMODATE LEVEL CHANGES

    30 Mar 2026 Full applications