Margam Green Energy Plant Longlands Lane Margam Neath Port Talbot SA13 2NU

Awaiting decision Neath Port Talbot P2026/0517

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Non-Material Amendment (NMA) to Condition 2 of Planning Permission P2025/0446 granted on 25.03.2026 to amend the approved site layout and for replacement building details at Margam Green Energy Plant.

As published by the council, reference P2026/0517

Application record

Reference
P2026/0517
Status
Awaiting decision
Received
7 Aug 2026
Validated
8 Aug 2026
Ward
Margam & Taibach
Parish
Port Talbot
Postcode
SA13 2NU

Timeline

Dates from the published record

  1. 7 Aug 2026

    Received by Neath Port Talbot

  2. 8 Aug 2026

    Validated

    Checked as complete and ready for consideration.

  3. 18 Aug 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 3 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Neath Port Talbot took a median of 55 days over the applications it decided in the last year.

What happens while it is decided

This application is with Neath Port Talbot for determination, against a statutory target of eight weeks. Over the last year Neath Port Talbot's median decision took 55 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Neath Port Talbot's portal will say. Our guide explains the common types.

Nearby applications

Within 500 metres

  • Hedgerow Located Along Heol Cae'r Bont Heol Cae'r Bont Margam Neath Port Talbot SA13 2NS

    P2026/0376 Submitted 8 Jun 2026 0m away

    97% historically approved · decision due ~3 Aug

    Application for the removal of approximately 40 metres of hedgerow to facilitate the creation of a temporary construction access from Heol Cae'r Bont, to the installation of an underground cable route, in association with the Margam Substation upgrade. On completion of the development the hedgerow will be reinstated using a native mixed species planting scheme comprising species consistent with the existing hedgerow and surrounding landscape.

    Withdrawn Trees
  • Margam Green Energy Plant Longlands Lane Margam

    P2023/0210 Submitted 15 Mar 2023 260m away

    Advertisment Consent: Entrance sign for "Margam Green Energy Plant" with the dimensions of 5500mm x 2000mm.

    Granted Advertising 6 docs
  • Land Off J38 Of The M4 Margam Port Talbot

    P2021/0625 Submitted 10 Jun 2021 415m away

    Request for a Scoping Opinion in Accordance With Regulation 14(1) of the Environmental Impact Assessment (Wales) Regulations 2017 for the Development of a Metal Processing Facility Comprising Operational Building (18,250 sq.m), Plus Administration and Amenity Buildings (1,848 sq.m), 300 Parking Spaces and Associated Development.

    Decided Outline 3 docs