Skip to content
PlanIndex Get alerts
Menu

Planning application

25/00366/SCR_L

Old Dormitory Site Marybank Isle Of Lewis

Decided Na h-Eileanan Siar Environmental Screening Opinion

Proposal

Proposed temporary workers residential accommodation, including welfare facilities, parking, associated infrastructure and other ancillary development.

As published by the council, reference 25/00366/SCR_L

Timeline

Dates from the published record

  1. 7 Oct 2025

    Received by Na h-Eileanan Siar

  2. 28 Nov 2025

    Decision issued: No Environmental Assessment Required

  3. 27 Jul 2026

    Added to PlanIndex

After the decision

The process from here

The council has decided this application; the published outcome sits in the record above and the decision notice on the council portal carries the detail, including any conditions.

If permission was granted, work must normally begin within three years of the decision. If it was refused, the applicant can appeal within the statutory time limit or submit a revised scheme.

About outline applications

How this application type works

An outline application tests the principle of developing a site before the detail is worked up. Some or all of the particulars, such as appearance, layout, scale, access and landscaping, are held back as reserved matters for later approval. Permission at outline stage does not by itself allow building to start; the reserved matters must be approved first.

More on outline applications in our guide

Nearby applications

Within 500 metres

  • 26/00009/PPDM Granted

    Old Dormitory Site Marybank Isle Of Lewis

    Proposed temporary workers residential accommodation, including welfare facilities, parking, associated infrastructure and other ancillary development

    12 Jan 2026 45m away Full applications
  • 25/00295/AGRIC Granted

    Agricultural Building 6A Marybank Isle Of Lewis

    Erect agricultural building

    20 Aug 2025 486m away Prior approval

In Na h-Eileanan Siar

  • 26/00191/SCR_L Decided

    Range Head West Gerinish Daliburgh Isle Of South Uist HS8 5RW

    Installation of a new launch pad and environmental shelter

    26 May 2026 Outline
  • 26/00254/PPP Awaiting decision

    7B Paiblesgarry Bayhead Isle Of North Uist

    Erect house with associated infrastructure and services.

    2 Jul 2026 Outline
  • 26/00107/CONSG Refused

    Offshore Works Spiorad Na Mara Wind Farm Barvas Barvas Isle Of Lewis

    Scottish Government - Marine Directorate Consultation on Applications for S36 Consent and Marine Licences associated with the Spiorad na Mara offshore windfarm, North West Lewis. [NOTE: Comhairle nan Eilean Siar issued its reponse to this consultation to Marine Directorate on 30 June 2026]. [Note: Scottish Ministers are the Determing Authority in respect of these applications.]

    19 Mar 2026 Outline
  • 26/00159/R62HRA Granted

    Subsea Cable Coilleag Eriskay Isle Of South Uist

    Eriskay to Barra 11KV submarine cable replacement onshore works (Regulation 62)

    5 May 2026 Outline
  • 26/00075/SCSC_L Decided

    Druim Loch A Mhaide Quarry Airidhbhruach Lochs Isle Of Lewis

    Re-open the former borrow pit at Kinloch for the extraction of rock for use in the construction of the approved Uisenis Wind Farm project

    26 Feb 2026 Outline