Rothes III Wind Farm Dallas Forres Moray

Granted Moray 24/01171/S36CON Dealt With By Scottish Executive

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Variation under section 36C of the Electricity Act 1989 to consented Rothes III Wind Farm (ECU ref. ECU00000474) to increase height of 3 wind turbines from max. tip height of 149.9m to up to max. tip height of 200m (turbines numbered 9, 13 and 14)

As published by the council, reference 24/01171/S36CON

Application record

Reference
24/01171/S36CON
Type
Dealt With By Scottish Executive
Status
Awaiting decision
Decision
Granted As published: Raise No Objections
Received
24 Jul 2024
Validated
24 Jul 2024
Decided
22 Oct 2024
Ward
Speyside Glenlivet
Parish
Speyside
Decision by
Cleared PE/ID - discuss with Officer

Site history

Applications at this address on the Moray register

This site has had 2 applications since 2024: 2 approved, 0 refused.

  • 24/01171/S36 Granted

    Rothes III Wind Farm Dallas Forres Moray

    Variation under section 36C of the Electricity Act 1989 to consented Rothes III Wind Farm (ECU ref. ECU00000474) to increase height of 3 wind turbines from max. tip height of 149.9m to up to max. tip height of 200m (turbines numbered 9, 13 and 14)

    Decided 22 Oct 2024

Timeline

Dates from the published record

  1. 24 Jul 2024

    Received by Moray

  2. 22 Oct 2024

    Decision issued: Raise No Objections

  3. 16 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

7 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Moray granted permission on 22 October 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Moray's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles

  • Rothes III Wind Farm Dallas Forres Moray

    24/01171/S36 Submitted 24 Jul 2024 50 yards away

    Variation under section 36C of the Electricity Act 1989 to consented Rothes III Wind Farm (ECU ref. ECU00000474) to increase height of 3 wind turbines from max. tip height of 149.9m to up to max. tip height of 200m (turbines numbered 9, 13 and 14)

    Granted 7 docs