Construct operate and decommission a wind farm with a generating capacity in excess of 50MW consisting of up to 22 wind turbines and associated infrastructure including a battery energy storage facility. Thirteen of the wind turbines have a ground to blade tip height of up to 200m and nine have a ground to blade tip height of up to 180m at

As published by the council, reference 23/00047/S36

Application record

Reference
23/00047/S36
Type
Dealt With By Scottish Executive
Status
Awaiting decision
Decision
Raise No Objections
Received
13 Jan 2023
Validated
13 Jan 2023
Decided
27 Jun 2023
Ward
Speyside Glenlivet
Parish
Dufftown & District
Decision by
Committee - National/Major

Timeline

Dates from the published record

  1. 13 Jan 2023

    Received by Moray

  2. 27 Jun 2023

    Decision issued: Raise No Objections

  3. 5 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

227 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Moray granted permission on 27 June 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Moray's portal will say. Our guide explains the common types.