Planning application
Rothes III Wind Farm Moray
Decided. The decision notice on the council portal carries the outcome in full, including any conditions.
Proposal
Screening Opinion for grid connection works at
As published by the council, reference 22/00310/S37
Application record
- Reference
- 22/00310/S37
- Type
- Section 37 SE Energy Consent Unit
- Status
- Awaiting decision
- Decision
- Screening Opinion Issued
- Received
- 1 Mar 2022
- Validated
- 2 Mar 2022
- Decided
- 24 May 2022
- Ward
- Speyside Glenlivet
- Parish
- Heldon
- Decision by
- Answer to PE/ID or application
Timeline
Dates from the published record
-
1 Mar 2022
Received by Moray
-
2 Mar 2022
Validated
Checked as complete and ready for consideration.
-
24 May 2022
Decision issued: Screening Opinion Issued
-
24 Aug 2026
Added to PlanIndex
After the decision
Moray has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Moray's portal will say. Our guide explains the common types.