Electricity Transmission Substation Newhouse Farm Industrial Estate Chepstow Monmouthshire

Granted Monmouthshire DM/2024/00455 Sta. Undertaker Development

Permission granted. Work must normally begin within five years of the decision or the permission lapses.

Proposal

National Grid are proposing to install a new high voltage overhead line at the National Grid 400kV Compound, situated at Newhouse Industrial Estate, Chepstow

As published by the council, reference DM/2024/00455

Application record

Reference
DM/2024/00455
Type
Sta. Undertaker Development
Status
Decided
Decision
No Objection
Received
8 Apr 2024
Validated
8 Apr 2024
Decided
1 May 2024
Ward
Bulwark And Thornwell
Parish
Chepstow Town Council
Decision by
Delegated Officer

Timeline

Dates from the published record

  1. 8 Apr 2024

    Received by Monmouthshire

  2. 1 May 2024

    Decision issued: No Objection

  3. 7 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

4 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Monmouthshire granted permission on 1 May 2024, subject to any conditions on the decision notice. Work must normally begin within five years or the permission lapses. More in our guide to what happens after a planning decision.