Decision times · Wales

How long planning decisions take in Monmouthshire

54 days. Ranked 87 of 343.

In the year to September 2026, the median planning application decided by Monmouthshire took 54 days from submission to decision — 2 days inside the eight week target. That is measured across 658 decisions where the council published both dates.

54 days
Median decision 2 days inside the eight week target
87 of 343
UK rank down 76 places in a year
52%
Within eight weeks 75% within thirteen
155 days
Nine in ten decided by The wait to budget for

How Monmouthshire compares

Year to September 2026

Monmouthshire decides faster than the country as a whole: 2 days below the national median of 56 days. Nationally 55% of applications are decided within eight weeks; here it is 52%.

The average here is 76 days, longer than the median because a handful of applications take very much longer than the rest. For planning around, 155 days is the more useful number: nine applications in ten were decided inside it.

  1. Within eight weeks the statutory target 344 52%
  2. Eight to thirteen weeks the major development band 152 23%
  3. Over thirteen weeks commonly an agreed extension 162 25%

The last few years

Each row is a full twelve months of decisions, ending in the quarter shown

Rolling twelve month windows overlap by nine months, so this reads as a trend rather than as four separate quarters. Only windows our records reach far enough back to measure in full are listed.

Monmouthshire: median days from application to decision, by rolling twelve month window. Source: PlanIndex, planindex.co.uk.
Twelve months to Median days UK rank
September 2026 54 87 of 343
June 2026 42 14 of 328
March 2026 36 7 of 243
December 2025 31 7 of 236
September 2025 28 11 of 324
June 2025 56 150 of 313
March 2025 56 148 of 315
December 2024 56 150 of 319

Against the same twelve months a year earlier, when the median was 28 days, Monmouthshire has moved down 76 places in the table.

By type of application

Year to September 2026 · types with at least ten decisions

The headline median mixes every kind of application together. A householder extension and an outline application for a housing site are not the same job, and the difference between them is usually larger than the difference between two councils.

  1. Other 31 decided 18 days
  2. Trees 104 decided 21 days
  3. Lawful development 45 decided 29 days
  4. Amendments 60 decided 30 days
  5. Conditions 88 decided 62 days
  6. Householder 191 decided 64 days
  7. Full applications 102 decided 97 days
  8. Heritage and listed buildings 26 decided 164 days

How these types compare nationally

What Monmouthshire decides

Year to September 2026

Monmouthshire issued 658 decisions in the year to September 2026. Of the clear-cut outcomes, 95% were approvals: 584 granted against 28 refused. Split decisions, withdrawals and other outcomes sit outside that percentage rather than being counted as either.

Speed and approval rate are separate things. A council that refuses quickly is not doing the same job as one that negotiates an approval slowly, and neither figure alone says which served the applicant better.

Common questions

How long does a planning decision take in Monmouthshire?

The median planning application decided by Monmouthshire in the year to September 2026 took 54 days from submission to decision, 2 days inside the eight week target. That is measured across 658 decisions where the council published both a start date and a decision date. It ranks 87 of 343 UK councils on decision speed.

Does Monmouthshire meet the eight week target?

52% of the 658 decisions Monmouthshire made in the year to September 2026 came within eight weeks of the application being received, and 75% within thirteen weeks. Nine in ten were decided within 155 days. Councils can agree an extension of time with an applicant, so a decision past eight weeks is not necessarily a missed deadline.

Is Monmouthshire faster or slower than average?

Monmouthshire is faster than average: its median of 54 days is 2 days below the national median of 56 days.

Is Monmouthshire getting faster or slower?

Against the same twelve month window a year earlier, when its median was 28 days, Monmouthshire has moved down 76 places in the table. Its median has risen by 26 days.

What proportion of applications does Monmouthshire approve?

95% of the clear-cut outcomes Monmouthshire issued in the year to September 2026 were approvals: 584 granted against 28 refused. Split decisions, withdrawals and other outcomes are excluded from that percentage.

Cite these figures

Click the text to select the whole citation.

Monmouthshire planning decision times, year to September 2026: median 54 days from application to decision (2 days inside the eight week target), across 658 decisions with both dates published. 52% were decided within the eight week statutory target, 75% within thirteen weeks; nine in ten within 155 days. Ranked 87 of 343 UK councils on decision speed (national median 56 days). 95% of clear-cut outcomes were approvals. Source: PlanIndex, planindex.co.uk.