Planning application
Lands Sw of Commercial Units at 127 Ballynakilly Road, Coalisland, Dungannon, (370M Nw of Tamnamore Substation)
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Erection of c. 250MW Battery Energy Storage System (BESS) facility comprising substation buildings, transformers, inverters, battery units, Harmonic Filter Compound, Static compensator Units, temporary welfare area, fencing, SuDS Pond, CCTV, landscaping and associated ancillary development.
As published by the council, reference LA09/2026/0620/F
Application record
- Reference
- LA09/2026/0620/F
- Type
- Full
- Status
- Awaiting decision
- Received
- 11 Jun 2026
- Validated
- 15 Jun 2026
- Ward
- Killyman
- Parish
- Dungannon
- Decision by
- Committee Decision
Timeline
Dates from the published record
-
11 Jun 2026
Received by Mid Ulster
-
15 Jun 2026
Validated
Checked as complete and ready for consideration.
-
29 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 10 August 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Mid Ulster took a median of 106 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
81 documents on file for this application
- CONSULTATION LETTER REMINDER
- CONSULTATION LETTER REMINDER
- DEPARTMENT FOR INFRASTRUCTURE RIVERS
- HED
- ROADS DEVELOPMENT CONTROL DEPARTMENT FOR INFRASTRUCTURE
- ROADS DEVELOPMENT CONTROL DEPARTMENT FOR INFRASTRUCTURE
- CONSULTATION LETTER REMINDER
- CONSULTATION LETTER REMINDER
- CONSULTATION LETTER REMINDER
- CONSULTATION LETTER REMINDER
- CONSULTATION LETTER REMINDER
- CONSULTATION LETTER REMINDER
- STANDARD CONSULTATION LETTER
- GEOLOGICAL SURVEY NORTHERN IRELAND
- GEOLOGICAL SURVEY NORTHERN IRELAND
- CONTACT DETAILS ADDED FOR COMPLAINANT
- NORTHERN IRELAND FIRE AND RESCUE SERVICE
- NIE NETWORKS
- HSENI PLANNING CONSULTATION
- MR ASHLEY CARDWELL-120 COASH ROAD DUNGANNON TYRONE-OBJECTS(FULL)
- OBJ W MCKAY
- OBJ N KIRK
- OBJ - EVAN & PAT HAYDOCK
- NI WATER PLANNING
- PLANNING RESPONSE TEAM DAERA EMFG AND NIEA
- STANDARD NN LETTER (BULK)
- PLANNING RESPONSE TEAM DAERA EMFG AND NIEA
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- MINE RISK ASSESSMENT - PART 2
- ACKNOWLEDGE APP AND FEE RECEIPT
- SITE LOCATION PLAN 01
- SITE LAYOUT 02
- PACC REPORT
- DESIGN & ACCESS STATEMENT
- PRELIMINARY RISK ASSESSMENT
- TRANSPORT ASSESSMENT FORM
- FLOOD RISK & DRAINAGE ASSESSMENT
- FLOOD RISK & DRAINAGE ASSESSMENT
- BESS CONTAINERS PLANS & ELEVATIONS 03
- TRANSFORMER PLAN & ELEVATIONS 04
- CUSTOMER SUBSTATION PLAN & ELEVATIONS 05
- METAL FIELD GATE DEER FENCING 08
- DEER FENCE DETAIL 09
- MESH SECURITY FENCING 10
- PALISADE FENCING 11
- TYPICAL LV & FEEDER PILLAR PLANS 14
- CCTV POST DETAILS 13
- ACCESS TRACK SPECIFICATIONS 15
- POST & RAIL FENCE DETAILS 12
- TOPOGRAPHY PLAN 16
- ARCHAEOLOGICAL IMPACT ASSESSMENT
- FIRE WATER MANAGEMENT PLAN
- MINE RISK ASSESSMENT
- SAFETY MANAGEMENT PLAN
- OUTLINE EMERGENCY RESPONSE PLAN
- ARBORICULTURAL REPORT
- TREE CONSTRAINTS PLAN 17
- TREE IMPACT PROTECTION PLAN 18
- TREE SCHEDULE
- CONSTRUCTION ENVIRONMENTAL MANAGEMENTPLAN
- LANDSCAPE & VISUAL IMPACT ASSESSMENT
- PROPOSED LANDSCAPE PLAN 07
- NOISE IMPACT ASSESSMENT
- APPLICATION FORM
- MINE RISK ASSESSMENT - PART 1
- COMPOUND PLANS & ELEVATIONS 06
- SAFETY MANAGEMENT PLAN - PART 2
- SAFETY MANAGEMENT PLAN - PART 1
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Mid Ulster for determination, against a statutory target of eight weeks. Over the last year Mid Ulster decided full applications in a median of 115 days. More in our guide to how long planning decisions take.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Lands SW of Commercial Units at 127 Ballynakilly Road, Coalisland, Dungannon, BT71 4HU (370m NW of Tamnamore Substation)
Battery Energy Storage System (BESS) facility and Solar PV Array
Decided 2 docs -
112 Coash Road Dungannon BT71 6JE.
Erection of dwelling, detached garage & associated site works.
Granted Full applications New dwelling 19 docsDomestic -
127 Ballynakilly Road Dungannon
Extension to existing storage unit for increase in stock
Granted Full applications Extension 13 docs -
111 Ballynakilly Road Coalisland
Proposed storage/warehouse provision for the storage of metal components
Granted Full applications 32 docs
Other full applications
In Mid Ulster
-
LA09/2026/0805/F Decided
Reid Engineering Ltd Kilcronagh Industrial Estate Cookstown BT80 9HG
Proposed relocation of existing entrance at Kilcronagh Industrial Estate, Cookstown, BT80 9H
-
LA09/2026/1126/F Awaiting decision
49 Church Street Cookstown BT80 8HT
Retention of single storey rear replacement extension with internal alterations to dwelling
-
LA09/2025/0520/F Decided
2 Lisnamuck Road Tobermore BT45 5QF
Production facility shed for the manufacture of decorative paving and walling products
-
LA09/2026/0726/F Decided
Dwelling Known As 80 Aghafad Road (by Applicant) 77 Aghafad Road (postal Address On Maps) Pomeroy BT70 2TR
Extension and alterations to dwelling
-
LA09/2025/0955/F Decided
Lands approximately 80M South of 39 Castle Road Cookstown Tyrone BT80 8TN
3 No. Glamping Pods, Parking, Landscaping and Associated Site Works