Planning application
Lands immediately South of No.157 Ballynakilly Road, C.170 Metres Northeast of Tamnamore Substation and C.60 Metres West of No. 167 Ballynakilly Road
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Erection of a c. 250MW battery energy storage system (BESS) facility and associated 275kV transformer and 33kV transformers including switch houses with control rooms, storage containers, officer trailer, lighting and closed circuit TV columns, site fencing, parking and all associated site works, including use of existing access from Drumkee Road
As published by the council, reference LA09/2025/1108/F
Application record
- Reference
- LA09/2025/1108/F
- Type
- Full
- Status
- Awaiting decision
- Received
- 23 Oct 2025
- Validated
- 24 Oct 2025
- Ward
- Killyman
- Parish
- Dungannon
- Decision by
- Committee Decision
Timeline
Dates from the published record
-
23 Oct 2025
Received by Mid Ulster
-
24 Oct 2025
Validated
Checked as complete and ready for consideration.
-
29 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 19 December 2025, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Mid Ulster took a median of 98 days over the applications it decided in the last year.
Who's behind it
Company information only, from the register and Companies House
TSA Planning Ltd Agent, a planning consultancy registered in Belfast
Active · incorporated 2007 · Belfast
217 applications on PlanIndex · across 11 councils · 100% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordHeron Storage Applicant, registered in Draperstown
Active · incorporated 2021 · Draperstown
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
120 documents on file for this application
- STANDARD CONSULTATION LETTER
- DFI ROADS DUNGANNON TEAM 1
- DFI ROADS DUNGANNON TEAM 1
- DFI ROADS DUNGANNON TEAM 1
- DFI ROADS DUNGANNON TEAM 1
- STANDARD CONSULTATION LETTER
- ENVIRONMENTAL HEALTH MID ULSTER DISTRICT COUNCIL
- DFI ROADS DUNGANNON TEAM 1
- DFI ROADS DUNGANNON TEAM 1
- PLANNING RESPONSE TEAM DAERA EMFG AND NIEA
- DEPARTMENT FOR INFRASTRUCTURE RIVERS
- DEPARTMENT FOR INFRASTRUCTURE RIVERS
- OBJ E & P HAYDOCK
- CODMP
- STANDARD CONSULTATION LETTER
- DFI ROADS DUNGANNON TEAM 1
- DFI ROADS DUNGANNON TEAM 1
- STANDARD CONSULTATION LETTER
- PLANNING RESPONSE TEAM DAERA EMFG AND NIEA
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- AMENDED PLANS RECEIVED (BULK)
- NOISE IMPACT ASSESSMENT
- LIVA PHOTOMONTAGES
- SPPS ADDENDUM
- FIRE AND SAFETY REPORT
- DRAINAGE ASSESSMENT
- STORAGE ACCESS
- SITE PLAN
- SITE PLAN
- SITE PLAN
- LANDSCAPE PLAN
- MR GARY WILKINS
- SHARED ENVIRONMENTAL SERVICE
- SHARED ENVIRONMENTAL SERVICE
- CONSULTATION LETTER REMINDER
- DFI ROADS DUNGANNON TEAM 1
- STANDARD CONSULTATION LETTER
- CONSULTATION LETTER REMINDER
- STANDARD CONSULTATION LETTER
- NIE NETWORKS
- PLANNING RESPONSE TEAM DAERA EMFG AND NIEA
- STANDARD CONSULTATION LETTER
- DFI ROADS DUNGANNON TEAM 1
- STANDARD CONSULTATION LETTER
- DEPARTMENT FOR INFRASTRUCTURE RIVERS
- EXISTING SITE PLAN
- EXISTING SITE PLAN
- PROPOSED SECTION 1
- PROPOSED SECTION 2
- PROPOSED SECTION 3
- PROPOSED ACCESS DRAWING
- PROPOSED SITE PLAN 2
- PROPOSED SITE PLAN 4
- NORTHERN IRELAND FIRE AND RESCUE SERVICE
- STANDARD NN LETTER (BULK)
- GEOLOGICAL SURVEY NORTHERN IRELAND
- STANDARD CONSULTATION LETTER
- DFI ROADS DUNGANNON TEAM 1
- ENVIRONMENTAL HEALTH MID ULSTER DISTRICT COUNCIL
- STANDARD NN LETTER (BULK)
- HSENI PLANNING CONSULTATION
- CEMP
- PLANNING RESPONSE TEAM DAERA EMFG AND NIEA
- OBJ ENDA & SIOBHAN MCGAHAN
- OBJ AIDAN & BERNADETTE MCGAHON
- OBJ EVAN & PAT HAYDOCK
- OBJ R MORGAN
- OBJ B MORGAN
- OBJ R MORGAN
- STANDARD NN LETTER (BULK)
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- STANDARD CONSULTATION LETTER
- ACKNOWLEDGE APP AND FEE RECEIPT
- SITE LOCATION PLAN 01
- SITE PLAN 02
- EXISTING SITE PLAN 20
- SWITCH HOUSE COMPOUND PLAN 08
- SWITCH HOUSE PLAN 06
- SITE PLAN 03
- COMMUNITY CONSULTATION REPORT
- DESIGN, ACCESS AND PLANNING STATEMENT
- PRELIMINARY ECOLOGICAL APPRAISAL REPORT
- MINING RISK ASSESSMENT
- PRELIMINARY RISK ASSESSMENT
- TRANSPORT ASSESSMENT FORM
- DRAINAGE ASSESSMENT
- BATTERY UNIT PLANS AND ELEVATIONS 15
- BATTERY UNIT PLANS AND ELEVATIONS 16
- SITE OFFICE PLANS AND ELEVATIONS 14
- SWITCH HOUSE PLANS AND ELEVATIONS 17
- SWITCH HOUSE FLOOR PLANS 07
- SWITCH HOUSE ELEVATIONS 18
- SWITCH HOUSE ELEVATIONS 19
- STORAGE CONTAINERS PLANS AND ELEVATIONS 12
- PROPOSED FENCING PLANS AND ELEVATIONS 13
- LIGHTING PLANS 09
- FIRE AND SAFETY ASSESSMENT
- EMERGENCY RESPONSE PLAN
- HAZARDOUS SUBSTANCE ASSESSMENT
- SUPPORTING PHOTOGRAPHS
- LANDSCAPE PLAN 05
- LIGHTING ASSESSMENT REPORT
- PROPOSED ACCESS PLAN 10
- PROPOSED VEHICLE TRACKING PLAN 11
- NOISE IMPACT ASSESSMENT
- LANDSCAPE AND VISUAL IMPACT ASSESSMENT
- EXISTING SITE PLAN 21
- SITE PLAN 04
- EXISTING SITE PLAN 22
- APPLICATION FOR PLANNING PERMISSION
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Mid Ulster for determination, against a statutory target of eight weeks. Over the last year Mid Ulster decided full applications in a median of 105 days. More in our guide to how long planning decisions take.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Lands immediately East of Tamnamore Substation and C.260m SouthWest of 167 Ballynakilly Road, Coalisland, Dungannon
Discharge of Conditions - 16 and 18 of Planning Reference LA09/2024/1529/F (Section 54 Amendment to vary Condition 17 of Planning Permission ref: LA09/2022/0600/F),
Granted Conditions 14 docs -
Lands between 177 and 179 Ballynakilly Road Coalisland
Dwelling and Domestic Garage on an Infill Site
Granted Outline Extension 9 docsDomestic -
Lands between 177 and 179 Ballynakilly Road Coalisland
Temporary permission for 2 No. mobile homes to house a family whilst planning permission for a dwelling is sought.
Granted Full applications 13 docsDomestic -
Site 100M SW Of 136 Ballynakilly Road Coalisland.
Proposed general purpose store for the storage of metal cladding materials & components.
Granted Full applications 20 docs -
20M North East Of 40 Drumkee Road Dungannon
2 Bedroom modular bungalow
Granted Full applications 25 docs
Other full applications
In Mid Ulster
-
LA09/2026/0809/F Granted
No 30 Cloverhill Road Ballinderry Cookstown BT80 0AT
Annex to dwelling for retired couple - Mr and Mrs Lawrence Loughran
-
LA09/2026/0205/F Granted
Site No 3 Beech Lane Maghera BT46 5GG
Change of dwelling and detached garage at site no 3Beech Lane, Maghera to supercede that approved under H/2000/0418/F
-
LA09/2026/0587/F Decided
24 Tullyreavy Road Cookstown BT70 3JN
Proposed extensions and alteration to existing dwelling and provision of new Detached Garage + Car Port and extension to existing site curtilage to create a new access
-
LA09/2025/0784/F Granted
Adjacent to 106 Creagh Road Castledawson Londonderry BT45 8EY
Single storey extension to existing store
-
LA09/2026/0951/F Awaiting decision
35 Oldtown Road Bellaghy BT45 8LQ
Demolition of existing rear sunroom and construction of a new single-storey rear extension in lieu, together with associated internal alterations