Skip to content
PlanIndex Get alerts
Menu

Planning application

Intergrated College Dungannon 21 Gortmerron Link Road Dungannon

Granted Mid Ulster LA09/2022/1702/F Full

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Temporary mobile classroom and school meals accommodation, hard play area, LPG gas compound, substation, retaining walls, underground drainage system and all associated ground work required for the operation of IC Dungannon during the construction and redevelopment of the College. Temporary permission is required until the new college becomes operational

As published by the council, reference LA09/2022/1702/F

Application record

Reference
LA09/2022/1702/F
Type
Full
Status
Permission Granted
Decision
Granted As published: Permission Granted
Received
7 Dec 2022
Validated
7 Dec 2022
Decided
13 Apr 2023
Ward
Killymeal
Parish
Dungannon
Decision by
Committee Decision

Timeline

Dates from the published record

  1. 7 Dec 2022

    Received by Mid Ulster

  2. 13 Apr 2023

    Decision issued: Permission Granted

  3. 23 Aug 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

Resolve Planning Agent, a planning consultancy

40 applications on PlanIndex · across 9 councils · 100% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Board of Governors of Integrated College Applicant

1 application on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

54 documents on file for this application

  • FULL - PERMISSION GRANTED Decision · 21 Apr 2023
  • STAMPED APPROVED DRAWINGS Drawings accompanying a Decision · 17 Apr 2023
  • COMMITTEE REPORT 04/04/23 Committee Report · 04 Apr 2023
  • EIA SCREENING EIA Determination · 22 Mar 2023
  • HSENI PLANNING CONSULTATION Consultee Comment · 22 Feb 2023
  • HRA SCREENING Proforma List · 20 Feb 2023
  • STANDARD CONSULTATION LETTER Consultation Request · 20 Feb 2023
  • MS MARIE MCCARTNEY Consultee Comment · 14 Feb 2023
  • STANDARD CONSULTATION LETTER Consultation Request · 07 Feb 2023
  • PLANNING RESPONSE TEAM DAERA EMFG AND NIEA Consultee Comment · 06 Feb 2023
  • MID ULSTER DISTRICT COUNCIL ENVIRONMENTAL HEALTH DEPARTMENT Consultee Comment · 06 Feb 2023
  • SITE LAYOUT Site Layout or Block Plan · 02 Feb 2023
  • SITE LAYOUT Site Layout or Block Plan · 02 Feb 2023
  • DFI ROADS COMMENT Consultee Comment · 02 Feb 2023
  • NEIL JENKINSON Consultee Comment · 24 Jan 2023
  • STANDARD NN LETTER (BULK) Neighbour Notification Letter · 17 Jan 2023
  • DFI ROADS MAGHERAFELT TEAM 1 Consultee Comment · 10 Jan 2023
  • DFI ROADS MAGHERAFELT TEAM 1 Consultee Comment · 10 Jan 2023
  • STANDARD CONSULTATION LETTER Consultation Request · 10 Jan 2023
  • STANDARD CONSULTATION LETTER Consultation Request · 10 Jan 2023
  • STANDARD CONSULTATION LETTER Consultation Request · 10 Jan 2023
  • STANDARD CONSULTATION LETTER Consultation Request · 10 Jan 2023
  • STANDARD CONSULTATION LETTER Consultation Request · 08 Dec 2022
  • APPLICATION RECEIPT WITH O/P Acknowledgement · 07 Dec 2022
  • SITE PLAN 03 Site Layout or Block Plan · 06 Dec 2022
  • PROPOSED SITE PLAN 12 Site Layout or Block Plan · 06 Dec 2022
  • PROPOSED FLOOR PLAN 15 Proposed Floor Plans · 06 Dec 2022
  • APPLICATION FORM P1 Application Form · 24 Nov 2022
  • COVER LETTER FROM AGENT Correspondence from Applicant or Agent · 24 Nov 2022
  • FORM P1A Application Form · 24 Nov 2022
  • NOISE IMPACT ASSESSMENT Noise Impact Assessment · 24 Nov 2022
  • FLOOD RISK AND DRAINAGE ASSESSMENT Report · 24 Nov 2022
  • PRELIMINARY ECOLOGICAL APPRAISAL Report · 24 Nov 2022
  • TRAFFIC STATEMENT Report · 24 Nov 2022
  • ECOLOGICAL IMPACT ASSESSMENT Report · 24 Nov 2022
  • DESIGN AND ACCESS STATEMENT Report · 24 Nov 2022
  • SITE LOCATION PLAN 01 Site Location Plan · 24 Nov 2022
  • SITE LOCATION PLAN 02 Site Location Plan · 24 Nov 2022
  • SITE PLAN 04 Site Layout or Block Plan · 24 Nov 2022
  • PROPOSED LAYOUT - LEVELS - MOBILE VILLAGE 05 Levels and Cross Sections · 24 Nov 2022
  • PROPOSED LAYOUT - SURFACING - MOBILE VILLAGE 06 Site Layout or Block Plan · 24 Nov 2022
  • PROPOSED DRAINAGE LAYOUT 07 Site Layout or Block Plan · 24 Nov 2022
  • PROPOSED SITE PREPARATION FOR TEMP CLASSROOM 08 Site Layout or Block Plan · 24 Nov 2022
  • PROPOSED TREE REMOVAL 09 Site Layout or Block Plan · 24 Nov 2022
  • CONSTRUCTION DETAILS - PAVEMENT 10 Proposed Floor Plans · 24 Nov 2022
  • EXISTING SITE PLAN 11 Site Layout or Block Plan · 24 Nov 2022
  • PROPOSED SITE PLAN 13 Site Layout or Block Plan · 24 Nov 2022
  • PROPOSED ELEVATIONS AND SECTION 16 Proposed Elevations · 24 Nov 2022
  • MECHANICAL PLANNING DRAWING 17 Proposed Floor Plans · 24 Nov 2022
  • MECHANICAL DRAWING LPG TANK COMPOUND LOCATION 18 Proposed Floor Plans · 24 Nov 2022
  • EXISTING AND PROPOSED SITE SECTIONS 19 Existing and Proposed Floor Plans · 24 Nov 2022
  • EXISTING BLOCK PLAN 20 Site Layout or Block Plan · 24 Nov 2022
  • EXISTING SITE LAYOUT AND LEVELS 21 Site Layout or Block Plan · 24 Nov 2022
  • EXISTING SITE ANALYSIS 22 Site Layout or Block Plan · 24 Nov 2022

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Mid Ulster granted permission on 13 April 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Land adjacent to 13 Lisnaclin Court Dungannon

    LA09/2026/0192/F Submitted 25 Feb 2026 200 yards away

    Renewal of planning application LA09/2020/1279/F (2no terraced dwellings)

    Granted Full applications 25 docs
  • Lands Within Brookfield Housing Development 60M East Of 52 Brookfield Road Dungannon BT71 6GR.

    LA09/2021/1170/F Submitted 12 Aug 2021 400 yards away

    Change of house types and layout to sites 171, 172, 173, 174, 175 & 176

    Granted Full applications 71 docs
  • Stevenson Park 36 Moy Road Dungannon Co Tyrone BT71 7DS.

    LA09/2019/1336/F Submitted 11 Oct 2019 0.3 miles away

    Small single storey extension to front entrance , including removal of existing porch and relocation of existing steps and alterations to existing front paving.

    Granted Full applications Extension 25 docs
    Small domestic
  • 20 Moy Road Dungannon BT71 7DS

    LA09/2026/1050/A Submitted 12 Oct 2026 0.3 miles away

    97% historically approved · decision due ~10 Dec

    Provision of new white ppc aluminium signage fascia with integrated led lighting capping 2 no. new illuminated EURSOPAR signs (single lettering) 3 no. illuminated brand icon signs 1 no. illuminated roundal sign Alteration to existing EUROSPAR community strapline message

    Awaiting decision
  • Lands Approx 45M Sw of No.194 Killyman Road Dungannon

    LA09/2023/0388/O Submitted 3 Apr 2023 0.3 miles away

    2 no infill dwellings and garages under PPS21 CTY8

    Granted Outline Extension 18 docs
  • Moy Park Killyman Road Dungannon Co Tyrone BT71 6LN

    M/2013/0157/HSC Submitted 3 Apr 2013 0.3 miles away

    Amended Proposal - Application for Hazardous Substance Consent for the storage of 120 tonnes of Part A, Entry 18. Part and Entry refer to The Planning (Hazardous Substances) Regulations (Northern Ireland) 1993 as amended by S.R. 2009/399 at Moy Park

    Granted Other 107 docs

In Mid Ulster

  • 14 Glenmaquill Road Magherafelt BT45 5EW

    Extension to dwelling

    Received 6 Jul, published by the council 29 Jul 2026 Full applications
  • 134 Ballyronan Road Magherafelt BT45 6HR

    Retention of Agricultural Storage / Livestock Building over an Existing Farm Tank

    Received 16 May, published by the council 3 Sep 2026 Full applications
  • 1 Coole Cottages Coalisland BT71 5DN

    Alteration and extension to provide a single storey extension to side of dwelling to accommodate a kitchen/dining and 2 no. additional bedrooms

    Received 15 Jun, published by the council 29 Jul 2026 Full applications
  • Land Approx. 75M SE of 21 Iniscarn Road Moneymore Londonderry BT45 7RH

    New agricultural access Laneway.

    Received 15 May, published by the council 29 Jul 2026 Full applications
  • 5 Annagher Road Coalisland BT71 4NE

    Demolition of existing dwelling and replace with two semi detached dwellings

    Received 23 Jul, published by the council 21 Oct 2026 Full applications