National Grid Yaxley 400kV Substation Leys Lane Yaxley Eye Suffolk IP23 8DX

Granted Mid Suffolk DC/26/01413 Discharge of Requirement

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

The Progress Power (Gas Fired Power Station) Order 2015: Application pursuant to requirement 16(2) to amend working hours to include Saturday - Sunday (07:00 - 19:00) from 01st May 2026 to 30th April 2027 (Weekend extended hours)

As published by the council, reference DC/26/01413

Application record

Reference
DC/26/01413
Type
Discharge of Requirement
Status
Granted
Decision
Granted
Received
26 Mar 2026
Validated
1 Apr 2026
Decided
12 May 2026
Ward
Palgrave
Parish
Yaxley
Decision by
Delegated Decision
Postcode
IP23 8DX

Site history

Applications at this address on the Mid Suffolk register

This site has had 2 applications since 2025: 1 approved, 1 refused.

  • DC/25/04349 Refused

    National Grid Yaxley 400kV Substation Leys Lane Yaxley Eye Suffolk IP23 8DX

    Discharge of Conditions Application for DC/23/01494 - Condition 11 (Noise Assessment)

    Decided 11 Dec 2025 Conditions

Timeline

Dates from the published record

  1. 26 Mar 2026

    Received by Mid Suffolk

  2. 1 Apr 2026

    Validated

    Checked as complete and ready for consideration.

  3. 12 May 2026

    Decision issued: Granted

  4. 9 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

6 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Mid Suffolk granted permission on 12 May 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • National Grid Yaxley 400kV Substation Leys Lane Yaxley Eye Suffolk IP23 8DX

    DC/26/01413 Submitted 26 Mar 2026 0m away

    The Progress Power (Gas Fired Power Station) Order 2015: Application pursuant to requirement 16(2) to amend working hours to include Saturday - Sunday (07:00 - 19:00) from 01st May 2026 to 30th April 2027 (Weekend extended hours)

    Granted Conditions 6 docs
  • Land Between A140 And Leys Lane Yaxley Eye

    DC/26/01709 Submitted 22 Apr 2026 0m away

    95% historically approved · decision due ~18 Jun

    Application under S73 for Removal or Variation of a Condition following grant of Planning Permission DC/23/01494 dated 26/06/2023 Town and Country Planning Act 1990 (as amended) - Construction and operation of Synchronous Condensers with ancillary infrastructure, and associated works including access and landscaping. - For non compliance with and removal of Condition 12 (Use and Re-instatement of Temporary Access Track) To allow for the retention of the access as per submitted plans/documents.

    Awaiting decision Conditions 15 docs
  • Land At The Leys And Ivy Farm Mellis Road Yaxley Suffolk IP21 4BT

    DC/25/04350 Submitted 1 Oct 2025 0m away

    Discharge of Condition Application for DC/23/01494 - Condition 7 (Surface Water and Drainage Verification Report)

    Granted Conditions 9 docs
  • National Grid Yaxley 400kV Substation Leys Lane Yaxley Eye Suffolk IP23 8DX

    DC/25/04349 Submitted 1 Oct 2025 0m away

    Discharge of Conditions Application for DC/23/01494 - Condition 11 (Noise Assessment)

    Refused Conditions 5 docs
  • Land At The Leys And Ivy Farm Mellis Road Yaxley Suffolk IP21 4BT

    DC/25/04350 Submitted 1 Oct 2025 0m away

    Discharge of Condition Application for DC/23/01494 - Condition 7 (Surface Water and Drainage Verification Report)

    Granted Conditions 9 docs
  • National Grid Yaxley 400kV Substation Leys Lane Yaxley Eye Suffolk IP23 8DX

    DC/25/04349 Submitted 1 Oct 2025 0m away

    Discharge of Conditions Application for DC/23/01494 - Condition 11 (Noise Assessment)

    Refused Conditions 5 docs

In Mid Suffolk

  • DC/26/03850 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    4 Sep 2026 Conditions
  • DC/26/03834 Awaiting decision

    Land East And West Of Aubrey Drive Sudbury Part In The Parish Of Chilton

    Discharge of Conditions Application for DC/21/06676 - 3 (Surface Water Managemet Strategy), 4 (Surface Water Management Strategy - Implementation and maintenance), 6 (Construction Surface Water Management Plan), 8 (Biodiversity Enhancement Strategy), 10 (Archaeological Works), 13 (Construction Management - Environmental protection), 14 (Construction Management - Highway Safety) and 15 (Landscaping Scheme)

    3 Sep 2026 Conditions
  • DC/26/03842 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 4(a) - Construction Environmental Management Plan for Stages 6-8 of the authorised development pursuant to the The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    3 Sep 2026 Conditions
  • DC/26/03798 Awaiting decision

    Land To The East Of Ely Road Barham Suffolk

    Discharge of Conditions Application for DC/22/06117 - Discharge of Conditions 5 (Advance Planting), 6 (Landscape Management), 7 (Hard and Soft Landscaping), 9 (Open Space and Play Space), 19 (Fire Hydrants), 28 (Ecology Mitigation and Enhancement Measures), 30 (Landscape and Ecological Management Plan), 31 (Lighting Design Scheme for Biodiversity) and 32 (SPA and Ramsar Site)

    2 Sep 2026 Conditions
  • DC/26/03802 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Trenches 359-366 - as marked on the attached plans.

    2 Sep 2026 Conditions