Skip to content
PlanIndex Get alerts
Menu

Planning application

EARL PUMPING STATION, CHILTON GROVE, LONDON, SE8

Granted Lewisham DC/19/114359 Thames Tunnel Application

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal application to partially discharge Schedule 3 EARPS 8 ? Specification of Accesses (Yeoman Street & Croft Street Construction) amendment for the Earl Pumping Station worksite.

As published by the council, reference DC/19/114359

Application record

Reference
DC/19/114359
Type
Thames Tunnel Application
Status
Decided
Decision
Granted
Received
18 Oct 2019
Validated
18 Oct 2019
Decided
13 Dec 2019
Decision by
Delegated

Site history

Applications at this address on the Lewisham register

This site has had 8 applications since 2019: 7 approved, 0 refused.

  • DC/21/121485 Granted

    EARL PUMPING STATION, CHILTON GROVE, LONDON, SE8

    Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 submission for Approval ? Formal Application under EARPS3 ? Addendum to the Remediation Strategy

    Decided 9 Jun 2021
  • DC/19/114972 Granted

    EARL PUMPING STATION, CHILTON GROVE, LONDON, SE8

    Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal application for the partial discharge Schedule 3 Requirement EARPS 3, Part 1(b) - Contaminated Land (Remediation Strategy) for the Earl Pumping Station (EARPS) worksite.

    Decided 17 Dec 2019
  • DC/19/114590 Decided

    EARL PUMPING STATION, CHILTON GROVE, LONDON, SE8

    Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal Application to partially discharge Schedule 3 EARPS 8 ? Specification of Accesses (Yeoman Street & Croft Street Construction) ? Formal Application for the Earl Pumping Station worksite

    Decided 21 Nov 2019
  • DC/19/114404 Granted

    EARL PUMPING STATION, CHILTON GROVE, LONDON, SE8

    Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (as amended) for approval of a variation to Code of Construction Practice Part B and the partial discharge of Schedule 3 Requirement EARPS 1.

    Decided 17 Dec 2019
  • DC/19/114380 Granted

    EARL PUMPING STATION, CHILTON GROVE, LONDON, SE8

    Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal Application - Partial discharge of Schedule 3 Requirement EARPS 6 ? Worksite Specific Traffic Management Plan (Phase 3 works) - Earl Pumping Station worksite.

    Decided 17 Dec 2019
  • DC/19/114383 Granted

    EARL PUMPING STATION, CHILTON GROVE, LONDON, SE8

    Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal application to partially discharge Schedule 3 Requirement PW6 CoCP Part A Section 5 ? Worksite Specific Construction Logistics Plan (Phase 3 works) for the Earl Pumping Station worksite.

    Decided 17 Dec 2019
  • DC/19/113455 Granted

    EARL PUMPING STATION, CHILTON GROVE, LONDON, SE8

    Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal Application to partially discharge Schedule 3 Requirement PW6 CoCP Part A ? Air Quality Management Plan at Earl Pumping Station, Chilton Grove.

    Decided 8 Oct 2019

Timeline

Dates from the published record

  1. 18 Oct 2019

    Received by Lewisham

  2. 13 Dec 2019

    Decision issued: Granted

  3. 28 Jul 2026

    Added to PlanIndex

What this grant of permission means

Lewisham granted permission on 13 December 2019, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Lewisham's portal will say. Our guide explains the common types.