Planning application
Coombe Boys School College Gardens New Malden KT3 6NT
Works: Demolition
Relates to 24/01386/FUL
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Application for a Non-Material Amendment to Planning Permission ref: 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.). Amendment to building elevations and wording of Condition 26.
As published by the council, reference 25/02519/NMA
Application record
- Reference
- 25/02519/NMA
- Type
- Non-Material Amendment
- Status
- Granted
- Decision
- Granted As published: Application Granted
- Received
- 26 Sep 2025
- Validated
- 26 Sep 2025
- Decided
- 16 Dec 2025
- Ward
- Motspur Park & Old Malden East
- Parish
- New And Old Malden
- Decision by
- Delegated Decision
- Postcode
- KT3 6NT
Site history
Applications at this address on the Kingston upon Thames register
This site has had 13 applications since 2024: 8 approved, 4 refused.
-
26/01040/CLC Granted
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Conditions 31 and 32 (Community Use Agreement) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
-
26/00992/CLC Granted
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 23 (Secure By Design) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
-
26/00923/FUL Granted
Coombe Boys School College Gardens New Malden KT3 6NT
Application under Section 73 of the Town and Country Planning Act 1990 to vary Conditions 10 (sustainable drainage scheme) and 25 (sustainability and energy conservation) for Application Reference Number: 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.) dated 03/12/2024. Variation of wording of Conditions 10 and 25 to reflect the phased nature of the construction programme.
-
26/00766/CLC Granted
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 24 (flood risk) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
-
26/00484/NMA Withdrawn
Coombe Boys School College Gardens New Malden KT3 6NT
Application for a Non-Material Amendment for proposed amendments to the wording of conditions 10 and 25 of Planning Permission ref: 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout)
-
25/03142/CLC Refused
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 31 (community use agreement) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
-
25/03140/CLC Refused
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 24 (flood risk) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
-
25/03141/CLC Refused
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 25 (Energy Evidence) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
-
25/03139/CLC Refused
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 10 (Drainage Scheme Evidence) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
-
25/03138/CLC Granted
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 8 (Fire Safety) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
Timeline
Dates from the published record
-
26 Sep 2025
Received by Kingston upon Thames
-
16 Dec 2025
Decision issued: Application Granted
-
3 Aug 2026
Added to PlanIndex
Related applications
Cases linked to this one on the register
-
24/01386/FUL Granted
Coombe Boys School College Gardens New Malden KT3 6NT
Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.
Documents
Plans, drawings, consultee responses and the officer's report
7 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Kingston upon Thames granted permission on 16 December 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About amendment applications
An amendment application makes limited changes to a permission that already exists; anything beyond modest adjustment needs a fresh application. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 31 (community use agreement) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
Refused Conditions Demolition 2 docs -
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 24 (flood risk) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
Refused Conditions Demolition 2 docs -
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 25 (Energy Evidence) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
Refused Conditions Demolition 2 docs -
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 10 (Drainage Scheme Evidence) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
Refused Conditions Demolition 4 docs -
Coombe Boys School College Gardens New Malden KT3 6NT
Details required for Condition 8 (Fire Safety) of planning permission 24/01386/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.)
Granted Conditions Demolition 2 docs -
Coombe Boys School College Gardens New Malden KT3 6NT
Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Conditions 1 (Approved plans), 10 (Sustainable Drainage Scheme) and 28 (Biodiversity and Nature Conservation) and removal of Condition 34 (Green roof) for Application Reference Number: 23/01623/FUL (Demolition of Existing blocks EFAA, EFAB, EFAC, EFAD, EFAE, EFAG and EFAH, consequential works to retained Block EFAF, and erection of two replacement three-storey school buildings including temporary teaching blocks to be used during the construction period, along with access, landscaping, and associated infrastructure.) dated 16/01/2024. Variation to consist of Removal of Air Source Heat Pump (ASHP) and Relocation of Ground Source Heat Pump (GSHP), Removal of retaining wall & stairs (north of NB01), Removal of green roof , Change in main temporary teaching block layout.
Granted Full applications Demolition 22 docs
Other amendment applications
In Kingston upon Thames
-
26/01832/NMA Granted
93A Mount Road Chessington KT9 1JH
Application for a Non-Material Amendment to Planning Permission 23/03450/FUL (Erection of two storey side extension to create a new dwelling, erection of a single storey rear extension to the existing dwelling.) to allow relocation of the main entrance door together with minor associated alterations to the ground-floor entrance layout.
-
26/01957/NMA Awaiting decision
7 Moorfield Road Chessington KT9 1AU
Application for a Non Material Amendment to planning permission 26/01125/HOUF (Erection of a single storey rear extension, hip to gable roof extension with 2 no. rear dormers, installation of 5 no. front rooflights. Addition of open front entrance porch.) to merge two rear dormers.
-
26/01755/NMA Granted
203 Tudor Drive Kingston Upon Thames KT2 5NU
Application for a Non-Material Amendment to Planning Permission ref: 26/00582/HOU (Erection of single storey rear extension). Amendment to change the approved roof lantern to 2nos. rooflights.
-
26/01940/NMA Awaiting decision
Swan House 51 High Street Kingston Upon Thames KT1 1LQ
Application for a Non-Material Amendment to Planning Permission 23/01865/FUL (Demolition of existing buildings and redevelopment to erect a part three, part four, part five storey building with a lower ground level to provide 758sqm of commercial floor space (Use Class E), 34 residential units (Class C3) and associated and associated communal and open space in addition to associated highways works and landscaping.) to amend the drawings approved under Condition 1 (Approved Plans) to reflect a revised entrance arrangement to Unit 1 and the consequential amendments required to maintain the approved design.
-
26/01651/NMA Granted
13 Pine Walk Surbiton KT5 8NJ
Application for a Non-Material Amendment to Planning Permission ref: 25/00694/HOU (Conversion of an existing garage into habitable space, erection of two storey side, single storey rear and first floor rear extension. Alteration to the roof, enlargement of existing rear dormer to accommodate a habitable room in the loft with installation of 1no front and 1no side rooflight.). Amendment to: 1. Not implement the approved two-storey side extension; 2. Allow minor amendments to the position, size and arrangement of windows and doors; 3. Change the approved external wall finish to a fully rendered finish; and 4. Allow minor refurbishment of the existing front porch.