Planning application
King's Lynn Power Station Willow Road Willows Business Park King's Lynn Norfolk PE34 3RD
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Discarge of Requirements 7, 9, 10, 13, 15, 17 and 18 of Secretary of State's decision dated 18 December 2013: construction and operation of a 2.8km (1.75 miles) 400,000 volt (400kv) overhead electricity transmission line between the proposed King's Lynn B power station and Willows Business Park, Saddlebow, near King's Lynn and the existing 400kV overhead ekectricity transmission line between Norwich main substation and Walpole substation
As published by the council, reference 12/00550/DISC_C
Application record
- Reference
- 12/00550/DISC_C
- Type
- Discharge of Planning condition_C
- Status
- Decided
- Decision
- Granted As published: Discharge of Condition final letter
- Received
- 7 Jan 2015
- Validated
- 7 Jan 2015
- Decided
- 27 Feb 2015
- Ward
- South And West Lynn
- Parish
- King's Lynn
- Decision by
- Discharge of Condition
- Postcode
- PE34 3RD
Site history
Applications at this address on the King’s Lynn and West Norfolk register
This site has had 4 applications since 2015: 4 approved, 0 refused.
-
12/00550/DISC_D Granted
King's Lynn Power Station Willow Road Willows Business Park King's Lynn Norfolk PE34 3RD
Discarge of Requirements 11 of Secretary of State's decision dated 18 December 2013: construction and operation of a 2.8km (1.75 miles) 400,000 volt (400kv) overhead electricity transmission line between the proposed King's Lynn B power station and Willows Business Park, Saddlebow, near King's Lynn and the existing 400kV overhead ekectricity transmission line between Norwich main substation and Walpole substation
-
12/00550/DISC_B Granted
King's Lynn Power Station Willow Road Willows Business Park King's Lynn Norfolk PE34 3RD
Discarge of Requirements 3(2) and 6(1) of Secretary of State's decision dated 18 December 2013: construction and operation of a 2.8km (1.75 miles) 400,000 volt (400kv) overhead electricity transmission line between the proposed King's Lynn B power station and Willows Business Park, Saddlebow, near King's Lynn and the existing 400kV overhead ekectricity transmission line between Norwich main substation and Walpole substation
-
12/00550/DISC_A Granted
King's Lynn Power Station Willow Road Willows Business Park King's Lynn Norfolk PE34 3RD
Discharge of Requirement 14 of Secretary of State's decision dated 18 December 2013: construction and operation of a 2.8km (1.75 miles) 400,000 volt (400kv) overhead electricity transmission line between the proposed King's Lynn B power station and Willows Business Park, Saddlebow, near King's Lynn and the existing 400kV overhead ekectricity transmission line between Norwich main substation and Walpole substation
Timeline
Dates from the published record
-
7 Jan 2015
Received by King’s Lynn and West Norfolk
-
27 Feb 2015
Decision issued: Discharge of Condition final letter
-
14 Sep 2026
Added to PlanIndex
What this grant of permission means
King’s Lynn and West Norfolk granted permission on 27 February 2015, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
King's Lynn Power Station Willow Road Willows Business Park King's Lynn Norfolk PE34 3RD
Discharge of Requirement 14 of Secretary of State's decision dated 18 December 2013: construction and operation of a 2.8km (1.75 miles) 400,000 volt (400kv) overhead electricity transmission line between the proposed King's Lynn B power station and Willows Business Park, Saddlebow, near King's Lynn and the existing 400kV overhead ekectricity transmission line between Norwich main substation and Walpole substation
Granted Conditions -
King's Lynn Power Station Willow Road Willows Business Park King's Lynn Norfolk PE34 3RD
Discarge of Requirements 11 of Secretary of State's decision dated 18 December 2013: construction and operation of a 2.8km (1.75 miles) 400,000 volt (400kv) overhead electricity transmission line between the proposed King's Lynn B power station and Willows Business Park, Saddlebow, near King's Lynn and the existing 400kV overhead ekectricity transmission line between Norwich main substation and Walpole substation
Granted Conditions -
King's Lynn Power Station Willow Road Willows Business Park King's Lynn Norfolk PE34 3RD
Discarge of Requirements 3(2) and 6(1) of Secretary of State's decision dated 18 December 2013: construction and operation of a 2.8km (1.75 miles) 400,000 volt (400kv) overhead electricity transmission line between the proposed King's Lynn B power station and Willows Business Park, Saddlebow, near King's Lynn and the existing 400kV overhead ekectricity transmission line between Norwich main substation and Walpole substation
Granted Conditions -
3 Golden Ball Farm Barns Low Road Saddlebow King's Lynn Norfolk PE34 3FN
Householder: Proposed Rear Oak Frame Extension
Granted Full applications Extension 10 docsDomestic -
Golden Ball Farm Low Road Saddlebow Norfolk PE34 3FN
DISCHARGE OF CONDITIONS 6,7 - Conversion of barn complex to 3 No dwellings
Granted ConditionsSeveral homes -
Golden Ball Farm Low Road Saddlebow Norfolk PE34 3FN
DISCHARGE OF CONDITIONS 6 AND 12: Conversion of barn complex to 3 No dwellings
Granted ConditionsSeveral homes
Other condition discharge and variation applications
In King’s Lynn and West Norfolk
-
15/01838/VAR1B Withdrawn
White House Farm 28 Chapel Road Pott Row Norfolk
Modification of planning obligation, reference LC/S106/16/55 relating to planning application reference 15/01838/OM
-
25/00792/DISC_G Granted
Land West of Knights Hill Village Grimston Road South Wootton Norfolk
DISCHARGE OF CONDITION 19 for PHASES 2 AND 3 ONLY as amended by 25/00792/NMA_1 - Variation of condition 6 attached to planning permission 16/02231/OM and variation of conditions 1, 23 and 25 of planning permission 22/01310/RMM: Residential development of the land to provide up to 600 dwellings, incorporating affordable housing, together with a local centre for uses A1, A2, A3 and/or A5 (600m2) with the total quantum of A1 net sales area not to exceed 279m2 in the alternative, D2 community floorspace (up to 500m2), open space, formal sport pitches, a car park to serve Reffley Wood and associated development to include substations, drainage features, roads, cycle and pedestrian paths and other such works.
-
15/01950/VAR2B Awaiting decision
Land SE of 25 Hall Road Outwell Wisbech Norfolk PE14 8PE
Modification of planning obligation, reference LC/S106/16/44 related to planning application 15/01950/OM
-
25/00060/DISC_A Granted
Land N of 4 Walton Road Marshland St James Norfolk
DISCHARGE OF CONDITIONS 5, 10 AND 11 FROM PLANNING PERMISSION 25/00060/O - Outline Application - 9 Self Build Dwellings
-
24/02087/DISC_E Withdrawn
Flat At 22 High Street Hunstanton Norfolk PE36 5AF
DISCHARGE OF CONDITIONS 3, 4 ATTACHED TO PLANNING PERMISSION 24/02087/F - Extension and alterations to commercial unit