Planning application
Barandon Walk, Hurstway Walk, Testerton Walk, Lancaster West Estate, London, W11
Works: Loft or dormer
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Details required by Condition 4a (submission of details - prior to relevant part of works) of planning permission PP/22/00430 (Refurbishment works to roofs of existing buildings including removal and replacement of roof build up and roof lights; construction of new upstand and parapet; removal and replacement of roof balustrade; replacement of dividing screens; and introduction of thermal insulation to terraces at Deck +03 level)
As published by the council, reference CON/26/02959
Application record
- Reference
- CON/26/02959
- Type
- Discharge of Conditions
- Status
- Validated and Registered
- Received
- 4 Jun 2026
- Ward
- Notting Dale
- Parish
- 12
Site history
Applications at this address on the Kensington and Chelsea register
This site has had 3 applications since 2023.
-
NMA/23/08077 Decided
Barandon Walk, Hurstway Walk, Testerton Walk, Lancaster West Estate, London, W11
Non-material amendment to planning permission 22/00430 to change the trigger for condition 3b and 3c (submission of details - pre-commencement) from pre-commencement to prior to relevant part of work
-
CON/23/06626 Withdrawn
Barandon Walk, Hurstway Walk, Testerton Walk, Lancaster West Estate, London, W11
Details required by condition nos. 3a, 3b (Submission of details - pre-commencement: (a) detailed drawings and material of the 1.1m high balustrade around perimeter of the roofs; and (b) details of floor material for the terraces at Deck +03 level;) and 4a (Submission of details - prior to relevant part of works: (a) details of materials, including sample, to be used on the front face of the new roof parapet of the buildings;) of planning permission 22/00430 (Refurbishment works to roofs of existing buildings including removal and replacement of roof build up and roof lights; construction of new upstand and parapet; removal and replacement of roof balustrade; replacement of dividing screens; and introduction of thermal insulation to terraces at Deck +03 level.)
Timeline
Dates from the published record
-
4 Jun 2026
Received by Kensington and Chelsea
-
20 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 30 July 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Kensington and Chelsea took a median of 84 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
16 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat happens while it is decided
This application is with Kensington and Chelsea for determination, against a statutory target of eight weeks. Over the last year Kensington and Chelsea decided condition discharge and variation applications in a median of 90 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Other condition discharge and variation applications
In Kensington and Chelsea
-
CON/26/03046 Granted
15 Launceston Place, London, W8 5RL
Details required by condition 3 (Submission of details - (a) Elevations and sections depicting form of awning and enclosure, inclusive of means of fixing, and colour and pattern of awning fabric. b) 1:10 elevations and sections of windows demonstrating arrangement, glazing thickness, material, glazing bars, with glazing bars to be integral and true.) of listed building consent 26/01556 (eplacement and enlargement of rear roof dormer and replacement of windows. Removal of front facade drainage downpipe. Installation of surface mounted traditional awnings over rear offshoot 1st floor windows.)
-
CON/26/03047 Withdrawn
2 Sloane Gardens, London, SW1W 8DL
Details required by condition 3 (Submission of details - (a) details of the waterproofing to the vaults) of listed building consent 25/05745 (Alterations to shopfront including lowering of windows, reinstatement of original entrance doors and fanlight and associated works; internal alterations, including restoration of historic features, removal of non-original partitions, revised ceiling arrangement; and reconfiguration of basement for back-of-house use with retention of historic masonry wall.).
-
CON/26/02710 Granted
21 Holland Villas Road, London, W14 8DH
DOCUMENTS AND DRAWINGS ARE NOT AVAILABLE ELECTRONICALLY FOR THIS APPLICATION. PLEASE CALL THE CASE OFFICER. Details required by Condition 3b (submission of details) Details of the framing and glazing of the conservatory rooflight at upper ground floor level and the windows and doors to rear lower ground floor level) of planning permission PP/16/01994 (Creation of basement below lower ground floor level; construction of three storey rear extension, single storey side extensions, dormers to top floor and internal alterations)
-
CON/26/03104 Granted
3 Earls Terrace, London, W8 6LP
Details required by Condition 3d (York Stone Sample) of listed building consent 24/08271 (Reinstatement of missing fireplaces and original room proportions. Installation of double glazed timber frame windows and doors on front and rear facades. Removal of lightings systems and recessed speakers.)
-
CON/26/03015 Granted
30-33 Sloane Street, 49 Pavilion Road, 2-4 Hans Crescent and Garages to rear of Marland House, London, SW1X 9NE
Details required by Condition 16 (Thames Water - works) of planning permission 22/06706 (Partial demolition of 30-33 Sloane Street, retention of fa?ade and erection of a 5-storey building of Class E (commercial, business and service) including installation of shopfronts. Total demolition of no.2 Hans Crescent and erection of replacement building to provide Class E floorspace including a rooftop terrace. Reconfiguration and extension of ground floor of no. 49 Pavillion Road to re-provide Class E floorspace, including service corridor. Provision of substation in basement of no. 4 Hans Crescent. Provision of cycle storage and facilities, waste storage, plant, landscaping, photovoltaic panels, and other ancillary works (Major Application).