Planning application
Site Adjacent To 11 To 13 Scarrots Lane Newport Isle Of Wight
Works: Windows or glazing
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Condition compliance application on 25/01007/FUL relating to Conditions 3 (Sight Lines), 4 (Archaeology), 6 (Materials), 7 (Windows and Doors), 8 (Landscaping), 10 (Noise) and 13 (Drainage) to be discharged
As published by the council, reference 26/01088/DIS
Application record
- Reference
- 26/01088/DIS
- Type
- Discharge of Condition
- Status
- Registered
- Received
- 10 Aug 2026
- Validated
- 10 Aug 2026
- Ward
- Newport Central
- Parish
- Newport & Carisbrooke Community Council
Timeline
Dates from the published record
-
10 Aug 2026
Received by Isle of Wight
-
12 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 5 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Isle of Wight took a median of 57 days over the applications it decided in the last year.
Related applications
Cases linked to this one on the register
- Application: 25/01007/FUL (Decided)
Who's behind it
Company information only, from the register and Companies House
MDJ Architectural Services Ltd Agent, an architecture practice
53 applications on PlanIndex · 98% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
11 documents on file for this application
- MR ISLAND ROADS
- ARCHAEOLOGICAL OFFICER
- PRE-APPLICATION PLANNING ADVICE FROM ISLAND ROADS
- DRAINAGE REPORT
- C4144_101_1_DRAINAGE LAYOUT
- C4144_301_1_CONSTRUCTION DETAILS
- PROGRAMME OF ARCHAEOLOGICAL WORKS
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Isle of Wight for determination, against a statutory target of eight weeks. Over the last year Isle of Wight decided condition discharge and variation applications in a median of 56 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Other condition discharge and variation applications
In Isle of Wight
-
26/01207/DIS Awaiting decision
Neutrik UK Ltd Cothey Way Ryde Isle Of Wight PO33 1QT
Condition compliance application on 25/01012/FUL relating to Condition 3 (Contamination) to be discharged
-
26/01169/DIS Awaiting decision
Masonic Hall 13 Solent Hill Freshwater Isle Of Wight PO40 9TG
Condition compliance application on P/00167/19 for conditions 4 (Landscaping), 5 (Construction Management Plan) and 6 (Arboreal Method Statement)
-
26/01147/DIS Awaiting decision
Toymaster 9 Union Street Ryde Isle Of Wight PO33 2DU
Condition compliance application on 23/02258/FUL for conditions 3 (Construction Management Code) and 4 (Materials and Finishes) in relation to flat 4 and semi-detached houses
-
26/00681/DIS Granted
Barnfield Solar Farm, East Of Wilmingham Lane, West Of Broad Lane, Yarmouth, And Parts Of Broad Lane, B3401 Thorley Street To Station Road, And Warlands Lane, And Shalfleet Substation, Warlands Lane, Shalfleet, Isle Of Wight
Condition compliance application on 22/01793/FUL relating to condition 11 (Construction Environmental Management Plan) to be discharged
-
26/01136/DIS Awaiting decision
Neutrik UK Ltd Cothey Way Ryde Isle Of Wight PO33 1QT
Condition compliance application on 25/01012/FUL relating to Conditions 4 (Construction Management Plan (CMP)), 5 (Engineering detail of junction), 9 (Pedestrian crossing points), 11 (construction environmental management plan (CEMP: Biodiversity), 12 (Habitat Management and Monitoring Plan (HMMP), 13 (Bird/swift boxes), 14 (Soft landscaping), 16 (Lighting), 18 (Delivery management plan) and the Biodiversity Net Gain (BNG) to be discharged