Ourack Wind Farm Grid Connection - Erection and operation of a 132 kilovolt (kV) single circuit connection between the proposed Clash Gour Collector 275/132 kV Substation and the consented Ourack 132/33 kV substation

As published by the council, reference 26/04258/PAN

Application record

Reference
26/04258/PAN
Type
Proposal of Application Notice
Status
Under Consideration
Received
25 Sep 2026
Validated
25 Sep 2026
Ward
Badenoch And Strathspey
Parish
Cromdale And Advie Community Council
Decision by
Delegated Decision

Timeline

Dates from the published record

  1. 25 Sep 2026

    Received by Highland

  2. 5 Oct 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 20 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Highland took a median of 68 days over the applications it decided in the last year.

Documents

Plans, drawings, consultee responses and the officer's report

2 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Highland for determination, against a statutory target of eight weeks. Over the last year Highland's median decision took 68 days. More in our guide to how long planning decisions take.

About this record