Skip to content
PlanIndex Get alerts
Menu

Planning application

Land 2400M SE Of Forsinain Forsinard

Awaiting decision Highland 26/03769/S36 Section 36

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Forsinain Forest Wind Farm - Erection and operation of a wind farm for a period of 40 years, comprising up to 12 wind turbines (10 with a maximum blade tip height of 219m, 2 with a maximum blade tip height of 206m) access tracks, borrow pits, substation, control building, anemometer mast, and ancillary infrastructure. This case will be determined by the Energy Consents Unit. Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationSearch.aspx?T=2 using reference number ECU00004935.

As published by the council, reference 26/03769/S36

Application record

Reference
26/03769/S36
Type
Section 36
Status
Under Consideration
Received
27 Aug 2026
Validated
28 Aug 2026
Ward
North, West And Central Sutherland
Parish
Melvich Community Council
Decision by
Delegated Decision

Comment by 18 September 2026

The council is taking comments on this application until then. Have your say on Highland's portal.

Timeline

Dates from the published record

  1. 27 Aug 2026

    Received by Highland

  2. 28 Aug 2026

    Validated

    Checked as complete and ready for consideration.

  3. 8 Sep 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 23 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Highland took a median of 67 days over the applications it decided in the last year.

Documents

Plans, drawings, consultee responses and the officer's report

472 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Highland for determination, against a statutory target of eight weeks. Over the last year Highland's median decision took 67 days. More in our guide to how long planning decisions take.

About this record