Planning application
Clynelish Distillery Old Brora Distillery Brora KW9 6LR
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Hazardous Substance Consent
As published by the council, reference 26/03628/HSC
Application record
- Reference
- 26/03628/HSC
- Type
- Hazardous Substance Consent
- Status
- Under Consideration
- Received
- 24 Aug 2026
- Validated
- 15 Sep 2026
- Ward
- East Sutherland And Edderton
- Parish
- Brora Community Council
- Decision by
- Delegated Decision
- Postcode
- KW9 6LR
Comment by 9 October 2026
The council is taking comments on this application until then. Have your say on Highland's portal.
Site history
Applications at this address on the Highland register
This site has had 3 applications since 2024: 1 approved, 0 refused.
-
26/01174/LBC Awaiting decision
Clynelish Distillery Old Brora Distillery Brora KW9 6LR
Installation of pipebridge
-
24/03552/FUL Granted
Clynelish Distillery Old Brora Distillery Brora KW9 6LR
Erection of a new steel pipebridge and road crossing for the installation of a new steam line between Old Brora Distillery and Clynliesh
Timeline
Dates from the published record
-
24 Aug 2026
Received by Highland
-
15 Sep 2026
Validated
Checked as complete and ready for consideration.
-
24 Sep 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 10 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Highland took a median of 67 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
13 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Highland for determination, against a statutory target of eight weeks. Over the last year Highland's median decision took 67 days. More in our guide to how long planning decisions take.
About less common application types
This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Clynelish Distillery Old Brora Distillery Brora KW9 6LR
Erection of a new steel pipebridge and road crossing for the installation of a new steam line between Old Brora Distillery and Clynliesh
Granted Full applications 18 docs -
Clynelish Distillery Old Brora Distillery Brora KW9 6LR
100% historically approved · decision due ~13 May
Installation of pipebridge
Awaiting decision Heritage and listed buildings 11 docs
Other less common application types
In Highland
-
26/03415/DEM Granted
Innis Mara 2 Teangue Isle Of Skye IV44 8RE
Demolition of house (Class 70)
-
26/03623/DEM Granted
Former Travis Perkins Woodlands Industrial Estate Woodlands Terrace Grantown-On-Spey PH26 3NA
Demolition of building - Class 70
-
26/03370/DEM Granted
Garten Lawn Acharacle PH36 4JY
Demolition of house - Class 70
-
26/03341/DEM Awaiting decision
Kila 79 Grampian Road Aviemore PH22 1RH
Demolition of house Class 70
-
26/00832/DEM Granted
Corrie Mhor 6 - 7 Academy Street Brora KW9 6QP
Demolition of building