Timeline
Dates from the published record
-
7 Oct 2025
Received by Hammersmith and Fulham
-
10 Oct 2025
Validated
Checked as complete and ready for consideration.
-
25 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Hammersmith and Fulham for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About conditions applications
How this application type works
This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.
Nearby applications
Within 500 metres
-
2025/00904/DET Awaiting decision
ARK Swift Primary Academy Australia Road London W12 7PT
Details to partially discharge Condition 64 (Inclusive Access Management Plan) for Phase 2 of Planning permission (ref. 2020/00596/VAR) dated 30 June 2020.
-
2025/03368/ADV Granted
ARK Swift Primary Academy Australia Road White City Estate London W12 7PT
Display of 1no. illuminated fascia sign including associated support structure to the roof of the Site.
-
2025/03312/DET Granted
ARK Swift Primary Academy Australia Road London W12 7PT
Details to discharge Condition 10 (remediation method statement) and Condition 11 (onward long-term monitoring methodology report); in relation to Phase 2 of Planning permission (ref. 2020/00596/VAR) dated 30 June 2020.
-
2025/02601/DET Awaiting decision
ARK Swift Primary Academy Australia Road London W12 7PT
Details to discharge Condition 24 (combustion plant) in relation to Phase 2 of Planning permission (ref. 2020/00596/VAR) dated 30 June 2020.
-
P/2026/01276/FUL Awaiting decision
1 EDCITY, 1 EDCITY WALK, LONDON, W12 7TF
Change of use from offices (Former Use class B1) to a flexible use as either offices (class E(g)) or education (Use Class F1(a)) at levels 5-8 of Volume C.
-
P/2026/01649/FUL Awaiting decision
Gateway Central, 187 Wood Lane, London, W12 7SA
Change of use of Unit 4 and 5 from Class E(a) (retail) and Class F1(a) (Cookery School) to Class F1(a) (Cookery School) and Class E(b) (Restaurant).
Other conditions applications
In Hammersmith and Fulham
-
P/2026/01938/DET Awaiting decision
421 A North End Road,London,Hammersmith And Fulham,SW6 1NY
Submission of details of full postal address pursuant to condition 9; parking permit scheme pursuant to condition 11; water efficient appliances pursuant to condition 13; mechanical ventilation system pursuant to condition 14; Ultra Low Nox Gas fired boilers to be provided for space heating and domestic hot water pursuant to condition 15; construction logistics plan pursuant to condition 17 of planning permission ref: 2017/03185/FUL granted 19th October 2017.
-
P/2026/01170/DET Granted
Former Bbc Television Centre Wood Lane, London
Details to discharge Condition 58 ( Car Parking Management Plan ) for Plot E & G1, of planning permission (ref. 2016/04585/VAR) dated 22 August 2017.
-
P/2026/01913/DET Awaiting decision
11 Farm Lane, London, SW6 1PU
Submission of details of the installation/commissioning reports of the Zero Emission MCS certified Air Source Heat Pumps to be provided for space heating and hot water for the thirty-one self-contained residential units, pursuant to Condition 18 of planning permission reference: 2022/03329/FR3 dated 19th July 2023.
-
P/2026/01912/DET Awaiting decision
43 Brook Green, London, W6 7EF
Submission of details of a post construction BREEAM assessment pursuant to condition 35 of planning permission ref: 2022/00949/FUL granted 13th July 2023.
-
P/2026/01906/DET Awaiting decision
156 Munster Road, London, SW6 5RA
Submission of details of details of the following external facing materials (including manufacturer's specifications, photographs) pursuant to condition 3; preliminary risk assessment report pursuant to condition 10; site investigation scheme pursuant to condition 11; quantitative risk assessment report pursuant to condition 12; remediation method statement pursuant to condition 13; verification report pursuant to condition 14; onward long-term monitoring methodology report pursuant to condition 15; enhanced sound insulation value DnT,w + Ctr L'nT,w of at least 10dB above the Building Regulations value, for the floor/ceil-ing /wall structures separating different types of rooms/ uses in adjoining dwellings, namely [eg. living room and kitchen above bedroom of separate dwelling] pursuant to condition 16; sound insulation of the floor/ ceiling/walls separating the commercial parts of the premises from dwellings pursuant to condition 17; detailed Demolition and Construction Logistics Plan... read more