Proposal
Works to the main entrance forecourt to improve accessibility, including an extended landing at the front doors, new set of steps and access ramps, associated balustrades, lighting and planting.
As published by the council, reference 2020/02150/FUL
Application record
- Reference
- 2020/02150/FUL
- Type
- Full Detailed Planning Application
- Status
- Pending Consideration
- Received
- 21 Aug 2020
- Validated
- 24 Aug 2020
- Ward
- Avonmore And Brook Green
- Decision by
- Delegated Decision
- Postcode
- W6 7BS
Site history
Applications at this address on the Hammersmith and Fulham register
This site has had 20 applications since 2020: 3 approved, 0 refused.
-
P/2026/02245/DLBC Awaiting decision
St Pauls Girls School Brook Green, London, W6 7BS
Submission of details of method statement detailing the method of demolition and any remedial works pursuant to condition 6; A Method Statement for the protection of internal and external architectural details and historic building fabric, during demolition and construction works pursuant to condition 12 of planning application ref: 2020/01525/LBC granted 13th May 2021.
-
P/2026/02029/DET Awaiting decision
St Pauls Girls School Brook Green, London, W6 7BS
Submission of details of a sample of the metal to be used in connection with acoustic enclosure and plant room pursuant to condition 3 of planning permission ref: 2025/02428/FUL granted 16th January 2026.
-
P/2026/02108/DLBC Awaiting decision
St Pauls Girls School Brook Green, London, W6 7BS
Submission of details of a sample of the metal to be used in connection with acoustic enclosure and plant room pursuant to condition 3 of planning application ref: 2025/02429/LBC granted 16th January 2026.
-
P/2026/01695/TREE Awaiting decision
St Pauls Girls School Brook Green, London, W6 7BS
##Red dot T2 Sycamore -Reduce new growth back to most recent pruning points, leaving the tree at a height of approx. 16metres and spread of approx. 16metres; ##White dot Cabbage tree -Remove to ground level , heavily declining, safety reasons (Black dot tree on separate application as on different site)
-
P/2026/01783/TPO Awaiting decision
St Pauls Girls School Brook Green, London, W6 7BS
Pruning of a Sycamore Tree (T1) subject to Tree Preservation Order TPO/369/05/10 by reducing new growth back to most recent pruning points, leaving the tree at a height of approx. 16metres and spread of approx. 16metres.
-
2025/02429/LBC Granted
St Pauls Girls School Brook Green, London, W6 7BS
Demolition of the existing plant room and erection of a new enlarged replacement plant room located on the eastern side of the main school building at lower ground floor level including the installation of an acoustic encloure on the roof of new plant room; infilling of the existing louvre to eastern elevation boundary wall; alterations at upper ground floor level (eastern elevation of the IT Director's room) to include the installation of a new door to replace the existing window; alterations at lower ground floor level (eastern elevation of the Staff Social Link area) to include the demolition of curtain wall and erection of a new partition wall in between the main building the plant room, installation of a new internal door including the formation of a new walkway with an external door in between the main building and plant room.
-
2025/02428/FUL Granted
St Pauls Girls School Brook Green, London, W6 7BS
Demolition of the existing plant room and erection of a new enlarged replacement plant room located on the eastern side of the main school building at lower ground floor level including the installation of an acoustic enclosure on the roof of new plant room; infilling of the existing louvre to eastern elevation boundary wall; alterations at upper ground floor level (eastern elevation of the IT Director's room) to include the installation of a new door to replace the existing window; alterations at lower ground floor level (eastern elevation of the Staff Social Link area) to include the demolition of curtain wall and erection of a new partition wall in between the main building the plant room, installation of a new internal door including the formation of a new walkway with an external door in between the main building and plant room.
-
2025/01784/DLBC Granted
St Pauls Girls School Brook Green, London, W6 7BS
Submission of details to partially discharge condition 6 (Demolition Method Statement) and condition 12 (Method Statement for the protection of internal and external architectural details and historic building fabric, during demolition and construction works) pursuant to Phase 4 (Staff Hub) of listed building consent ref. 2020/01525/LBC granted 13 May 2021.
-
2024/02802/DET Awaiting decision
St Pauls Girls School Brook Green, London, W6 7BS
Submission of details of a compliance report with details of the two exhaust flues and Central ventilation extraction systems of the Mercer Building in order to mitigate air pollution pursuant to condition 4 of planning permission ref: 2021/02999/FUL granted 9th September 2022.
-
2020/03473/FUL Awaiting decision
St Pauls Girls School Brook Green London W6 7BS
The installation of 3 no. demountable freestanding external Jumbrellas within the Science Courtyard and 1 no. demountable freestanding external Shelter in the Garden Building courtyard.
Timeline
Dates from the published record
-
21 Aug 2020
Received by Hammersmith and Fulham
-
24 Aug 2020
Validated
Checked as complete and ready for consideration.
-
15 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 19 October 2020, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Hammersmith and Fulham took a median of 78 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
36 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat happens while it is decided
This application is with Hammersmith and Fulham for determination, against a statutory target of eight weeks. Over the last year Hammersmith and Fulham decided full applications in a median of 88 days. More in our guide to how long planning decisions take.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
St Pauls Girls School Brook Green London W6 7BS
100% historically approved · decision due ~19 Oct
Works to the main entrance forecourt to improve accessibility, including an extended landing at the front doors, new set of steps and access ramps, associated balustrades, lighting and planting. Works to the internal entrance lobby and adjacent rooms to improve accessibility, safeguarding and security, including provision of a concealed platform lift within the existing steps, installation of new timber framed glazed screens and widened doors within the side walls of the lobby, associated removal and modification of timber panelling, architraves and handrails and decoration within adjacent rooms.
Awaiting decision Heritage and listed buildings Windows or glazing 37 docs -
St Pauls Girls School Brook Green, London, W6 7BS
95% historically approved · decision due ~22 Oct
Submission of details of method statement detailing the method of demolition and any remedial works pursuant to condition 6; A Method Statement for the protection of internal and external architectural details and historic building fabric, during demolition and construction works pursuant to condition 12 of planning application ref: 2020/01525/LBC granted 13th May 2021.
Awaiting decision Conditions Demolition 3 docs -
St Pauls Girls School Brook Green, London, W6 7BS
95% historically approved · decision due ~2 Jan
Submission of details of a compliance report with details of the two exhaust flues and Central ventilation extraction systems of the Mercer Building in order to mitigate air pollution pursuant to condition 4 of planning permission ref: 2021/02999/FUL granted 9th September 2022.
Awaiting decision Conditions 11 docs -
St Pauls Girls School Brook Green, London, W6 7BS
Demolition of the existing plant room and erection of a new enlarged replacement plant room located on the eastern side of the main school building at lower ground floor level including the installation of an acoustic encloure on the roof of new plant room; infilling of the existing louvre to eastern elevation boundary wall; alterations at upper ground floor level (eastern elevation of the IT Director's room) to include the installation of a new door to replace the existing window; alterations at lower ground floor level (eastern elevation of the Staff Social Link area) to include the demolition of curtain wall and erection of a new partition wall in between the main building the plant room, installation of a new internal door including the formation of a new walkway with an external door in between the main building and plant room.
Granted Heritage and listed buildings Demolition Windows or glazing 31 docsSmall domestic -
St Pauls Girls School Brook Green, London, W6 7BS
Demolition of the existing plant room and erection of a new enlarged replacement plant room located on the eastern side of the main school building at lower ground floor level including the installation of an acoustic enclosure on the roof of new plant room; infilling of the existing louvre to eastern elevation boundary wall; alterations at upper ground floor level (eastern elevation of the IT Director's room) to include the installation of a new door to replace the existing window; alterations at lower ground floor level (eastern elevation of the Staff Social Link area) to include the demolition of curtain wall and erection of a new partition wall in between the main building the plant room, installation of a new internal door including the formation of a new walkway with an external door in between the main building and plant room.
Granted Full applications Demolition Windows or glazing 31 docsSmall domestic -
St Pauls Girls School Brook Green, London, W6 7BS
97% historically approved · decision due ~4 Sep
##Red dot T2 Sycamore -Reduce new growth back to most recent pruning points, leaving the tree at a height of approx. 16metres and spread of approx. 16metres; ##White dot Cabbage tree -Remove to ground level , heavily declining, safety reasons (Black dot tree on separate application as on different site)
Awaiting decision Trees 4 docs
Other full applications
In Hammersmith and Fulham
-
P/2026/01173/FUL Granted
343 Fulham Palace Road, London, SW6 6TD
Installation of a new structure with door opening and the erection of obscure glazed screen around part of the flat roof at third floor level to the rear elevation in connection with its use as a terrace.
-
P/2026/01729/FR3 Granted
24-26 Matheson Road, London, W14 8SW
Replacement of existing vehicular entrance gates with new vehicular entrance gates and railings in between building no. 24-26 Matheson Road and no. 32 Matheson Road; installation of a pedestrian entrance gate in between building no. 24-26 Matheson Road and no. 22 Matheson Road.
-
P/2026/01645/FUL Granted
10 Cathnor Road, London, W12 9JA
Replacement of existing single glazed timber framed sash windows to the front elevation with double glazed timber framed sash windows and the existing single glazed rear elevations with new double glazed timber sash windows; and replacement of existing single glazed timber framed basement entrance door to the rear elevation with a new double glazed composite GRP door.
-
P/2026/01106/FUL Granted
44 Flat B,Studland Street,London,Hammersmith And Fulham,W6 0JS
Replacement of all existing timber framed windows at first floor level with new double glazed timber framed windows. Replacement of existing rooflight to the roof of the rear back addition.
-
P/2026/01614/FUL Granted
59A Chesson Road, London, W14 9QT
Erection of an additional floor at roof level.