Land At Widnes Waterfront Bounded By Earle Road, Tan House Lane, Moss Bank Road, Gorsey Road, Johnson's Lane; North Of St Helens Canal And Warrington & Stockport Railway Line At Moss Bank Widnes WA8 0GY

Awaiting decision Halton 26/00081/OUTEIA Outline/Env.Impact Assessment

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

HYBRID PLANNING APPLICATION COMPRISING: FULL PLANNING application for construction, engineering and change of use (part retrospective) including; new and altered means of access at Earle Road and Moss Bank Road and related transport infrastructure; remodelling/regrading of land; related engineering and infrastructure works; drainage strategy; landscaping; means of enclosure; enabling works and ancillary development; and temporary change of use for open storage, storage of vehicles including commercial vehicles and self-storage (through shipping containers); and OUTLINE application (with all matters reserved except for Access) for a phased development comprising up to 169,800 sqm of total floorspace across commercial / industrial / warehousing / waste management facilities including: - Up to 162,850 sqm for B2/B8 uses (with ancillary offices) - Up to 75,320 sqm for a data centre (sui generis) - A battery energy storage system - Up to 28,610 sqm of E(g)(iii) floorspace (light industrial) - Up to 600 sqm retail / food & drink (E(a) / E(b)) - Up to 500 sqm indoor sport/recreation (E(d)) - Up to 500 sqm for a creche, nursery or day centre (E(f)) Plus associated works including site remediation, internal roads, parking, servicing, cycle and pedestrian routes, landscaping, SuDS and other ancillary infrastructure at

As published by the council, reference 26/00081/OUTEIA

Application record

Reference
26/00081/OUTEIA
Type
Outline/Env.Impact Assessment
Status
Registered
Received
27 Feb 2026
Validated
11 Mar 2026
Ward
Central & West Bank
Parish
No Parish
Postcode
WA8 0GY

Timeline

Dates from the published record

  1. 27 Feb 2026

    Received by Halton

  2. 11 Mar 2026

    Validated

    Checked as complete and ready for consideration.

  3. 21 Jul 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 6 May 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Halton took a median of 62 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

Plan Red Ltd Agent, registered in Manchester

Active · incorporated 2021 · Manchester

34 applications on PlanIndex · across 8 councils · 80% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

307 documents on file for this application

  • CATALYST BUSINESS PARK WIDNES HEALTH IMPACT ASSESSMENT Supporting Documents · 23 Apr 2026
  • 20260206 - UES BNG STATUTORY METRIC (MACROS-ENABLED) - LAND OFF MOSS STREET (DZS Biodiversity · 12 Mar 2026
  • 04. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - APPENDIX 3 Supporting Documents · 05 Mar 2026
  • 01. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - MAIN REPORT Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 4 CROSS SECTIONS SH1 Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 4 CROSS SECTIONS SH2 Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 4 CUT AND FILL Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 5 EXISTING CONTOURS Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 5 CUT AND FILL Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 5 CROSS SECTIONS Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 5 COMPLETED Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 4 PROPOSED CONTOURS Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 4 EXISTING CONTOURS Plans · 27 Feb 2026
  • ES VOLUME 3_EIA PARAMETER PLAN - HEIGHTS Plans · 27 Feb 2026
  • ES VOLUME 3_EIA PARAMETER PLAN - BUILT EXTENTS Plans · 27 Feb 2026
  • ES VOLUME 3_EIA PARAMETER PLAN - ACCESS Plans · 27 Feb 2026
  • ES VOLUME 3_DRAWING 8.1 SENSITIVE RECEPTOR LOCATION PLAN Plans · 27 Feb 2026
  • ES VOLUME 3_DRAWING 17.1_COMMITTED AND REASONABLY FORESEEABLE PROJECTS PLAN Plans · 27 Feb 2026
  • ES VOLUME 3_DRAWING 14.1_ILLUSTRATIVE LANDSCAPE MASTERPLAN Plans · 27 Feb 2026
  • ES VOLUME 3_DRAWING 11.1_BASELINE SURFACE WATER ENVIRONMENT Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 5 TEMPORARY DRAINAGE Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 5 PROPOSED CONTOURS Plans · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 5 EXISTING CONTOURS Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.3_NATIONAL LANDSCAPE CHARACTER Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.2_ACCESS AND CIRCULATION REGIONAL ROUTES Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.1_ACCESS AND CIRCULATION PROW Plans · 27 Feb 2026
  • ES VOLUME 3_EXISTING SITE PLAN-DEVELOPMENT ZONE 5 Plans · 27 Feb 2026
  • ES VOLUME 3_EXISTING SITE PLAN-DEVELOPMENT ZONE 4 Plans · 27 Feb 2026
  • ES VOLUME 3_EXISTING SITE PLAN-DEVELOPMENT ZONE 3 Plans · 27 Feb 2026
  • ES VOLUME 3_EXISTING SITE PLAN-DEVELOPMENT ZONE 2 Plans · 27 Feb 2026
  • ES VOLUME 3_EXISTING SITE PLAN - SITE WIDE BOUNDARY PLAN Plans · 27 Feb 2026
  • ES VOLUME 3_EXISTING SITE PLAN - DEVELOPMENT ZONE 1 Plans · 27 Feb 2026
  • ES VOLUME 3_EIA PARAMETER PLAN - LANDSCAPE Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.9_ZONE OF THEORETICAL VISIBILITY (ZTV) PHASE 1 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.8_ZONE OF THEORETICAL VISIBILITY (ZTV) ALL DEVELOPMENT Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.7_TOPOGRAPHY Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.6_ENVIRONMENTAL DESIGNATIONS Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.5_LANDSCAPE DESIGNATIONS Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.4_LOCAL LANDSCAPE CHARACTER Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.13_VIEWPOINT LOCATION MAP Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.12_ZONE OF THEORETICAL VISIBILITY (ZTV) PHASE 4 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.11_ZONE OF THEORETICAL VISIBILITY (ZTV) PHASES 1 TO 3 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.10_ZONE OF THEORETICAL VISIBILITY (ZTV) PHASES 1 AND 2. Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.24_VIEWPOINT 5 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.23_VIEWPOINT 4 PHASE 2 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.22_VIEWPOINT 4 PHASE 2 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.21_VIEWPOINT 4 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.20_VIEWPOINT 3 PHASE 3 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.19_VIEWPOINT 3 PHASE 2 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.18_VIEWPOINT 3 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.17_VIEWPOINT 2 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.16_VIEWPOINT 1 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.15_VIEWPOINT 1 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.14_VIEWPOINT 1 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.63_VIEWPOINT 21 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.62_VIEWPOINT 20 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.61_VIEWPOINT 19 PHASE 4 OPERATIONAL (YEAR 15) WIREFRAME Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.60_VIEWPOINT 19 PHASE 4 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.59_VIEWPOINT 19 PHASE 4 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.58_VIEWPOINT 19 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.57_VIEWPOINT 18 PHASE 4 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.56_VIEWPOINT 18 PHASE 4 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.55_VIEWPOINT 18 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.54_VIEWPOINT 17 PHASE 4 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.53_VIEWPOINT 17 PHASE 4 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.52_VIEWPOINT 17 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.51_VIEWPOINT 16 PHASE 3 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.50_VIEWPOINT 16 PHASE 3 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.49_VIEWPOINT 16 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.48_VIEWPOINT 15 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.47_VIEWPOINT 14 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.46_VIEWPOINT 13B Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.45_VIEWPOINT 13A Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.44_VIEWPOINT 12 PHASE 4 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.43_VIEWPOINT 12 PHASE 4 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.42_VIEWPOINT 12 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.41_VIEWPOINT 11 PHASE 4 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.40_VIEWPOINT 11 PHASE 4 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.39_VIEWPOINT 11 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.38_VIEWPOINT 10 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.37_VIEWPOINT 9 PHASE 4 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.36_VIEWPOINT 9 PHASE 4 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.35_VIEWPOINT 9 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.34_VIEWPOINT 8 PHASES 3 AND 4 OPERATIONAL (YEAR 14) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.33_VIEWPOINT 8 PHASE 4 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.32_VIEWPOINT 8 PHASE 3 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.31_VIEWPOINT 8 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.30_VIEWPOINT 7. Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.29_VIEWPOINT 6 PHASE 3 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.28_VIEWPOINT 6 PHASE 3 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.27_VIEWPOINT 6 Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.26_VIEWPOINT 5 PHASE 2 OPERATIONAL (YEAR 15) Plans · 27 Feb 2026
  • ES VOLUME 3_FIGURE 14.25_VIEWPOINT 5 PHASE 2 OPERATIONAL (YEAR 1) Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 4 - DEVELOPMENT ZONE 5 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 4 - DEVELOPMENT ZONE 4 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 4 - DEVELOPMENT ZONE 3 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 4 - DEVELOPMENT ZONE 2 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 4 - DEVELOPMENT ZONE 1 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 3 - DEVELOPMENT ZONE 5 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 3 - DEVELOPMENT ZONE 4 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 3 - DEVELOPMENT ZONE 3 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 3 - DEVELOPMENT ZONE 2 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 3 - DEVELOPMENT ZONE 1 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 2 - DEVELOPMENT ZONE 5 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 2 - DEVELOPMENT ZONE 4 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 2 - DEVELOPMENT ZONE 3 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 2 - DEVELOPMENT ZONE 2 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 2 - DEVELOPMENT ZONE 1 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 1 - DEVELOPMENT ZONE 5 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 1 - DEVELOPMENT ZONE 4 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 1 - DEVELOPMENT ZONE 3 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 1 - DEVELOPMENT ZONE 2 Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLAN_PHASE 1 - DEVELOPMENT ZONE 1 Plans · 27 Feb 2026
  • ES VOLUME 3_PROPOSED WIDNES WATERFRONT MASTERPLAN Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLANS - PHASE 4_SITE WIDE Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLANS - PHASE 3_SITE WIDE Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLANS - PHASE 2_SITE WIDE Plans · 27 Feb 2026
  • ES VOLUME 3_PHASING PLANS - PHASE 1_SITE WIDE Plans · 27 Feb 2026
  • 10. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - APPENDIX 9 Supporting Documents · 27 Feb 2026
  • 09. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - APPENDIX 8 Supporting Documents · 27 Feb 2026
  • 08. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - APPENDIX 7 Supporting Documents · 27 Feb 2026
  • 07. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - APPENDIX 6 Supporting Documents · 27 Feb 2026
  • 06. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - APPENDIX 5 Supporting Documents · 27 Feb 2026
  • 05. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - APPENDIX 4 PART 2 Supporting Documents · 27 Feb 2026
  • 05. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - APPENDIX 4 PART 1 Supporting Documents · 27 Feb 2026
  • 03. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - APPENDIX 2 Supporting Documents · 27 Feb 2026
  • 02. 0702-07 WIDNES - PRELIMINARY UPS 0.2 - APPENDIX 1 Supporting Documents · 27 Feb 2026
  • BNG STATUTORY METRIC Biodiversity · 27 Feb 2026
  • 15226A- SOLAR PHOTOVOLTAIC GLINT AND GLARE STUDY Supporting Documents · 27 Feb 2026
  • 1256-MCAU-IND-001-DESIGN AND ACCESS STATEMENT_PART5 Supporting Documents · 27 Feb 2026
  • 1256-MCAU-IND-001-DESIGN AND ACCESS STATEMENT_PART4 Supporting Documents · 27 Feb 2026
  • 1256-MCAU-IND-001-DESIGN AND ACCESS STATEMENT_PART3 Supporting Documents · 27 Feb 2026
  • 1256-MCAU-IND-001-DESIGN AND ACCESS STATEMENT_PART2 Supporting Documents · 27 Feb 2026
  • 1256-MCAU-IND-001-DESIGN AND ACCESS STATEMENT_PART1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 9_AIR QUALITY AND DUST Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 8_TRAFFIC AND TRANSPORT Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 7_SOCIO ECONOMICS Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 10_NOISE AND VIBRATION Supporting Documents · 27 Feb 2026
  • ECONOMIC BENEFITS AND WORKFORCE ASSESSMENT FINAL Supporting Documents · 27 Feb 2026
  • ECONOMIC BENEFITS AND WORKFORCE ASSESSMENT FINAL Supporting Documents · 27 Feb 2026
  • BREEAM NC V7 SUMMARY Supporting Documents · 27 Feb 2026
  • P24083-007A PROPOSED SITE ACCESS ROUNDABOUT Plans · 27 Feb 2026
  • APPLICATIONFORMREDACTED Application Form · 27 Feb 2026
  • P24068-011 SWEPT PATH ANALYSIS PROPOSED SIGNALISATION SITE 1 ACCESS Plans · 27 Feb 2026
  • NON TECHNICAL SUMMARY Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTERS 1 TO 6 INTRODUCTORY CHAPTERS Supporting Documents · 27 Feb 2026
  • FICON CATALYST BUSINESS PARK FCEMP Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 19_STATEMENT OF SIGNIFICANCE AND CONCLUSIONS Supporting Documents · 27 Feb 2026
  • FICON CATALYST BUSINESS PARK CPHSP Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 18_MITIGATION AND MONITORING Supporting Documents · 27 Feb 2026
  • FI048-006 P1 FEE LETTER (WARRINGTON) Supporting Documents · 27 Feb 2026
  • FI048-004 P1 FEE LETTER (HALTON) Supporting Documents · 27 Feb 2026
  • FI048-005 P1 CATALYST BUSINESS PARK HEADS OF TERMS Plans · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 17_CUMULATIVE EFFECTS Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 16_LIGHTING Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 15_HUMAN HEALTH Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 14_LANDSCAPE AND VISUAL Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 13_ECOLOGY AND BIODIVERSITY Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 12_GROUND_CONDITIONS Supporting Documents · 27 Feb 2026
  • ES VOLUME 1_CHAPTER 11_WATER ENVIRONMENT Supporting Documents · 27 Feb 2026
  • FI048-003 P1 CATALYST BUSINESS PARK DEVELPOMENT SCHEDULE Supporting Documents · 27 Feb 2026
  • FI048-002 P1 COVERING LETTER (HALTON AND WARRINGTON) Supporting Documents · 27 Feb 2026
  • FI048-001 P1 CATALYST BUSINESS PARK PLANNING STATEMENT Supporting Documents · 27 Feb 2026
  • FI DEVELOPMENT WIDNES SOCIAL VALUE AND SKILLS PROPOSAL (006) Supporting Documents · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.9_PHASE 3 OPERATION (DAYTIME) Plans · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.8_PHASE 2 OPERATION (NIGHT-TIME) Plans · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_E_PART3 Supporting Documents · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.7_PHASE 2 OPERATION (DAYTIME) Plans · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_E_PART2 Supporting Documents · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.6_PHASE 1 OPERATION (NIGHT TIME) Plans · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_E_PART1 Supporting Documents · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.5_PHASE 1 OPERATION (DAYTIME) Plans · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.4_PHASE 3 CONSTRUCTION (NIGHT TIME) Plans · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_D Supporting Documents · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.3_PHASE 3 CONSTRUCTION (DAYTIME) Plans · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_C Supporting Documents · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.2_PHASE 2 CONSTRUCTION (NIGHT TIME) Plans · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_B_PART2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_B_PART1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_A Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 1.1_EIA SCOPING OPINION Supporting Documents · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.1_PHASE 2 CONSTRUCTION (DAYTIME) Plans · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.12_PHASE 4 OPERATION (NIGHT-TIME) Plans · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.11_PHASE 4 OPERATION (DAYTIME) Plans · 27 Feb 2026
  • ES_VOLUME 3_DRAWING 10.10_PHASE 3 OPERATION (NIGHT-TIME) Plans · 27 Feb 2026
  • ES_VOLUME 2_APPENDIX 9.2 DETAILED MONITORING TECHNICAL INFORMATION Plans · 27 Feb 2026
  • ES_VOLUME 2_APPENDIX 9.1 DETAILED MODELLING TECHNICAL INFORMATION Plans · 27 Feb 2026
  • ES_VOLUME 2_APPENDIX 8.2_TRAVEL PLAN Supporting Documents · 27 Feb 2026
  • ES_VOLUME 2_APPENDIX 8.1 TRANSPORT ASSESSMENT Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_L_PART2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_L_PART1 Supporting Documents · 27 Feb 2026
  • ES_VOLUME 2_APPENDIX 16.1_LIGHTING TECHNICAL REPORT PART 4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_K_PART2 Supporting Documents · 27 Feb 2026
  • ES_VOLUME 2_APPENDIX 16.1_LIGHTING TECHNICAL REPORT PART 3 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_K_PART1 Supporting Documents · 27 Feb 2026
  • ES_VOLUME 2_APPENDIX 16.1_LIGHTING TECHNICAL REPORT PART 2 Supporting Documents · 27 Feb 2026
  • ES_VOLUME 2_APPENDIX 16.1_LIGHTING TECHNICAL REPORT PART 1 Plans · 27 Feb 2026
  • ES_VOLUME 2_APPENDIX 10.1_NOISE IMPACT ASSESSMENT Supporting Documents · 27 Feb 2026
  • Z69232A WIDNES INDUSTRIAL SITES BREEAM_NC_V6.1_PRE-ASSESSMENT_03-09-25MA Supporting Documents · 27 Feb 2026
  • Z69232.3 HALTON WIDNES DEVELOPMENT ZONES 1-5 ENERGY STATEMENT_19-01-26MA Supporting Documents · 27 Feb 2026
  • Z69232 WIDNES INDUSTRIAL SITES 1-5 BREEAM NC 2018 RIBA STAGE 2 EVIDENCE SCHEDULE Supporting Documents · 27 Feb 2026
  • WIDNES WASTE MANAGEMENT PLAN_FINAL Supporting Documents · 27 Feb 2026
  • WIDNES STATEMENT OF COMMUNITY INVOLVEMENT Supporting Documents · 27 Feb 2026
  • WIDNES - VALIDATION AND APPLICATION CHECKLIST V1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_J Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_I Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_H Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_G Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_F Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_E_PART4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.5_GREAT CRESTED NEWT EDNA AND IMPACT ASSESSMENT Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.1_PRELIMINARY ECOLOGICAL APPRAISAL_PART4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.1_PRELIMINARY ECOLOGICAL APPRAISAL_PART3 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.1_PRELIMINARY ECOLOGICAL APPRAISAL_PART2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.1_PRELIMINARY ECOLOGICAL APPRAISAL_PART1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_O Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_N_PART2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_N_PART1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_M_PART2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 11.1_FRA AND DRAINAGE STRATEGY_APPENDIX_M_PART1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.9_SHADOW HABITAT REGULATIONS ASSESSMENT Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.8_WINTERING BIRD SURVEY REPORT Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.7_OTTER AND WATER VOLE SURVEY REPORT Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.6_GROUND LEVEL TREE ASSESSMENT - DEVELOPMENT ZONE 5_PART Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.6_GROUND LEVEL TREE ASSESSMENT - DEVELOPMENT ZONE 5_PART Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.10_BNG BIODIVERSITY STATEMENT_PART5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.10_BNG BIODIVERSITY STATEMENT_PART4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.10_BNG BIODIVERSITY STATEMENT_PART3 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.10_BNG BIODIVERSITY STATEMENT_PART2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 13.10_BNG BIODIVERSITY STATEMENT_PART1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.3_LANDSCAPE STRATEGY PART 4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.3_LANDSCAPE STRATEGY PART 3 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.3_LANDSCAPE STRATEGY PART 2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.3_LANDSCAPE STRATEGY PART 1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.2_PART E_ARBORICULTURAL IMPACT ASSESSMENT Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.2_PART D_ARBORICULTURAL IMPACT ASSESSMENT Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.2_PART C_ARBORICULTURAL IMPACT ASSESSMENT Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.2_PART B_ARBORICULTURAL IMPACT ASSESSMENT Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.2_PART A_ ARBORICULTURAL IMPACT ASSESSMENT Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.1_ LANDSCAPE AND VISUAL METHODOLOGY Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-4_REMEDIATIONVERIFICATIONSTRATEGY_DZ1_PART1OF1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-3_GEOENVIRONMENTALASSESSMENT_DZ1_PART1OF1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-2_SIFACTUALREPORT_DZ1_PART1OF1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-1_PRELIMINARYRISKASESSMENT_DZ1_PART5OF5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-1_PRELIMINARYRISKASESSMENT_DZ1_PART4OF5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-1_PRELIMINARYRISKASESSMENT_DZ1_PART3OF5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-1_PRELIMINARYRISKASESSMENT_DZ1_PART2OF5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-1_PRELIMINARYRISKASESSMENT_DZ1_PART1OF5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.4_ LOCAL AUTHORITY CONSULTATION Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX 14.3_LANDSCAPE STRATEGY PART 5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-9_REMEDIATIONVERIFICATIONSTRATEGY_DZ2_PART1OF1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-8_DETAILEDQUANTIATIVERISKASSESSMENT_DZ2_PART1OF1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-7_GEOENVIRONMENTALASSESSMENT_DZ2_PART1OF1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-6_SIFACTUALREPORT_DZ2_PART1OF1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-5_PRELIMINARYRISKASSESSMENT_DZ2_PART4OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-5_PRELIMINARYRISKASSESSMENT_DZ2_PART3OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-5_PRELIMINARYRISKASSESSMENT_DZ2_PART2OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-5_PRELIMINARYRISKASSESSMENT_DZ2_PART1OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-10_PRELIMINARYRISKASSESSMENT_DZ3_PART2OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-10_PRELIMINARYRISKASSESSMENT_DZ3_PART1OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-15_PRELIMINARYRISKASSESSMENTDZ4_PART2OF6 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-15_PRELIMINARYRISKASSESSMENTDZ4_PART1OF6 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-14_REMEDIATIONVERIFICATIONSTRATEGY_DZ3_PART1OF1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-13_DETAILEDQUANTIATIVERISKASSESSMENT_DZ3_PART1OF1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-12_GEOENVIRONMENTALASSESSMENT_DZ3_PART2OF2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-12_GEOENVIRONMENTALASSESSMENT_DZ3_PART1OF2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-11_SIFACTUALREPORT_DZ3_PART2OF2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-11_SIFACTUALREPORT_DZ3_PART1OF2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-10_PRELIMINARYRISKASSESSMENT_DZ3_PART4OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-10_PRELIMINARYRISKASSESSMENT_DZ3_PART3OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-17_JOHNSONSLN_SURFACEWATERRESULTS_DZ4_PART1OF1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-16_CONEPENETRATIONTESTINGREPORT_DZ4-DZ5_PART5OF5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-16_CONEPENETRATIONTESTINGREPORT_DZ4-DZ5_PART4OF5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-16_CONEPENETRATIONTESTINGREPORT_DZ4-DZ5_PART3OF5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-16_CONEPENETRATIONTESTINGREPORT_DZ4-DZ5_PART2OF5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-16_CONEPENETRATIONTESTINGREPORT_DZ4-DZ5_PART1OF5 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-15_PRELIMINARYRISKASSESSMENTDZ4_PART6OF6 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-15_PRELIMINARYRISKASSESSMENTDZ4_PART5OF6 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-15_PRELIMINARYRISKASSESSMENTDZ4_PART4OF6 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-15_PRELIMINARYRISKASSESSMENTDZ4_PART3OF6 Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 1 EXISTING CONTOURS Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 1 CUT AND FILL Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 1 CROSS SECTION Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 1 COMPLETED Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 2 HIGHWAY LONG SECTION Supporting Documents · 27 Feb 2026
  • ES VOLUME 3 DEVELOPMENT ZONE 3 CUT AND FILL Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-18_PRELIMINARYRISKASSESSMENT_DZ5_PART4OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-18_PRELIMINARYRISKASSESSMENT_DZ5_PART3OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-18_PRELIMINARYRISKASSESSMENT_DZ5_PART2OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 2_APPENDIX_12-18_PRELIMINARYRISKASSESSMENT_DZ5_PART1OF4 Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 3 AND 4 HIGHWAY LONG SECTION Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 3 AND 4 COMPLETED Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 2 TEMPORARY DRAINAGE Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 2 PROPOSED CONTOURS Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 2 EXISTING CONTOURS Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 2 CUT AND FILL Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 2 CROSS SECTIONS Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 2 COMPLETED Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 1 TEMPORARY DRAINAGE Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 1 PROPOSED CONTOURS Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 3 PROPOSED CONTOURS Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 3 EXISTING CONTOURS Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 3 CROSS SECTIONS SH2 Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 3 CROSS SECTIONS SH1 Supporting Documents · 27 Feb 2026
  • ES VOLUME 3_DEVELOPMENT ZONE 3 AND 4 TEMPORARY DRAINAGE Supporting Documents · 27 Feb 2026

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Halton for determination, against a statutory target of eight weeks. Over the last year Halton's median decision took 62 days. More in our guide to how long planning decisions take.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Blue Phoenix Johnsons Lane Widnes Cheshire WA8 0SJ

    26/00140/NMA Submitted 14 Apr 2026 100 yards away

    Application for Non-Material Amendment to planning permission 22/00434/WST to amend approved plans:- Site Layout (P19043-SMCE-ZZ-XX-DR-C-0010 - Revision P02), Paving Layout (P19043-2021-0727-sk02 - Revision P01) and Emergency Access (P19043-SMCE-ZZ-XX-DR-C-0025 - Revision P01) at

    Granted Amendments 6 docs
  • Blue Phoenix Johnsons Lane Widnes Cheshire WA8 0SJ

    26/00336/COND Submitted 2 Sep 2026 100 yards away

    97% historically approved · decision due ~28 Oct

    Application to discharge condition no. 8 (Landscape and Ecological Management Plan) of planning permission 22/00434/WST at

    Awaiting decision Conditions 2 docs
  • Site B Johnsons Lane Widnes Cheshire WA8 0SJ

    24/00402/COND Submitted 25 Oct 2024 200 yards away

    Application to discharge condition no 12 (Boundary Treatments Scheme) of planning permission 20/00164/WST at

    Decided Conditions 5 docs
  • Blue Phoenix Johnsons Lane Widnes WA8 0SJ

    26/00411/WST Submitted 24 Jul 2026 350 yards away

    97% historically approved · decision due ~15 Dec

    Proposed extension of existing processing building at

    Awaiting decision Extension
  • Bowman Works Gorsey Lane Widnes Cheshire WA8 0YZ

    26/00208/NMA Submitted 8 Jun 2026 0.3 miles away

    Application for Non Material Amendment to planning permission 21/00498/FUL for alterations to the Production Area and the Magnetite Storage Section at

    Granted Amendments
  • Phase 2 Land Off Gorsey Lane Widnes Cheshire WA8 0YZ

    21/00382/FUL Submitted 21 Jun 2021 0.3 miles away

    Proposed erection of electricity sub-station at

    Granted Full applications 8 docs

In Halton

  • 25/00328/OUT Granted

    136 Hough Green Road Widnes Cheshire WA8 4PG

    Outline planning application (with all matters other than access, layout and scale reserved) for the demolition of existing derelict nursery building and proposed 4 detached house development with alterations to the access at

    Received 21 Jul, published by the council 21 Jul 2026 Outline
  • 26/00348/OUT Awaiting decision

    Lunts Bridge Farm Lunts Heath Road Widnes Cheshire WA8 5RY

    Outline planning application (with all matters reserved) for one dwelling at

    Received 8 Sep, published by the council 10 Sep 2026 Outline
  • 26/00323/OUT Awaiting decision

    192 Runcorn Road Moore Warrington Cheshire WA4 6SY

    Outline planning application (with all matters reserved) for the construction of detached single storey dwelling and detached garage at

    Received 21 Aug, published by the council 27 Aug 2026 Outline
  • 26/00089/ADJ Awaiting decision

    Land Adjacent To Cronton Road Cronton Knowsley

    Adjoining Authority Consultation by Knowsley Metropolitan Borough Council regarding an Outline Planning Application (including details of access with all other matters reserved) for the erection of up to 120 dwellings (Use Class C3) and other associated works at

    Received 13 Mar, published by the council 21 Jul 2026 Outline
  • 25/00471/OUT Awaiting decision

    141 Runcorn Road Moore Warrington Cheshire WA4 6UQ

    Outline planning application (with all matters reserved) for the erection of 9 dwellings with associated landscaping and new access to Runcorn Road at

    Received 13 Nov, published by the council 21 Jul 2026 Outline