Planning application
Land Adjacent To 30 Spinnaker Road Gloucester
Relates to 25/01016/FUL
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Discharge of Conditions 8 (flood evacuation manegement plan) and 16 (waste minimisation statement) of permission ref. 25/01016/FUL
As published by the council, reference 26/00717/CONDIT
Application record
- Reference
- 26/00717/CONDIT
- Status
- Unknown
- Received
- 7 Aug 2026
- Validated
- 7 Aug 2026
Site history
Applications at this address on the Gloucester register
This site has had 3 applications since 2025: 1 approved, 1 refused.
-
25/01016/FUL Granted
Land Adjacent To 30 Spinnaker Road Gloucester
Retrospective Change of Use to B8 storage including ground levelling works, retention of hardstanding and office container unit and proposed assembly and storage building, palisade fencing, new vehicular access and landscaping.
-
25/00788/LAW Refused
Land Adjacent To 30 Spinnaker Road Gloucester
Application for certificate of lawful development - Lawfulness of engineering operation to create elevated ground levels
Timeline
Dates from the published record
-
7 Aug 2026
Received by Gloucester
-
13 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 2 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Gloucester took a median of 56 days over the applications it decided in the last year.
Related applications
Cases linked to this one on the register
-
25/01016/FUL Granted
Land Adjacent To 30 Spinnaker Road Gloucester
Retrospective Change of Use to B8 storage including ground levelling works, retention of hardstanding and office container unit and proposed assembly and storage building, palisade fencing, new vehicular access and landscaping.
What happens while it is decided
This application is with Gloucester for determination, against a statutory target of eight weeks. Over the last year Gloucester's median decision took 56 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Gloucester's portal will say. Our guide explains the common types.