Central Engineering Works Lower Lydbrook Lydbrook Gloucestershire GL17 9NA

Awaiting decision Forest of Dean P0992/25/FUL Full Application

Works: Demolition Several homes

Read from the description, not a valuation. How we read the register

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Erection of 9 dwellings and new commercial/office space with associated works. Demolition of existing factory. Revised description.

As published by the council, reference P0992/25/FUL

Application record

Reference
P0992/25/FUL
Type
Full Application
Status
Pending Consideration
Received
8 Aug 2025
Validated
21 Aug 2025
Ward
Lydbrook
Parish
Lydbrook
Decision by
Committee Decision
Postcode
GL17 9NA

Site history

Applications at this address on the Forest of Dean register

This site has had 3 applications since 2023.

  • P0923/25/FUL Awaiting decision

    Central Engineering Works Lower Lydbrook Lydbrook Gloucestershire GL17 9NA

    Change of use from vehicle dismantling (sui generis) and repairs (B2) plus the storage of depolluted cars to Class B2 Engineering including external storage (retrospective)

    Submitted 24 Jul 2025 Full applications
  • P0435/23/OUT Withdrawn

    Central Engineering Works Lower Lydbrook Lydbrook Gloucestershire GL17 9NA

    Outline Planning Permission for the erection of up to 15 dwellings with associated works. Demolition of existing industrial unit. (some matters reserved)

    Decided 26 Jun 2023 Outline

Timeline

Dates from the published record

  1. 8 Aug 2025

    Received by Forest of Dean

  2. 21 Aug 2025

    Validated

    Checked as complete and ready for consideration.

  3. 27 Jul 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 16 October 2025, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Forest of Dean took a median of 57 days over the applications it decided in the last year.

Documents

The council's own list, drawings first

139 documents on file for this application

Drawings (27)

  • Proposed elevations & floor plans 08 Aug 2025
  • Proposed elevations & floor plans 08 Aug 2025
  • Proposed elevations & floor plans 08 Aug 2025
  • Proposed elevations & floor plans 08 Aug 2025
  • Proposed elevations & floor plans 08 Aug 2025
  • Proposed office floor plans 08 Aug 2025
  • Proposed office elevations 08 Aug 2025
  • Revised proposed site plan 05 Jan 2026
  • Proposed site plan 08 Aug 2025
  • Revised elevations & floor plans plots 1 05 Jan 2026
  • Revised elevations & floor plans plots 4 05 Jan 2026
  • Revised elevations & floor plans plots 6-9 05 Jan 2026
  • Revised office floor plans 05 Jan 2026
  • Elevations & floor plans 08 Aug 2025
  • Revised street scene 30 Jul 2026
  • Revised street scene 05 Jan 2026
  • Revised office unit elevations 05 Jan 2026
  • Street scene 08 Aug 2025
  • Additional visibility splays 07 May 2026
  • Topographical survey 05 Jan 2026
  • Revised bicycle shelter 05 Jan 2026
  • Bicycle shelter 08 Aug 2025
  • Revised existing elevations & floor plan 05 Jan 2026
  • Existing elevations & floor plan 08 Aug 2025
  • Existing site plan 05 Jan 2026
  • Existing topo survey 08 Aug 2025
  • Existing site & location plan 08 Aug 2025

Everything on file (133)

  • GCC COMMUNITY INFRASTRUCTURE Consultee Comment · 12 Aug 2026
  • GCC HIGHWAYS ? POINTS OF CLARIFICATION Consultee Comment · 11 Aug 2026
  • REVISED STREET SCENE Drawing · 30 Jul 2026
  • AGREEMENT TO EXTENSION OF TIME Correspondence · 29 Jul 2026
  • HIGHWAYS DEVELOPMENT MANAGEMENT - ADDITIONAL COMMENTS Consultee Comment · 02 Jul 2026
  • RE: HIGHWAY ENGINEERS REPORT Correspondence · 02 Jul 2026
  • GCC HIGHWAYS ROAD SAFETY AUDIT ? DESIGNER?S RESPONSE Consultee Comment · 02 Jul 2026
  • NATURAL ENGLAND TO OFFICER RE RESPONSE Consultee Comment · 18 Jun 2026
  • NATURAL ENGLAND Consultee Comment · 18 Jun 2026
  • NATURAL ENGLAND ANNEX A Consultee Comment · 18 Jun 2026
  • ENVIRONMENT AGENCY RESPONSE Consultee Comment · 16 Jun 2026
  • LEAD LOCAL FLOOD AUTHORITY Consultee Comment · 15 Jun 2026
  • ENVIRONMENTAL HEALTH Consultee Comment · 08 Jun 2026
  • HIGHWAY ENGINEER?S RESPONSE NOTE Report · 03 Jun 2026
  • TO NATURAL ENGLAND FROM CASE OFFICER RE: APPROPRIATE ASSESSMENT Correspondence · 02 Jun 2026
  • BETWEEN CASE OFFICER AND SUSTAINABILITY Correspondence · 29 May 2026
  • SUSTAINABILITY ? SCREENING FOR LIKELY SIGNIFICANT EFFECTS Consultee Comment · 29 May 2026
  • SUSTAINABILITY Consultee Comment · 29 May 2026
  • SUSTAINABILITY ? APPROPRIATE ASSESSMENT Consultee Comment · 29 May 2026
  • ADDITIONAL ? TECHNICAL NOTE ? ENGINEER?S RESPONSE TO LLFA Report · 28 May 2026
  • ADDITIONAL ? TECHNICAL NOTE ? ENGINEER?S RESPONSE TO ENVIRONMENT AGENCY Report · 28 May 2026
  • AGREEMENT TO EXTENSION OF TIME Correspondence · 26 May 2026
  • ADDITIONAL - BAT SURVEY Report · 20 May 2026
  • HIGHWAYS DEVELOPMENT MANAGEMENT Consultee Comment · 12 May 2026
  • ROAD SAFETY AUDIT DECISION LOG AS REFERENCED IN FORMAL RESPONSE Consultee Comment · 12 May 2026
  • HIGHWAYS TO OFFICER RE RESPONSE Consultee Comment · 12 May 2026
  • HIGHWAYS TO OFFICER RE ROAD SAFETY AUDIT DECISION LOG Consultee Comment · 12 May 2026
  • ADDITIONAL ? ROAD SAFETY AUDIT - DESIGNER?S RESPONSE Report · 07 May 2026
  • CORRESPONDENCE - FROM AGENT E mail · 07 May 2026
  • ADDITIONAL - NOISE IMPACT ASSESSMENT TECHNICAL NOTE 3 Report · 07 May 2026
  • ADDITIONAL - ROAD SAFETY AUDIT Report · 07 May 2026
  • ADDITIONAL ? VISIBILITY SPLAYS Drawing · 07 May 2026
  • CORRESPONDENCE BETWEEN AGENT AND OFFICER Correspondence · 01 May 2026
  • ADDITIONAL - COMMERCIAL REPORT Report · 01 May 2026
  • REVISED - APPLICATION FORM Application Form · 26 Feb 2026
  • ENVIRONMENTAL HEALTH (NOISE) Consultee Comment · 20 Feb 2026
  • WYE VALLEY NATIONAL LANDSCAPE TEAM Consultee Comment · 18 Feb 2026
  • FURTHER COMMENT FROM JONES, E Public Comment · 12 Feb 2026
  • ENVIRONMENT AGENCY Consultee Comment · 12 Feb 2026
  • FLOOD RISK MANAGEMENT OFFICER Consultee Comment · 10 Feb 2026
  • LEAD LOCAL FLOOD AUTHORITY ADDITIONAL COMMENTS Consultee Comment · 05 Feb 2026
  • GCC - ARCHAEOLOGY Consultee Comment · 28 Jan 2026
  • REVISED FLOOD RISK ASSESSMENT Report · 22 Jan 2026
  • FROM AGENT RE: UPDATES INCLUDING ARCHAEOLOGY Correspondence · 22 Jan 2026
  • TO GCC ARCHAEOLOGY ? REQUEST FOR CONSULTATION Correspondence · 22 Jan 2026
  • CONSERVATION OFFICER - ADDITIONAL COMMENTS Consultee Comment · 21 Jan 2026
  • HIGHWAYS DEVELOPMENT MANAGEMENT - ADDITIONAL COMMENTS Consultee Comment · 21 Jan 2026
  • EXTENSION OF TIME AGREEMENT Correspondence · 21 Jan 2026
  • OBJECTION - CANNON, J Public Comment · 12 Jan 2026
  • CORRESPONDENCE ? RE; REVISED DESCRIPTION AND QUERIES RE: SUBMISSION OF FURTHER I Correspondence · 08 Jan 2026
  • TOPOGRAPHICAL SURVEY Drawing · 05 Jan 2026
  • REVISED EXISTING ELEVATIONS & FLOOR PLAN Drawing · 05 Jan 2026
  • REVISED STREET SCENE Drawing · 05 Jan 2026
  • REVISED ELEVATIONS & FLOOR PLANS PLOTS 1, 2, 3 Drawing · 05 Jan 2026
  • REVISED ELEVATIONS & FLOOR PLANS PLOTS 4 & 5 Drawing · 05 Jan 2026
  • REVISED ELEVATIONS & FLOOR PLANS PLOTS 6-9 Drawing · 05 Jan 2026
  • REVISED NOISE IMPACT ASSESSMENT Report · 05 Jan 2026
  • ADDITIONAL ? HERITAGE IMPACT ASSESSMENT Report · 05 Jan 2026
  • EXISTING SITE PLAN Drawing · 05 Jan 2026
  • REVISED PROPOSED SITE PLAN Drawing · 05 Jan 2026
  • REVISED OFFICE UNIT ELEVATIONS Drawing · 05 Jan 2026
  • REVISED OFFICE FLOOR PLANS Drawing · 05 Jan 2026
  • REVISED BICYCLE SHELTER Drawing · 05 Jan 2026
  • LEAD LOCAL FLOOD AUTHORITY Consultee Comment · 12 Dec 2025
  • NATURAL ENGLAND - RE: APPROPRIATE ASSESSMENT Consultee Comment · 11 Dec 2025
  • NATURAL ENGLAND- ANNEX A Consultee Comment · 11 Dec 2025
  • NATURAL ENGLAND RE: APPROPRIATE ASSESSMENT Correspondence · 11 Dec 2025
  • ENVIRONMENT AGENCY ADDITIONAL COMMENTS Consultee Comment · 11 Dec 2025
  • GENERAL - PHELPS, S Public Comment · 26 Nov 2025
  • CORRESPONDENCE FROM AGENT RE: APPLICATION Correspondence · 25 Nov 2025
  • ADDITIONAL ? TECHNICAL NOTE ? ENGINEER?S RESPONSE: FLOOD RISK Report · 25 Nov 2025
  • REVISED FLOOD RISK ASSESSMENT Report · 25 Nov 2025
  • AGREEMENT TO EXTENSION OF TIME Correspondence · 25 Nov 2025
  • OFFICER CONSULTEE REQUEST Correspondence · 25 Nov 2025
  • CORRESPONDENCE FROM ECOLOGY Correspondence · 31 Oct 2025
  • UPDATED COMMENTS - ECOLOGY Consultee Comment · 31 Oct 2025
  • CORRESPONDENCE FROM AGENT Correspondence · 29 Oct 2025
  • ADDITIONAL ? STATUTORY BIODIVERSITY METRIC BNG Metric · 29 Oct 2025
  • ADDITIONAL ? WATERCOURSE BIODIVERSITY NET GAIN TECHNICAL NOTE Report · 29 Oct 2025
  • FROM APPLICANT ECOLOGIST RE: ECOLOGY RESPONSE Correspondence · 29 Oct 2025
  • AGREEMENT TO EXTENSION OF TIME Correspondence · 17 Oct 2025
  • FROM CASE OFFICER TO AGENT Correspondence · 17 Oct 2025
  • SUSTAINABILITY - REVISED APPROPRIATE ASSESSMENT Consultee Comment · 17 Oct 2025
  • SUSTAINABILITY - HABITAT REGULATIONS APPROPRIATE ASSESSMENT Consultee Comment · 17 Oct 2025
  • CORRESPONDENCE BETWEEN CASE OFFICER AND SUSTAINABILITY TEAM E mail · 17 Oct 2025
  • NATIONAL LANDSCAPE OFFICER Consultee Comment · 06 Oct 2025
  • HIGHWAYS DEVELOPMENT MANAGEMENT Consultee Comment · 23 Sep 2025
  • HOUSING STRATEGY AND ENABLING OFFICER Consultee Comment · 23 Sep 2025
  • ENVIRONMENT AGENCY Consultee Comment · 18 Sep 2025
  • APPENDIX TO PUBLIC COMMENT FROM LYDWOOD Public Comment · 18 Sep 2025
  • OBJECTION - LYDWOOD Public Comment · 18 Sep 2025
  • GCC MINERALS & WASTE Consultee Comment · 17 Sep 2025
  • WELSH WATER Consultee Comment · 17 Sep 2025
  • ENVIRONMENTAL HEALTH (AIR QUALITY) CER Consultee Comment · 17 Sep 2025
  • OBJECTION - CANNON, J Public Comment · 17 Sep 2025
  • ARCHAEOLOGY COMMENTS Consultee Comment · 16 Sep 2025
  • SEVERN TRENT WATER Consultee Comment · 16 Sep 2025
  • NATURE SPACE - GCN Consultee Comment · 15 Sep 2025
  • CRIME PREVENTION RESPONSE Consultee Comment · 15 Sep 2025
  • COVER EMAIL - NATURE SPACE - GCN Consultee Comment · 15 Sep 2025
  • ECOLOGY Consultee Comment · 12 Sep 2025
  • ECOLOGY - HABITATS REGULATIONS ASSESSMENT Consultee Comment · 12 Sep 2025
  • EHO - CONTAMINATED LAND OFFICER Consultee Comment · 12 Sep 2025
  • EHO - CONTAMINATED LAND OFFICER Consultee Comment · 12 Sep 2025
  • LEAD LOCAL FLOOD AUTHORITY Consultee Comment · 11 Sep 2025
  • NATURAL ENGLAND Consultee Comment · 08 Sep 2025
  • NATURAL ENGLAND - ANNEX A Consultee Comment · 08 Sep 2025
  • SUSTAINABILITY - TREES Consultee Comment · 08 Sep 2025
  • GCC COMMUNITY INFRASTRUCTURE - EDUCATION DATA SHEET Consultee Comment · 04 Sep 2025
  • GCC COMMUNITY INFRASTRUCTURE Consultee Comment · 04 Sep 2025
  • CONSERVATION OFFICER Consultee Comment · 29 Aug 2025
  • CONSULTATION CRITERIA FOR ENVIRONMENT AGENCY Report · 28 Aug 2025
  • GLOUCESTERSHIRE WILDLIFE TRUST Consultee Comment · 27 Aug 2025
  • ECOLOGICAL ASSESSMENT Report · 12 Aug 2025
  • DESIGN AND ACCESS STATEMENT Report · 12 Aug 2025
  • PRE-PLANNING GEO-ENVIRONMENTAL DESK STUDY Report · 12 Aug 2025
  • BIODIVERSITY SELF ASSESSMENT FORM Report · 12 Aug 2025
  • EXISTING SITE & LOCATION PLAN Drawing · 08 Aug 2025
  • ENVIRONMENTAL NOISE IMPACT ASSESSMENT Report · 08 Aug 2025
  • PROPOSED ELEVATIONS & FLOOR PLANS Drawing · 08 Aug 2025
  • PROPOSED ELEVATIONS & FLOOR PLANS Drawing · 08 Aug 2025
  • PROPOSED ELEVATIONS & FLOOR PLANS Drawing · 08 Aug 2025
  • ELEVATIONS & FLOOR PLANS Drawing · 08 Aug 2025
  • PROPOSED ELEVATIONS & FLOOR PLANS Drawing · 08 Aug 2025
  • PROPOSED ELEVATIONS & FLOOR PLANS Drawing · 08 Aug 2025
  • BICYCLE SHELTER Drawing · 08 Aug 2025
  • PROPOSED OFFICE ELEVATIONS Drawing · 08 Aug 2025
  • PROPOSED OFFICE FLOOR PLANS Drawing · 08 Aug 2025
  • EXISTING ELEVATIONS & FLOOR PLAN Drawing · 08 Aug 2025
  • EXISTING TOPO SURVEY Drawing · 08 Aug 2025
  • PROPOSED SITE PLAN Drawing · 08 Aug 2025
  • FLOOD RISK ASSESSMENT & DRAINAGE STRATEGY Report · 08 Aug 2025
  • STREET SCENE Drawing · 08 Aug 2025

Watch members (£5 a month) open the document list from here.

Open the documents

Working a patch? Trade sends you the drawings on every job in your area. 14 days free.

What happens while it is decided

This application is with Forest of Dean for determination, against a statutory target of eight weeks. Over the last year Forest of Dean decided full applications in a median of 67 days. More in our guide to how long planning decisions take.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

In Forest of Dean

  • P0440/26/FUL Granted

    Selwyn Cottage Walmore Hill Minsterworth Gloucester Gloucestershire GL2 8LA

    Demolition of single-storey extension, erection of single and two-storey extensions, internal alterations

    Received 14 Apr, published by the council 27 Jul 2026 Full applications
  • P0852/26/FUL Granted

    Craig Y Heul Ross Road Lower Lydbrook Lydbrook Gloucestershire GL17 9NU

    Erection of 3 storey front/side extension and extension to timber decking with association works.

    Received 22 Jul, published by the council 12 Aug 2026 Full applications
  • P0423/25/FUL Granted

    Coppice House Main Road Huntley Gloucester Gloucestershire GL19 3DZ

    Erection of three standalone assisted living units and staff office associated with existing care facility.

    Received 2 Apr, published by the council 2 Aug 2026 Full applications
  • P1067/26/FUL Granted

    Bridgewood Church Road Longhope Gloucestershire GL17 0LG

    Erection of a detached mono pitched roof garage & workshop

    Received 8 Sep, published by the council 22 Sep 2026 Full applications
  • P1071/26/FUL Granted

    Yew Tree House Blakeney Hill Blakeney Gloucestershire GL15 4BS

    Erection of a single storey first floor rear extension, with alterations to landscaping to provide additional parking, and associated works.

    Received 10 Sep, published by the council 21 Sep 2026 Full applications