HVDC Link From Westfield Substation To South Of A921 Kinghorn Fife

Awaiting decision Fife 25/03298/EIA Planning Permission (EIA Development)

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Planning permission in principle for construction of a converter station (onshore components of the Eastern Green Link 4 transmission connection between Westfield, Fife and Norfolk, England) and associated infrastructure including accesses, drainage and landscaping

As published by the council, reference 25/03298/EIA

Application record

Reference
25/03298/EIA
Type
Planning Permission (EIA Development)
Status
Registered
Received
3 Dec 2025
Validated
19 Feb 2026
Ward
Lochgelly, Cardenden And Benarty
Parish
Cardenden

Comment by 19 November 2026

The council is taking comments on this application until then. Have your say on Fife's portal.

Site history

Applications at this address on the Fife register

This site has had 2 applications since 2025.

  • 25/03297/EIA Awaiting decision

    HVDC Link From Westfield Substation To South Of A921 Kinghorn Fife

    Full planning permission for the installation of high voltage direct and alternating current underground cables (onshore components of the Eastern Green Link 4 transmission connection between Westfield, Fife and Norfolk, England) and associated infrastructure including drainage, compounds and accesses

    Submitted 3 Dec 2025 Outline

Timeline

Dates from the published record

  1. 3 Dec 2025

    Received by Fife

  2. 19 Feb 2026

    Validated

    Checked as complete and ready for consideration.

  3. 6 Aug 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 16 April 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Fife took a median of 46 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

AECOM Limited Agent, registered in London

Active · incorporated 1984 · London

303 applications on PlanIndex · across 77 councils · 97% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

107 documents on file for this application

  • COURIER ADVERT 22.10.26 Other · 13 Oct 2026
  • EDINBURGH GAZETTE COVER EMAIL 20.10.26 Other · 13 Oct 2026
  • EDINBURGH GAZETTE ADVERT 20.10.26 Other · 13 Oct 2026
  • SCOTTISH WATER Consultee · 01 Oct 2026
  • 65 - PWS TECHNICAL NOTE Report · 29 Sep 2026
  • PSAD Application Form · 29 Sep 2026
  • PSAD Application Form · 07 Aug 2026
  • 62 - PEATLAND AND PEAT MANAGEMENT REPORT Report · 07 Aug 2026
  • SEPA Consultee · 24 May 2026
  • HSE FORM - CS PLAN Drawing · 28 Apr 2026
  • HSE FORM - BUILDINGS PADHI Questionnaire · 28 Apr 2026
  • HSE FORM - LANDSCAPING PADHI Questionnaire · 28 Apr 2026
  • TRANSPORTATION Consultee · 15 Apr 2026
  • NATURESCOT Consultee · 10 Apr 2026
  • HISTORIC ENVIRONMENT SCOTLAND Consultee · 25 Mar 2026
  • TREES Consultee · 23 Mar 2026
  • MR GRAHAM GOURLAY(FULL) General Comment · 19 Mar 2026
  • MR GRAHAM GOURLAY(FULL) General Comment · 19 Mar 2026
  • NATURAL HERITAGE Consultee · 19 Mar 2026
  • SCOTTISH WATER Consultee · 18 Mar 2026
  • SEPA Consultee · 18 Mar 2026
  • ARCHAEOLOGY Consultee · 14 Mar 2026
  • THE COAL AUTHORITY Consultee · 12 Mar 2026
  • STRUCTURAL SERVICES Consultee · 11 Mar 2026
  • 54 - APPENDIX 11 - PPP CHECKLIST Other · 19 Feb 2026
  • 55 - APPENDIX 7 AND 8 - FRA COMPLIANCE AND CHECK CERTIFICATE Other · 19 Feb 2026
  • 59 - INDEMNITY INSURANCE LETTER Correspondence · 19 Feb 2026
  • 56 - APPENDIX 4 - SUDS INDEPENDENT CHECK CERTIFICATE ? TIER 2 MAJOR APPLICATIONS Other · 19 Feb 2026
  • 57 - APPENDIX 3 - SUDS DESIGN COMPLIANCE CERTIFICATE - TIER 2 MAJOR APPLICATIONS Other · 19 Feb 2026
  • 17 - EIA VOL 2: CH07 - ECOLOGY PART 3 Report · 19 Feb 2026
  • 18 - EIA VOL 2: CH08 - WATER ENVIRONMENT AND FLOOD RISK PART 3 Report · 19 Feb 2026
  • 19 - EIA VOL 2: CH09 - CULTURAL HERITAGE PART 3 Report · 19 Feb 2026
  • 58 - GEOTECHNICAL INTERPRETIVE REPORT PART 1 Report · 19 Feb 2026
  • 58 - GEOTECHNICAL INTERPRETIVE REPORT PART 2 Report · 19 Feb 2026
  • 58 - GEOTECHNICAL INTERPRETIVE REPORT PART 3 Report · 19 Feb 2026
  • PSAD Application Form · 19 Feb 2026
  • LAND OWNERSHIP CERTIFICATE Application Form · 19 Feb 2026
  • LAND OWNERSHIP CERTIFICATES Application Form · 19 Feb 2026
  • 53 - COAL MINING RISK ASSESSMENT PART 1 Report · 03 Dec 2025
  • 53 - COAL MINING RISK ASSESSMENT PART 2 Report · 03 Dec 2025
  • 53 - COAL MINING RISK ASSESSMENT PART 3 Report · 03 Dec 2025
  • 07 - GENERIC QUANTITATIVE RISK ASSESSMENT REPORT PART 1 Report · 03 Dec 2025
  • 07 - GENERIC QUANTITATIVE RISK ASSESSMENT REPORT PART 2 Report · 03 Dec 2025
  • 07 - GENERIC QUANTITATIVE RISK ASSESSMENT REPORT PART 3 Report · 03 Dec 2025
  • 52 - DRAINAGE STRATEGY Report · 03 Dec 2025
  • 06 - PROPOSED PERMANENT ACCESS ARRANGEMENT Drawing · 03 Dec 2025
  • 05 - PROPOSED TEMPORARY ACCESS Drawing · 03 Dec 2025
  • 03 - DESIGN AND ACCESS STATEMENT Other · 03 Dec 2025
  • 08 - PRE-APPLICATION CONSULTATION (PAC) REPORT Report · 03 Dec 2025
  • 09 - EIA VOL 1: NON-TECHNICAL SUMMARY Report · 03 Dec 2025
  • 10 - EIA VOL 2: CH00 - CONTENTS AND ABBREVIATIONS Report · 03 Dec 2025
  • 11 - EIA VOL 2: CH01 - INTRODUCTION Report · 03 Dec 2025
  • 12 - EIA VOL 2: CH02 - PROJECT DESCRIPTION Other · 03 Dec 2025
  • 13 - EIA VOL 2: CH03 - SITE SELECTION Report · 03 Dec 2025
  • 14 - EIA VOL 2: CH04 - LEGISLATIVE AND POLICY FRAMEWORK Report · 03 Dec 2025
  • 15 - EIA VOL 2: CH05 - ASSESSMENT METHODOLOGY Report · 03 Dec 2025
  • 16 - EIA VOL 2: CH06 - LANDSCAPE AND VISUAL PART 1 Report · 03 Dec 2025
  • 16 - EIA VOL 2: CH06 - LANDSCAPE AND VISUAL PART 2 Report · 03 Dec 2025
  • 17 - EIA VOL 2: CH07 - ECOLOGY PART 1 Report · 03 Dec 2025
  • 17 - EIA VOL 2: CH07 - ECOLOGY PART 2 Report · 03 Dec 2025
  • 17 - EIA VOL 2: CH07 - ECOLOGY PART 4 Report · 03 Dec 2025
  • 17 - EIA VOL 2: CH07 - ECOLOGY PART 5 Other · 03 Dec 2025
  • 17 - EIA VOL 2: CH07 - ECOLOGY PART 6 Other · 03 Dec 2025
  • 17 - EIA VOL 2: CH07 - ECOLOGY PART 7 Report · 03 Dec 2025
  • 18 - EIA VOL 2: CH08 - WATER ENVIRONMENT AND FLOOD RISK PART 1 Report · 03 Dec 2025
  • 18 - EIA VOL 2: CH08 - WATER ENVIRONMENT AND FLOOD RISK PART 2 Report · 03 Dec 2025
  • 18 - EIA VOL 2: CH08 - WATER ENVIRONMENT AND FLOOD RISK PART 4 Report · 03 Dec 2025
  • 19 - EIA VOL 2: CH09 - CULTURAL HERITAGE PART 1 Report · 03 Dec 2025
  • 19 - EIA VOL 2: CH09 - CULTURAL HERITAGE PART 2 Report · 03 Dec 2025
  • 20 - EIA VOL 2: CH10 - TRAFFIC AND TRANSPORT Report · 03 Dec 2025
  • 21 - EIA VOL 2: CH11 - NOISE Report · 03 Dec 2025
  • 22 - EIA VOL 2: CH12 - GEOLOGY PART 1 Report · 03 Dec 2025
  • 22 - EIA VOL 2: CH12 - GEOLOGY PART 2 Report · 03 Dec 2025
  • 23 - EIA VOL 2: CH13 - CLIMATE CHANGE Report · 03 Dec 2025
  • 24 - EIA VOL 2: CH14 - CUMULATIVE EFFECTS Report · 03 Dec 2025
  • 25 - EIA VOL 2: CH15 - SUMMARY AND CONCLUSIONS Report · 03 Dec 2025
  • 26 - EIA VOL 3: VISUALISATIONS PART 01 Report · 03 Dec 2025
  • 26 - EIA VOL 3: VISUALISATIONS PART 02 Report · 03 Dec 2025
  • 26 - EIA VOL 3: VISUALISATIONS PART 03 Report · 03 Dec 2025
  • 38 - EIA VOL 4: APPENDIX 10.1 TRAFFIC AND TRANSPORT Report · 03 Dec 2025
  • 39 - EIA VOL 4: APPENDIX 11.1 NOISE PERCEPTION AND TERMINOLOGY Report · 03 Dec 2025
  • 40 - EIA VOL 4: APPENDIX 11.2 INDICATIVE LAYOUT Report · 03 Dec 2025
  • 41 - EIA VOL 4: APPENDIX 11.3 BASELINE SURVEY Report · 03 Dec 2025
  • 42 - EIA VOL 4: APPENDIX 11.4 NOISE MODEL SETUP Report · 03 Dec 2025
  • 43 - EIA VOL 4: APPENDIX 11.5 NOISE RATING CURVE Report · 03 Dec 2025
  • 44 - EIA VOL 4: APPENDIX 15.1 MITIGATION MEASURES REGISTER Report · 03 Dec 2025
  • 27 - EIA VOL 4: APPENDIX 5.1 SCOPING OPINION Report · 03 Dec 2025
  • 28 - EIA VOL 4: APPENDIX 6.1 LANDSCAPE AND VISUAL METHOD Report · 03 Dec 2025
  • 29 - EIA VOL 4: APPENDIX 6.2 LANDSCAPE ASSESSMENT Report · 03 Dec 2025
  • 30 - EIA VOL 4: APPENDIX 6.3 VISUAL ASSESSMENT Report · 03 Dec 2025
  • 45 - EIA VOL 4: APPENDIX 7.1 ECIA METHODS Report · 03 Dec 2025
  • 46 - EIA VOL 4: APPENDIX 7.2 BATS Report · 03 Dec 2025
  • 47 - EIA VOL 4: APPENDIX 7.3 OTHER MAMMALS Report · 03 Dec 2025
  • 48 - EIA VOL 4: APPENDIX 7.4 ORNITHOLOGY Report · 03 Dec 2025
  • 49 - EIA VOL 4: APPENDIX 7.5 GREAT CRESTED NEWT Report · 03 Dec 2025
  • 50 - EIA VOL 4: APPENDIX 7.6 HABITAT REGS ASSESSMENT Report · 03 Dec 2025
  • 51 - EIA VOL 4: APPENDIX 7.7 BIODIVERSITY NET GAIN Report · 03 Dec 2025
  • 31 - EIA VOL 4: APPENDIX 8.1 PRIVATE WATER SUPPLY Report · 03 Dec 2025
  • 32 - EIA VOL 4: APPENDIX 8.2 WATER FRAMEWORK DIRECTIVE ASSESSMENT Report · 03 Dec 2025
  • 33 - EIA VOL 4: APPENDIX 8.3 FLOOD RISK ASSESSMENT Report · 03 Dec 2025
  • 34 - EIA VOL 4: APPENDIX 8.4 WATERCOURSE CROSSINGS Report · 03 Dec 2025
  • 35 - EIA VOL 4: APPENDIX 8.5 CAR LICENCES Report · 03 Dec 2025
  • 36 - EIA VOL 4: APPENDIX 9.1 HERITAGE GAZETTEER Report · 03 Dec 2025
  • 37 - EIA VOL 4: APPENDIX 9.2 HERITAGE SITE VISIT PHOTOS Report · 03 Dec 2025
  • 01 - LOCATION PLAN OS Extract · 03 Dec 2025
  • 04 - PLANNING STATEMENT Other · 03 Dec 2025
  • 02 - SPEN LAND OWNERSHIP PLAN OS Extract · 03 Dec 2025

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Fife for determination, against a statutory target of eight weeks. Over the last year Fife decided outline applications in a median of 41 days. More in our guide to how long planning decisions take.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Westfield Substation Fife

    26/01047/NEA Submitted 27 Mar 2026 50 yards away

    Notification under The Overhead Lines (Exemption) (Scotland) Regulations 2013 for temporary diversion of 132kV Overhead Line and replacement of Tower

    Decided Other 3 docs
  • North Pitkinny Farm Lochgelly Fife KY5 0HG

    25/02604/DPN Submitted 17 Sep 2025 300 yards away

    Prior Notification for Demolition of buildings.

    Granted Other Demolition 12 docs

In Fife

  • 26/02546/SCR Decided

    Hillcairnie Farm Cairnie Cupar Fife KY15 4QD

    Screening request for proposed development of 2 No. poultry sheds

    Received 10 Sep, published by the council 23 Sep 2026 Outline
  • 26/02645/PAS Decided

    Fife Ethylene Plant Mossmorran Fife

    Pre-application screening opinion (Section 35A) for alterations to and reuse of existing offices and warehouses, and erection of an energetics manufacturing facility comprising process buildings, earth-covered storage magazines with associated earthworks, ancillary buildings, access, parking, landscaping, drainage and associated infrastructure

    Received 8 Sep, published by the council 4 Oct 2026 Outline
  • 26/02646/SCR Decided

    Fife Ethylene Plant Mossmorran Fife

    EIA screening opinion for alterations to and reuse of offices and warehouses, and erection of an energetics manufacturing facility comprising process buildings, earth-covered storage magazines with associated earthworks, ancillary buildings, access, parking, landscaping,drainage and associated infrastructure

    Received 8 Sep, published by the council 4 Oct 2026 Outline
  • 26/02460/SCO Awaiting decision

    Sand And Gravel Pits South Of Boulterhall Straiton Balmullo Fife

    EIA Scoping Opinion to extend operations by 15 years and revised public road access

    Received 3 Sep, published by the council 4 Oct 2026 Outline
  • 26/02432/PPP Awaiting decision

    Land East Of 25 Venturefair Avenue Dunfermline Fife

    Planning Permission in Principle for erection of dwellinghouse, formation of access, hardstanding, landscaping, and associated works Site: Land East of 35 Venturefair Avenue, Dunfermline

    Received 3 Sep, published by the council 23 Sep 2026 Outline