Skip to content
PlanIndex Get alerts
Menu

Planning application

East Anglia ONE North Offshore Wind Farm Suffolk

Granted East Suffolk DC/26/1958/DRR Discharge of Requirements (56 days)

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Discharge of Requirement 40 (Amendments to approved details - Use of Tower Cranes during the Construction of Kiln Lane Substation) Substation Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

As published by the council, reference DC/26/1958/DRR

Application record

Reference
DC/26/1958/DRR
Type
Discharge of Requirements (56 days)
Status
Permitted
Decision
Application Permitted
Received
27 May 2026
Validated
27 May 2026
Decided
29 Jul 2026
Ward
Woodbridge
Parish
Woodbridge
Decision by
Delegated Decision

Site history

Applications at this address on the East Suffolk register

This site has had 47 applications since 2025: 42 approved, 0 refused.

  • DC/26/2999/DRR Awaiting decision

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 40 (Amendments to approved details - Amendment to Approved Landscape Masterplan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Submitted 24 Aug 2026 Conditions
  • DC/26/2306/CON Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Consultation - Pre-construction Monitoring Plan for East Anglia One North

    Decided 9 Jul 2026 Outline
  • DC/26/1172/CON Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Consultation - East Anglia TWO Limited (EATL) and East Anglia ONE North Limited (EAONL) are writing to the MMO to formally respond to a request for further information received on the 9th February 2026 in relation to the EA TWO and EA ONE North HDD Discharge Documents (EA2-LDF-CNS-REP-IBR-000119 and EA1N-LDF-CNS-REP-IBR-000058).

    Decided 13 Apr 2026 Outline
  • DC/25/4823/CCC Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 41 (1) and (2) (Operational Drainage Management Plan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 11 Feb 2026 Outline
  • DC/25/4823/DRR Awaiting decision

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 41 (1) and (2) (Operational Drainage Management Plan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Submitted 12 Dec 2025 Outline
  • DC/25/4822/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 12 (1) to (16) (Detailed Design Report) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 20 Feb 2026 Conditions
  • DC/25/4821/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 14(1) (Landscape Management Plan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 18 Feb 2026 Conditions
  • DC/25/4700/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 40 (Amendments to Approved Details - Vegetation Clearance) Cable Enabling Works - Early Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 8 Jan 2026 Conditions
  • DC/25/4703/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 12 (2) and 27 (2) (Operational Phase Noise Management Plan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 11 Feb 2026 Conditions
  • DC/25/4597/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 17(1) (Fencing and other means of enclosure) Substation Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 5 Feb 2026 Conditions

Timeline

Dates from the published record

  1. 27 May 2026

    Received by East Suffolk

  2. 24 Jul 2026

    Added to PlanIndex

  3. 29 Jul 2026

    Decision issued: Application Permitted

Documents

Plans, drawings, consultee responses and the officer's report

14 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

East Suffolk granted permission on 29 July 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • East Anglia ONE North Offshore Wind Farm Suffolk

    DC/25/4120/CCC Submitted 24 Oct 2025 0m away

    County Council Consultation - Discharge of Requirement 33 Emergency Planning Arrangements for the Onshore Substation Stage and Onshore Cable Stage, and Offshore Works Phase in respect of Scottish Power Renewables East Anglia ONE North Offshore Wind Farm

    Granted Outline 6 docs
  • East Anglia TWO Offshore Wind Farm Suffolk

    DC/25/4121/CCC Submitted 24 Oct 2025 0m away

    County Council Consultation - Discharge of Requirement 33 Emergency Planning Arrangements for the Onshore Substation Stage and Onshore Cable Stage, and Offshore Works Phase in respect of Scottish Power Renewables East Anglia TWO Offshore Wind Farm

    Granted Outline 6 docs
  • East Anglia ONE North Offshore Wind Farm Suffolk

    DC/25/4515/DRR Submitted 21 Nov 2025 0m away

    Discharge of Requirement 22(2)(c) (Construction Phase Noise and Vibration Management Plan) Substation Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Granted Conditions 6 docs
  • East Anglia ONE North Offshore Wind Farm Suffolk

    DC/25/4823/CCC Submitted 12 Dec 2025 0m away

    Discharge of Requirement 41 (1) and (2) (Operational Drainage Management Plan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Granted Outline 7 docs
  • East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk

    DC/25/4827/DRR Submitted 12 Dec 2025 0m away

    99% historically approved · decision due ~6 Feb

    Discharge of Requirement 12 (1) to (16) (Detailed Design) Substations Stage of East Anglia TWO Offshore Wind Farm Development Consent Order

    Awaiting decision Conditions 10 docs
  • East Anglia ONE North Offshore Wind Farm Suffolk

    DC/25/4100/DRR Submitted 22 Oct 2025 0m away

    Discharge of Requirement 14(1) (Landscape Management Plan) Onshore Cable Duct Installation Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Granted Conditions 7 docs

In East Suffolk

  • DC/26/1893/DRC Granted

    The Workshop Brick Kiln Lane Melton Woodbridge Suffolk IP12 2PB

    Discharge of conditions 7 and 10 of DC/23/2365/FUL - Demolition of existing workshop buildings, erection of replacement workshop, authorisation of existing workshop extensions, associated works. - Condition 7 - Construction Management Plan; Condition 10 - Noise Management Plan

    21 May 2026 Conditions
  • DC/26/2573/DRC Granted

    North Suffolk Skills Academy Harrisons Lane Halesworth Suffolk IP19 8PY

    Discharge of condition Nos. 14, 19 & 26 of DC/21/0007/FUL - Change of use to sports facilities comprising new grass football pitch adjacent to Harrisons Lane and construction of a new artificial football pitch with associated parking, access, lighting, acoustic fencing and drainage adjacent to the Apollo Youth Centre and adjacent field to the south. - 14 - Construction Mngt Plan, 19 - Construction and Phasing Plan and 26 - Surface Water

    20 Jul 2026 Conditions
  • DC/26/2736/DRC Granted

    Land Adj School Road Church Road Ringsfield Suffolk

    Discharge of Condition No. 10 of DC/25/3030/VOC - Variation of Condition No. 2 of DC/17/2934/VOC - Construction of 10 No.Holiday Lodges, 1 No. retail unit and 1 No. self contained flat. This application is seeking modification to the appearance and layout of the originally approved lodges - discharge of surface water

    3 Aug 2026 Conditions
  • DC/26/3165/DRC Awaiting decision

    Timber Mill Barns Sizewell Hall Road Leiston Suffolk IP16 4TT

    Discharge of Condition Nos. 18, 21 and 23 of DC/25/1355/FUL - Alterations to the existing structure & external envelope as part of the formation of two residential dwellings from agricultural barn - 18. Construction Method Statement 21. Emergency Demolition/Construction Manangement Plan 23. Radiation Emergency Contingency Plan.

    8 Sep 2026 Conditions
  • DC/26/3167/DRC Awaiting decision

    St Michaels Church Church Street Framlingham Suffolk IP13 9BQ

    Discharge of Condition No. 3 of DC/26/1993/FUL - Rebuilding of a brick bounday wall - Archaeological Monitoring

    8 Sep 2026 Conditions