Granted East Suffolk DC/26/1172/CON Other Consultation

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Consultation - East Anglia TWO Limited (EATL) and East Anglia ONE North Limited (EAONL) are writing to the MMO to formally respond to a request for further information received on the 9th February 2026 in relation to the EA TWO and EA ONE North HDD Discharge Documents (EA2-LDF-CNS-REP-IBR-000119 and EA1N-LDF-CNS-REP-IBR-000058).

As published by the council, reference DC/26/1172/CON

Application record

Reference
DC/26/1172/CON
Type
Other Consultation
Status
Responded
Decision
No Objections
Received
26 Mar 2026
Validated
26 Mar 2026
Decided
13 Apr 2026
Ward
Woodbridge
Parish
Woodbridge
Decision by
Delegated Decision

Site history

Applications at this address on the East Suffolk register

This site has had 47 applications since 2025: 42 approved, 0 refused.

  • DC/26/2999/DRR Awaiting decision

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 40 (Amendments to approved details - Amendment to Approved Landscape Masterplan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Submitted 24 Aug 2026 Conditions
  • DC/26/2306/CON Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Consultation - Pre-construction Monitoring Plan for East Anglia One North

    Decided 9 Jul 2026 Outline
  • DC/26/1958/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 40 (Amendments to approved details - Use of Tower Cranes during the Construction of Kiln Lane Substation) Substation Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 29 Jul 2026 Conditions
  • DC/25/4823/CCC Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 41 (1) and (2) (Operational Drainage Management Plan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 11 Feb 2026 Outline
  • DC/25/4823/DRR Awaiting decision

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 41 (1) and (2) (Operational Drainage Management Plan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Submitted 12 Dec 2025 Outline
  • DC/25/4822/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 12 (1) to (16) (Detailed Design Report) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 20 Feb 2026 Conditions
  • DC/25/4821/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 14(1) (Landscape Management Plan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 18 Feb 2026 Conditions
  • DC/25/4700/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 40 (Amendments to Approved Details - Vegetation Clearance) Cable Enabling Works - Early Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 8 Jan 2026 Conditions
  • DC/25/4703/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 12 (2) and 27 (2) (Operational Phase Noise Management Plan) Substations Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 11 Feb 2026 Conditions
  • DC/25/4597/DRR Granted

    East Anglia ONE North Offshore Wind Farm Suffolk

    Discharge of Requirement 17(1) (Fencing and other means of enclosure) Substation Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Decided 5 Feb 2026 Conditions

Timeline

Dates from the published record

  1. 26 Mar 2026

    Received by East Suffolk

  2. 13 Apr 2026

    Decision issued: No Objections

  3. 24 Jul 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

4 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

East Suffolk granted permission on 13 April 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

In East Suffolk

  • DC/26/3197/EIA Awaiting decision

    Part Land South East Of Grimseys Lane Leiston Suffolk

    EIA Screening Opinion - Reservoir Extension to Sizewell Estate

    10 Sep 2026 Outline
  • DC/26/2832/CON Granted

    Land To North Of Railway Line Henley Road Ipswich Suffolk

    Consultation - Submission of Reserved Matters (appearance, layout, landscaping, and scale) for part of Phase 4a and Phase 4b (Part of Phase 5 of approved Phasing Strategy) of the development at Henley Gate comprising 121 dwellings, roads, parking, open space, landscaping, drainage, and other associated works; pursuant to Outline Planning Permission IP/16/00608/OUT comprising up to 1,100 dwellings, local centre, country park, open space, sustainable urban drainage systems, access points from Henley Road and associated engineering works. IP/16/00608/OUT was an EIA development and an Environmental Statement was submitted with the application under the Town and Country Planning (Environmental Impact Assessment) (England and Wales) Regulations 2011 (as amended).

    10 Aug 2026 Outline
  • DC/26/3120/CON Awaiting decision

    Suffolk Water Recycling Transfer And Storage Project Suffolk

    Consultation - Request for Scoping Opinion under Regulation 10 of The Infrastructure Planning (Environmental Impact Assessment) Regulations 2017 and Regulation 13 of The Marine Works (Environmental Impact Assessment) Regulations 2007 (as amended in 2017)

    4 Sep 2026 Outline
  • DC/26/2886/CON Granted

    Land At Silverlace Green Benhall Suffolk IP17 1JH

    Consultation - To facilitate a new connection it has become necessary for Eastern Power Networks plc to upgrade the existing pole mounted transformer to 50kVa.

    13 Aug 2026 Outline
  • DC/26/2965/CCC Granted

    Land At Foxburrow Farm Brightwell Suffolk

    County Council Consultation - Retrospective extension to an existing recycling facility for the importation, storage, treatment and recycling of inert waste and storage of building materials, with parking, office, storage facilities and associated infrastructure.

    21 Aug 2026 Outline