Planning application
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Discharge of Requirement 18(1) and (2) (Contaminated Land Mitigation Scheme) Onshore Cable Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
As published by the council, reference DC/25/4005/DRR
Application record
- Reference
- DC/25/4005/DRR
- Type
- Discharge of Requirements (56 days)
- Status
- Permitted
- Decision
- Application Permitted
- Received
- 15 Oct 2025
- Validated
- 15 Oct 2025
- Decided
- 10 Dec 2025
- Ward
- Woodbridge
- Parish
- Woodbridge
- Decision by
- Delegated Decision
Site history
Applications at this address on the East Suffolk register
This site has had 12 applications since 2025: 9 approved, 0 refused.
-
DC/25/4827/DRR Awaiting decision
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 12 (1) to (16) (Detailed Design) Substations Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
-
DC/25/4828/CCC Awaiting decision
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 41 (1) and (2) (Operational Drainage Management Plan) Substations Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
-
DC/25/4828/DRR Awaiting decision
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 41 (1) and (2) (Operational Drainage Management Plan) Substations Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
-
DC/25/4404/DRR Granted
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22 (2)(k) (Watercourse Crossing Method Statement) Substation Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
-
DC/25/4398/DRR Granted
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22 (2)(f) (Air Quality Management Plan) Substation Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
-
DC/25/4367/DRR Granted
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22 (2)(d) (Site Waste Management Plan) Substation Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
-
DC/25/4060/DRR Granted
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22 (Code of Construction Practice) Onshore Cable Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
-
DC/25/4014/DRR Granted
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22(2)(h) (Pollution Prevention and Response Plan) Onshore Cable Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
-
DC/25/4012/DRR Granted
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22(2)(j) (Construction Artificial Light Emissions Management Plan) Onshore Cable Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
-
DC/25/3848/DRR Granted
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22 (2)(e) (Soil Management Plan) Onshore Cable Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
Timeline
Dates from the published record
-
15 Oct 2025
Received by East Suffolk
-
10 Dec 2025
Decision issued: Application Permitted
-
9 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
9 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
East Suffolk granted permission on 10 December 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22 (Code of Construction Practice) Onshore Cable Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
Granted Conditions 10 docs -
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22(2)(h) (Pollution Prevention and Response Plan) Onshore Cable Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
Granted Conditions 8 docs -
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22(2)(j) (Construction Artificial Light Emissions Management Plan) Onshore Cable Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
Granted Conditions 7 docs -
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22 (2)(d) (Site Waste Management Plan) Substation Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
Granted Conditions 6 docs -
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
County Council Consultation - SCC/0100/25/DoR - Discharge of Requirement 19 (1) pre-commencement archaeology execution plan, requirement 20(1) archaeology, and requirement 32(1) prow strategy for new footpath creation works, in respect of Scottish Power Renewables East Anglia TWO Wind Farm
Granted Outline 13 docs -
East Anglia Two Offshore Wind Farm Underground Cabling Between Thorpeness And Friston Suffolk
Discharge of Requirement 22 (2)(e) (Soil Management Plan) Onshore Cable Stage of East Anglia TWO Offshore Wind Farm Development Consent Order
Granted Conditions 6 docs
Other condition discharge and variation applications
In East Suffolk
-
DC/26/2035/DRC Split decision
The Old Rectory The Street South Elmham St Margaret Harleston Suffolk IP20 0PJ
Discharge of Condition Nos. 4, 5, 6, 7, 10, 11, 12, 13, 14, 16, 17, 18, 19, 20, 21, 22, 23, 24, 27, 28 and 30 of DC/24/4379/LBC - Listed Building Consent - Partial Demolition, extension and internal reordering, plus conversion and repair of outbuildings - Supporting Statement and Drawings submitted
-
DC/26/2017/DRC Granted
Hand Car Wash Montrose Service Garage London Road Beccles Suffolk NR34 9YU
Discharge of Condition No. 3 of DC/25/3495/FUL - Erection of a two-storey, 66-bed care home for the elderly with associated access, parking, landscaping, and ancillary buildings, following the demolition of existing garages and associated structures - Fuel Tank and Canopy Removal
-
DC/26/3060/DRC Awaiting decision
25 Cotmer Road Lowestoft Suffolk NR33 9PN
Discharge of Condition No. 14 of DC/24/1151/FUL - Sub division of gardens to create 2 plots and construction of 2 detached bungalows with integral garages - Water Calculations
-
DC/26/2904/DRC Granted
North Suffolk Skills Academy Harrisons Lane Halesworth Suffolk IP19 8PY
Discharge of Condition No. 3 of DC/21/0007/FUL - Change of use to sports facilities comprising new grass football pitch adjacent to Harrisons Lane and construction of a new artificial football pitch with associated parking, access, lighting, acoustic fencing and drainage adjacent to the Apollo Youth Centre and adjacent field to the south - Demolition and Construction Management Strategy
-
DC/26/3028/DRR42 Awaiting decision
Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
Development Consent Order Requirement 9 - Main Development Site: Site Clearance of the Sizewell C Development Consent Order