Granted East Suffolk DC/24/2792/DRR Discharge of Requirements (56 days)

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Discharge of Requirement 21(2) (Ecological Management Plan) and Requirement 26(1) (Onshore preparation works Management Plan) for the Archaeological Mitigation Works of the East Anglia TWO Offshore Windfarm Development Consent Order

As published by the council, reference DC/24/2792/DRR

Application record

Reference
DC/24/2792/DRR
Type
Discharge of Requirements (56 days)
Status
Permitted
Decision
Granted As published: Application Permitted
Received
2 Aug 2024
Validated
2 Aug 2024
Decided
3 Oct 2024
Ward
Aldeburgh And Leiston
Parish
Aldringham Cum Thorpe
Decision by
Delegated Decision

Site history

Applications at this address on the East Suffolk register

This site has had 2 applications since 2024: 2 approved, 0 refused.

  • DC/24/3472/CCC Granted

    East Anglia TWO Thorpeness Aldringham Cum Thorpe Suffolk

    County Council Consultation - SCC/0102/24/DoR/EA2 - Discharge of requirements 19(1) pre-commencement archaeology execution plan, requirement 20(1) archaeology, for borehole survey works, in respect of Scottish Power Renewables East Anglia Two Offshore Wind Farms

    Decided 24 Oct 2024 Outline

Timeline

Dates from the published record

  1. 2 Aug 2024

    Received by East Suffolk

  2. 3 Oct 2024

    Decision issued: Application Permitted

  3. 22 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

10 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

East Suffolk granted permission on 3 October 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • East Anglia One Thorpeness Aldringham Cum Thorpe Suffolk

    DC/24/2794/DRR Submitted 2 Aug 2024 50 yards away

    Discharge of Requirement 21(2) (Ecological Management Plan) and Requirement 26(1) (Onshore preparation works Management Plan) for the Archaeological Mitigation Works of the East Anglia ONE North Offshore Windfarm Development Consent Order

    Granted Conditions 10 docs
  • East Anglia ONE Thorpeness Aldringham Cum Thorpe Suffolk

    DC/24/3471/CCC Submitted 25 Sep 2024 50 yards away

    County Council Consultation - SCC/0101/24/DoR/EA1N - Discharge of requirements 19(1) pre-commencement archaeology execution plan, requirement 20(1) archaeology, for borehole survey works, in respect of Scottish Power Renewables East Anglia One North Offshore Wind Farms

    Granted Outline 6 docs
  • East Anglia ONE North Offshore Wind Farm Suffolk

    DC/25/4120/CCC Submitted 24 Oct 2025 50 yards away

    County Council Consultation - Discharge of Requirement 33 Emergency Planning Arrangements for the Onshore Substation Stage and Onshore Cable Stage, and Offshore Works Phase in respect of Scottish Power Renewables East Anglia ONE North Offshore Wind Farm

    Granted Outline 6 docs
  • East Anglia ONE North Offshore Wind Farm Thorpeness Aldringham Cum Thorpe Suffolk

    DC/25/0531/DRR Submitted 10 Feb 2025 50 yards away

    Discharge of Requirement 22 (2) (i) (Stakeholder Communications Plan) of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Granted Conditions 11 docs
  • East Anglia TWO Offshore Wind Farm Suffolk

    DC/25/4121/CCC Submitted 24 Oct 2025 50 yards away

    County Council Consultation - Discharge of Requirement 33 Emergency Planning Arrangements for the Onshore Substation Stage and Onshore Cable Stage, and Offshore Works Phase in respect of Scottish Power Renewables East Anglia TWO Offshore Wind Farm

    Granted Outline 6 docs
  • East Anglia ONE North Offshore Wind Farm Suffolk

    DC/25/4515/DRR Submitted 21 Nov 2025 50 yards away

    Discharge of Requirement 22(2)(c) (Construction Phase Noise and Vibration Management Plan) Substation Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

    Granted Conditions 6 docs

In East Suffolk

  • DC/26/3488/DRC Awaiting decision

    183 Normanston Drive Lowestoft Suffolk NR32 2PY

    Discharge of Condition Nos. 3 and 7 of DC/24/3846/ARM - Approval of Reserved Matters of DC/24/0716/OUT - Outline Application (Some Matters Reserved) - Subdivision of land to the rear of 183, Normanston drive and the construction of 2 no. detached dwellings with garages. - Appearance, landscaping, layout and scale. - Cycle storgae and Highways surface water.

    Received 6 Oct, published by the council 11 Oct 2026 Conditions
  • DC/26/2695/DRC Granted

    Land At Park Farm Loudham Hall Road Loudham Woodbridge Suffolk IP13 0NW

    Discharge of conditions 13 (Construction Environmental Management Plan: Biodiversity) and 17 (Construction Management Plan) of DC/21/5550/FUL (construction of 21MW solar farm with associated infrastructure)

    Received 29 Jul, published by the council 9 Aug 2026 Conditions
  • Sizewell C And Associated Development Sites Sizewell Leiston Suffolk

    Discharge of Requirement 9 - Main Development Site: Site Clearance of the Sizewell C Development Consent Order

    Received 26 Aug, published by the council 7 Sep 2026 Conditions
  • DC/26/3438/DRC Awaiting decision

    4 Hackney Terrace Melton Woodbridge Suffolk IP12 1NN

    Discharge of Condition Nos. 3, 11, 12 and 14 of DC/23/4732/FUL - Demolition of existing annexe/extension and erection of a new dwelling - precise details of fences, walls and other means of enclosure, details of the provision of secure, covered, and lit cycle storage, details of the areas to be provided for the storage and presentation of refuse and recycling bins for collection/emptying and details of a hedge planting scheme (which shall include species, size and numbers of plants to be planted)

    Received 1 Oct, published by the council 11 Oct 2026 Conditions
  • DC/26/2755/DRC Granted

    The Gables The Green Grundisburgh Woodbridge Suffolk IP13 6TA

    Discharge of Condition No. 4 of DC/26/0532/FUL - Creation of a natural swimming pond - Written Scheme of Investigation

    Received 4 Aug, published by the council 15 Aug 2026 Conditions