Proposal
To discharge Condition 8 (Noise Verification Report) of decision 21/00816/FUL dated 10th December 2021 for construction of a 30MW battery energy storage system facility and associated access, landscaping and other infrastructure works
As published by the council, reference 21/00816/DISD
Application record
- Reference
- 21/00816/DISD
- Type
- Discharge of Conditions - 4th Submission
- Status
- Pending Consideration
- Received
- 26 Aug 2026
- Validated
- 26 Aug 2026
- Ward
- Burwell
- Parish
- Burwell
Site history
Applications at this address on the East Cambridgeshire register
This site has had 3 applications since 2026.
-
21/00816/DISC Awaiting decision
Land North Of Electricity Sub-Station Weirs Drove Burwell
To discharge Condition 9 (Noise Management Plan) of decision 21/00816/FUL dated 10th December 2021 for construction of a 30MW battery energy storage system facility and associated access, landscaping and other infrastructure works
-
21/00816/DISB Awaiting decision
Land North Of Electricity Sub-Station Weirs Drove Burwell
To discharge Condition 14 (Emergency Response Plan) of decision 21/00816/FUL dated 10th December 2021 for Construction of a 30MW battery energy storage system facility and associated access, landscaping and other infrastructure works
Timeline
Dates from the published record
-
26 Aug 2026
Received by East Cambridgeshire
-
31 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 21 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
East Cambridgeshire took a median of 59 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
4 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with East Cambridgeshire for determination, against a statutory target of eight weeks. Over the last year East Cambridgeshire decided condition discharge and variation applications in a median of 65 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Land North Of Electricity Sub-Station Weirs Drove Burwell
99% historically approved · decision due ~30 Sep
To discharge Condition 9 (Noise Management Plan) of decision 21/00816/FUL dated 10th December 2021 for construction of a 30MW battery energy storage system facility and associated access, landscaping and other infrastructure works
Awaiting decision Conditions 9 docs -
Land North Of Electricity Sub-Station Weirs Drove Burwell
99% historically approved · decision due ~24 Sep
To discharge Condition 14 (Emergency Response Plan) of decision 21/00816/FUL dated 10th December 2021 for Construction of a 30MW battery energy storage system facility and associated access, landscaping and other infrastructure works
Awaiting decision Conditions 8 docs -
Burwell (E) Eastern Elec Sub Station Weirs Drive Burwell CB25 0EJ
Existing 3 no. Dipole Array at 13m to be relocated on proposed 3m tower extension on existing 28-5 tower
Granted Full applications Extension 14 docs -
16 Smiths Orchard Burwell Cambridge Cambridgeshire CB25 0FT
Proposed conservatory to the rear of the property
Withdrawn Lawful development Extension 4 docs -
Poplars Farmhouse 64 Low Road Burwell Cambridge CB25 0EJ
Proposed replacement of second storey window
Withdrawn Lawful development Windows or glazing 6 docs -
Hightown Drove Burwell CB25 0BP
Construction of a private underground power cable with associated electrical and communications equipment between North Angle Solar Farm and Swaffham Prior Energy Centre; erection of electrical substation/ switch gear buildings with associated compound and parking at High Town Drove, and installation of new switch gear at the Swaffham Prior Energy Centre.
Decided Outline 2 docs
Other condition discharge and variation applications
In East Cambridgeshire
-
25/00176/DISC Granted
Lake View Bereavement Centre And Crematorium Chatteris Road Mepal Cambridgeshire CB6 2AZ
To discharge Conditions 7 (Noise Impact Assessment), 26 (Flood Emergency Plan), 29 (Boundary Treatment/Gates) and 33 (Hydrant Confirmation) of planning permission ref: 25/00176/VAR3M dated 6th May 2025 (To Vary Conditions 1 (Approved Plans), 8 (Contamination), 12 (Sustainability), 13 (Operating Hours), 14 (Use of Function Room), 15 (Hard Landscaping), 16 (External Lighting), 19 (Soft Landscaping), 21 (Tree Protection), 24 (Foul Water Drainage), 25 (Surface Water Drainage), Condition 27 (External Materials), 28 (Flower Court & Function Room), 29 (Boundary Treatments), 31 (Visibility Splays), 34 (Fire Hydrants) and 35 (Delivery Times) for previously approved 21/01216/F3M dated 26 October 2022 for construction of a crematorium and associated service and administration building, function building, memorial garden, natural burial areas, pet cemetery, car parking, new vehicular access from the A142 north of the site and landscaping)
-
20/00413/DISF Decided
Land Between 3 And 5 New Road Haddenham Cambridgeshire
To discharge Conditions 3 (Soft Landscaping), 4 (Hard Landscaping), 16 (Verification Report), 29 (Future Maintenance and Management) of decision 20/00413/FUM dated 30th June 2021 for erection of 24 dwelling houses, together with access road, parking, open space, landscaping, boundary treatments and associated works
-
26/00086/DISA Granted
26 Main Street Coveney Ely Cambridgeshire CB6 2DJ
To discharge Condition 21 (Waste Collection Plan) of decision 26/00086/VAR dated 26th June 2026 to vary condition 1 (Approved plans) and remove condition 4 (Remediation scheme) and condition 5 (Remediation report) of 21/01196/FUL for construction of three detached dwellings and associated works, provision of parking, and private amenity space
-
20/01238/DISS Awaiting decision
Land To North Of Saxon Business Park Woodfen Road Littleport Cambridgeshire
To discharge Condition 56 (Residential Travel Plan) of decision 20/01238/FUM dated 25th June 2024 for Hybrid planning application seeking full planning permission for 180 dwellings, access, landscaping, sustainable urban drainage, public open space and associated primary infrastructure; and outline planning permission for up to 217 dwellings with all matters reserved except access
-
26/00208/DISA Granted
Appleacre 42 Westley Waterless Westley Waterless Cambridgeshire CB8 0RQ
To discharge conditions 5 (Scheme of Features for Protected or Priority Species) and 6 (Precautionary Working Method Statement) of Planning Permission ref: 26/00208/FUL dated 02/07/2026 (Rear two storey extension (demolished outbuilding), front/side tower extension and two new front dormer roof extensions)