Skip to content
PlanIndex Get alerts
Menu

Planning application

Land East Of Gretna Substation 3km To The North Of Gretna

Awaiting decision Dumfries and Galloway 26/1500/OBL Discharge of condition

Relates to 23/2331/S42

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

DISCHARGE OF CONDITION 7 OF PLANNING PERMISSION 23/2331/S42

As published by the council, reference 26/1500/OBL

Application record

Reference
26/1500/OBL
Type
Discharge of condition
Status
Assessment Stage
Received
26 Aug 2026
Validated
26 Aug 2026
Ward
Annandale East And Eskdale
Parish
Canonbie And District Community Council

Site history

Applications at this address on the Dumfries and Galloway register

This site has had 3 applications since 2022: 2 approved, 0 refused.

  • 23/2331/S42 Granted

    Land East Of Gretna Substation 3km To The North Of Gretna

    PROPOSED GRID STABILITY FACILITY COMPRISING FORMATION OF AN ELECTRICAL TRANSMISSION INFRASTRUCTURE COMPOUND CONTAINING TRANSFORMERS, CABLES AND INFRASTRUCTURE, THE ERECTION OF MAIN PLANT ROOM BUILDING, FORMATION OF NEW ACCESS, ANCILLARY CAR PARKING, DRAINAGE, BOUNDARY TREATMENT AND LANDSCAPING AT VARIANCE WITH CONDITION 4 OF PLANNING PERMISSION 20/2071/FUL CONDITION RELATION TO AIL DELIVERIES TO ENABLE AIL DELIVERIES WITHOUT THE NEED FOR A TEST RUN AND TO PROVIDE SUFFICIENT TECHNICAL EVIDENCE TO BE SUBMITTED AND APPROVED IN WRITING INSTEAD

    Decided 7 Jun 2024
  • 22/2080/OBL Granted

    Land East Of Gretna Substation 3km To The North Of Gretna

    DISCHARGE OF CONDITIONS 2, 3 AND 5 OF PLANNING PERMISSION 20/2071/FUL

    Decided 11 Jun 2024 Conditions

Timeline

Dates from the published record

  1. 26 Aug 2026

    Received by Dumfries and Galloway

  2. 29 Aug 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 21 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Dumfries and Galloway took a median of 50 days over the applications it decided in the last year.

Cases linked to this one on the register

  • 23/2331/S42 Granted

    Land East Of Gretna Substation 3km To The North Of Gretna

    PROPOSED GRID STABILITY FACILITY COMPRISING FORMATION OF AN ELECTRICAL TRANSMISSION INFRASTRUCTURE COMPOUND CONTAINING TRANSFORMERS, CABLES AND INFRASTRUCTURE, THE ERECTION OF MAIN PLANT ROOM BUILDING, FORMATION OF NEW ACCESS, ANCILLARY CAR PARKING, DRAINAGE, BOUNDARY TREATMENT AND LANDSCAPING AT VARIANCE WITH CONDITION 4 OF PLANNING PERMISSION 20/2071/FUL CONDITION RELATION TO AIL DELIVERIES TO ENABLE AIL DELIVERIES WITHOUT THE NEED FOR A TEST RUN AND TO PROVIDE SUFFICIENT TECHNICAL EVIDENCE TO BE SUBMITTED AND APPROVED IN WRITING INSTEAD

    Decided 7 Jun 2024

Documents

Plans, drawings, consultee responses and the officer's report

9 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Dumfries and Galloway for determination, against a statutory target of eight weeks. Over the last year Dumfries and Galloway decided condition discharge and variation applications in a median of 36 days. More in our guide to how long planning decisions take.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

In Dumfries and Galloway

  • 26/1682/OBL Awaiting decision

    Guild Hall New Abbey Dumfries DG2 8DX

    DISCHARGE OF CONDITIONS 3 AND 4 OF PLANNING PERMISSION 26/0623/FUL

    Received 28 Sep, published by the council 30 Sep 2026 Conditions
  • 26/1491/NMV Decided

    Lockerbie Creamery Lockerbie DG11 1LW

    NON MATERIAL VARIATION REQUEST RELATING TO PLANNING PERMISSION 25/0716/FUL FOR REPOSITIONING AND INCREASE IN HEIGHT OF SPRINKLER TANKS AND PUMP HOUSE

    Received 25 Aug, published by the council 4 Sep 2026 Conditions
  • 26/1651/NMV Granted

    Plots 8.01, 8.02 And 8.03 Stanfield Farm Eastriggs Annan DG12 6TF

    NON MATERIAL VARIATION REQUEST RELATING TO PLANNING PERMISSION 19/1969/FUL FOR PLOTS 8.02 AND 8.03 FOR INSTALLATION OF AIR SOURCE HEAT PUMPS, ENLARGEMENT OF DWELLINGHOUSE (INTEGRAL GARAGE WIDENED BY 1.5M FOR PLOT 8.03) AND RE-ALIGNMENT OF PLOT BOUNDARY OF PLOT 8.02 AND PLOT 8.01 (RELATING TO PLANNING PERMISSION 24/1311/FUL)

    Received 21 Sep, published by the council 24 Sep 2026 Conditions
  • 26/1666/OBL Awaiting decision

    Stockholm Farm Beattock DG10 9PT

    DISCHARGE OF CONDITION 2 OF PLANNING PERMISSION 25/2291/FUL

    Received 24 Sep, published by the council 30 Sep 2026 Conditions
  • 26/1021/OBL Decided

    Stockholm Farm Beattock Moffat DG10 9PT

    DISCHARGE OF CONDITION 2 OF PLANNING PERMISSION 25/2291/FUL

    Received 10 Jun, published by the council 29 Jul 2026 Conditions