Planning application
Land Between Callisterhall Wind Farm Approx 8km West Of Langholm And Gretna Substation
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
PROPOSAL OF APPLICATION NOTICE FOR 132KV OVERHEAD LINE CONNECTION
As published by the council, reference 25/2084/PAN
Application record
- Reference
- 25/2084/PAN
- Type
- Proposal of Application Notice
- Status
- Assessment Stage
- Received
- 11 Nov 2025
- Validated
- 11 Nov 2025
- Ward
- Annandale East And Eskdale
- Parish
- Gretna & Rigg Community Council
Timeline
Dates from the published record
-
11 Nov 2025
Received by Dumfries and Galloway
-
29 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 6 January 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Dumfries and Galloway took a median of 47 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
3 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat happens while it is decided
This application is with Dumfries and Galloway for determination, against a statutory target of eight weeks. Over the last year Dumfries and Galloway's median decision took 47 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Dumfries and Galloway's portal will say. Our guide explains the common types.