Unit 6 To 7 Menzies Road White Cliffs Business Park Whitfield CT16 2HQ

Awaiting decision Dover 26/00840

Relates to 26/00275

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Variation of condition 2 (approved plans) of planning permission 26/00275 for "Erection of above ground fuel tanks and pumps" to allow alterations to approved drawing and installation of an electrical GRP kiosk

As published by the council, reference 26/00840

Application record

Reference
26/00840
Status
Awaiting decision
Received
7 Sep 2026
Validated
8 Sep 2026
Ward
Whitfield
Parish
WHITFIELD
Postcode
CT16 2HQ

Site history

Applications at this address on the Dover register

This site has had 2 applications since 2026.

  • 26/00813 Awaiting decision

    Unit 6 To 7 Menzies Road White Cliffs Business Park Whitfield CT16 2HQ

    Display of an internally illuminated totem pole sign

    Submitted 1 Sep 2026

Timeline

Dates from the published record

  1. 7 Sep 2026

    Received by Dover

  2. 8 Sep 2026

    Validated

    Checked as complete and ready for consideration.

  3. 8 Sep 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 3 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Dover took a median of 56 days over the applications it decided in the last year.

Cases linked to this one on the register

  • 26/00275 Granted

    Dover Truck Stop And Customs 6 To 7 Menzies Road White Cliffs Business Park Whitfield CT16 2HQ

    Erection of above ground fuel tanks and pumps

    Decided 18 Jun 2026 Full applications

Who's behind it

Company information only, from the register and Companies House

Agent on file, an engineering consultancy

1 application on PlanIndex

Trade members see who it is, their full track record, and every application they have filed.

See who's behind it

Documents

Plans, drawings, consultee responses and the officer's report

19 documents on file for this application

  • ELECTRICAL SAFE ROOM Drawing · 08 Sep 2026
  • OVERVIEW Drawing · 08 Sep 2026
  • SPINNER ASSEMBLY Drawing · 08 Sep 2026
  • FILL POINT Drawing · 08 Sep 2026
  • SPECIFICATIONS Drawing · 08 Sep 2026
  • ROOF ASSEMBLY Drawing · 08 Sep 2026
  • ADBLUE TANK Drawing · 08 Sep 2026
  • BUND ASSEMBLY Drawing · 08 Sep 2026
  • BASE ASSEMBLY Drawing · 08 Sep 2026
  • DERV TANK Drawing · 08 Sep 2026
  • FUEL PUMP Drawing · 08 Sep 2026
  • PUMP SERVICE ROOM Drawing · 08 Sep 2026
  • APPLICATION FORM Application Form · 07 Sep 2026
  • SITE_LOCATION_PLAN Drawing · 07 Sep 2026
  • DRAINAGE CONCEPT Drawing · 07 Sep 2026
  • CONCEPT LAYOUT Drawing · 07 Sep 2026
  • CONCEPT CIVIL DETAILS Drawing · 07 Sep 2026
  • CONCEPT INTERCEPTOR Drawing · 07 Sep 2026
  • KIOSK PLANS AND ELEVATIONS Drawing · 07 Sep 2026

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Dover for determination, against a statutory target of eight weeks. Over the last year Dover's median decision took 56 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Dover's portal will say. Our guide explains the common types.

Nearby applications

Within 500 metres