Planning application
Land between Woodlands Solar Farm, North Farm Solar Farm, and Mannington Substation
Relates to P/FUL/2023/02829
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Proposed cable route in conjunction with approved solar farm developments (North Farm Solar Farm ref. P/FUL/2023/02829 and Woodlands Solar Farm ref. P/FUL/2023/03415) at Mannington, Horton.
As published by the council, reference P/FUL/2025/06819
Application record
- Reference
- P/FUL/2025/06819
- Type
- Full Planning Application
- Status
- Application Approved
- Decision
- Granted
- Received
- 14 Nov 2025
- Validated
- 14 Nov 2025
- Decided
- 22 Jul 2026
- Ward
- Cranborne and Alderholt Ward
- Parish
- Holt
- Decision by
- Committee
Timeline
Dates from the published record
-
14 Nov 2025
Received by Dorset
-
22 Jul 2026
Decision issued: Granted
-
26 Jul 2026
Added to PlanIndex
Related applications
Cases linked to this one on the register
-
P/FUL/2023/02829 Granted
North Farm Horton Dorset BH21 7HL
Construction of Solar Farm and associated infrastructure
Documents
Plans, drawings, consultee responses and the officer's report
74 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Dorset granted permission on 22 July 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
North Solar Farm and Woodlands Solar Farm Mannington Horton
Environmental Impact Assessment Screening Opinion pursuant to Regulation 6 of the Town and County Planning (EIA) Regulations 2017 for a proposed cable route in conjunction with the approved solar farm developments known as North Farm Solar Farm (planning application reference P/FUL/2023/02829) and Woodlands Solar Farm (planning application reference P/FUL/2023/03415) at Mannington Farm, Horton
Decided Outline 5 docs -
Woodlands Manor Farm Horton Wimborne BH21 8ND
Construction of Solar Farm and associated infrastructure
Granted Full applications 229 docs
Other full applications
In Dorset
-
P/FUL/2026/05392 Awaiting decision
Ashleigh Farm Dottery Road Salwayash DT6 5HT
Change of use from residential dwelling to short-term holiday let accommodation, including associated internal alterations & minor external modifications
-
P/FUL/2026/04413 Granted
Lynch Farm Icen Lane Shipton Gorge DT6 4PP
Erect a Rural Workers Dwelling.
-
P/FUL/2026/02312 Withdrawn
1,2 & 3 Church Cottages High Street Ashmore Salisbury SP5 5AF
Form new entrance & parking area, boundary wall to be realigned and rebuilt
-
P/FUL/2026/04384 Granted
Lifeboat House Peveril Point Road Swanage BH19 2AY
Install information boards. Erect courtyard stone walls (to replace sections of existing metal rail guarding). Install an Air Source Heat Pump (ASHP)
-
P/FUL/2026/02776 Granted
Poxwell Lower Dairy Poxwell DT2 8ND
Site 1no. mobile home for a dairy worker (to continue occupation of mobile home by an agricultural worker consented under P/FUL/2021/00157).