Land At Junction Of Anchor Boulevard And Galleon Boulevard Crossways Business Park Dartford Kent DA2 6QE

Awaiting decision Dartford 26/01097/VCON Variation of Condition

Relates to 25/01318/VCON

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Variation of conditions 1 and 4 of planning permission 25/01318/VCON to allow a revised substation location and associated revised parking layout (following the application granted under Ref 25/01318/VCON for 'Submission of reserved matters pursuant to DA/09/01473/VCON for erection of a 3 storey mixed use development comprising of an A1/A3 coffee shop, an A1 retail unit, with B1 office units to the upper floors and plant and staff facilities on roof plus two ancillary A1 retail single storey units (convenience store and a dry cleaners'))

As published by the council, reference 26/01097/VCON

Application record

Reference
26/01097/VCON
Type
Variation of Condition
Status
Awaiting decision
Received
21 Sep 2026
Validated
23 Sep 2026
Ward
Stone Castle
Parish
Stone
Postcode
DA2 6QE

Comment by 14 October 2026

The council is taking comments on this application until then. Have your say on Dartford's portal.

Site history

Applications at this address on the Dartford register

This site has had 3 applications since 2025: 1 approved, 0 refused.

  • 25/01318/VCON Granted

    Land At Junction Of Anchor Boulevard And Galleon Boulevard Crossways Business Park Dartford Kent DA2 6QE

    Variation of conditions 1 and 4 of planning permission 17/00493/REM to include a new substation and revised parking layout, (following the application granted under Ref 17/00493/REM for 'Submission of reserved matters pursuant to DA/09/01473/VCON for erection of a 3 storey mixed use development comprising of an A1/A3 coffee shop, an A1 retail unit, with B1 office units to the upper floors and plant and staff facilities on roof plus two ancillary A1 retail single storey units (convenience store and a dry-cleaners'))

    Decided 27 Feb 2026 Amendments
  • 25/01196/FUL Withdrawn

    Land At Junction Of Anchor Boulevard And Galleon Boulevard Crossways Business Park Dartford Kent DA2 6QE

    Erection of an electricity substation

    Decided 14 Nov 2025 Full applications

Timeline

Dates from the published record

  1. 21 Sep 2026

    Received by Dartford

  2. 23 Sep 2026

    Validated

    Checked as complete and ready for consideration.

  3. 26 Sep 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 18 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Dartford took a median of 56 days over the applications it decided in the last year.

Cases linked to this one on the register

  • 25/01318/VCON Granted

    Land At Junction Of Anchor Boulevard And Galleon Boulevard Crossways Business Park Dartford Kent DA2 6QE

    Variation of conditions 1 and 4 of planning permission 17/00493/REM to include a new substation and revised parking layout, (following the application granted under Ref 17/00493/REM for 'Submission of reserved matters pursuant to DA/09/01473/VCON for erection of a 3 storey mixed use development comprising of an A1/A3 coffee shop, an A1 retail unit, with B1 office units to the upper floors and plant and staff facilities on roof plus two ancillary A1 retail single storey units (convenience store and a dry-cleaners'))

    Decided 27 Feb 2026 Amendments

Documents

Plans, drawings, consultee responses and the officer's report

3 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Dartford for determination, against a statutory target of eight weeks. Over the last year Dartford decided amendment applications in a median of 69 days. More in our guide to how long planning decisions take.

About amendment applications

An amendment application makes limited changes to a permission that already exists; anything beyond modest adjustment needs a fresh application. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

In Dartford

  • 26/01105/VCON Awaiting decision

    40 Fernheath Way Wilmington Kent DA2 7PF

    Erection of a single storey rear/side extension and loft conversion comprising alterations to roof to provide dormer window in rear elevation, window in gable and roof lights in front roof slope (Variation of condition 2 (approved drawings) of planning permission DA/26/00798/FUL in respect of changing the depth of rear extension from 3m to 3.5)

    Received 23 Sep, published by the council 26 Sep 2026 Amendments
  • 26/00157/VCON Granted

    Former Lynch Plant Site And Ambulance Station Hawley Road Dartford DA1 1PD

    Demolition of existing buildings and construction of buildings to provide flexible employment floorspace (Use Classes E(g)/B2/B8, with ancillary office accommodation within Use Class E (g)), together with the creation of a new vehicular access via Butterly Avenue, improvements to the existing vehicular access from Hawley Road, provision of car and cycle parking and service yards, drainage works, landscaping, installation of an acoustic fence and other associated works (variation of conditions 1 (approved plans), 2 (phase 2B drainage design), 4 (phasing) & 7 (levels) of permission Ref 25/00760/VCON to allow an interim Open Storage use on Phase 2B with associated works)

    Received 11 Feb, published by the council 26 Jul 2026 Amendments
  • 26/00267/VCON Granted

    Stone Pit 1 Atlas Park London Road Stone

    Erection of one and two storey buildings to provide a Neighbourhood Centre comprising of a mix of A1 (retail), A2 (financial and professional), A3 (restaurant/cafe), B1a (office) and D1 (medical centre/non-residential institution) uses with associated car parking, security fence and delivery space, provision of a Sports Club to comprise of football/sports pitches with clubhouse (use class D2) and associated car park, floodlights, enabling land level changes with retaining walls and security fencing, a new internal access road from London Road and the provision of recreational open space with accesses from London Road and Stone Place Road (variation of condition 2 to substitute drawings to allow a larger neighbourhood centre extent with minor changes to parking layout and landscaping and variations to 1, 3, 4, 11-25 to ensure that they refer to the most up to date drawings and details)

    Received 9 Mar, published by the council 26 Jul 2026 Amendments
  • 26/00385/VCON Granted

    Hayden Youth Association Leyton Cross Road Wilmington Kent

    Variation of condition (1) of planning permission 24/01456/VCON (which amended conditions 2, 3 and 14 of 95/00349/FUL) to vary the approved plans to allow the refurbishment of the club house and an enlarged extension (projecting by five metres rather than three as previously approved) to provide improved facilities

    Received 7 Apr, published by the council 26 Jul 2026 Amendments
  • 26/00279/VCON Granted

    Land At Dartford International Ferry Terminal Clipper Boulevard Dartford DA2 6QB

    Demolition of the existing buildings and redevelopment to provide commercial warehouse development with associated access, servicing, parking and landscaping (Variation of Condition 1 of planning permission ref: DA/25/01236/VCON to vary the approved listed plans to reflect minor design changes and variation of Condition 21 to extend the permitted uses at Unit 5 to include Class B2 (general industrial) in addition to the previously consented Class B8 (storage and distribution) use)

    Received 10 Mar, published by the council 26 Jul 2026 Amendments