Skip to content
PlanIndex Get alerts
Menu

Planning application

Land At Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

Awaiting decision Cumberland 25/0449 Discharge of Condition(s)

Works: Trees

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Discharge Of Conditions 8 (Highway Works); 10 (School Link); 11 (Underground Ducts); 13 (Archaeology); 15 (Contamination); 17 (Construction Method Statement); 19 (Noise Mitigation Measures); 20 (Siltation & Pollution Barriers); 21 (Biodiversity Enhancement Protection Plan); 23 (Landscaping); 25 (Tree Protection Barriers); 28 (Surface Water Drainage) & 29 (Foul Drainage) Of Previously Approved Application 09/0413

As published by the council, reference 25/0449

Application record

Reference
25/0449
Type
Discharge of Condition(s)
Status
Registered
Received
7 Aug 2025
Validated
7 Aug 2025
Ward
Multiple Wards
Parish
Cummersdale

Site history

Applications at this address on the Cumberland register

This site has had 10 applications since 2009: 6 approved, 0 refused.

  • 26/0359 Awaiting decision

    Land At Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

    Discharge Of Condition 26 (Landscape Management Plan) Of Previously Approved Permission 09/0413

    Submitted 25 Jun 2026 Conditions
  • 26/0306 Granted

    Land At Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

    Display Of 2no. Flags & 2no. Leaderboards Adjacent To Temporary Sales Cabin; 2no. V-Stacks & 4no. Flags Along Dalston Road & 2no. Straight Stacks At Entrance To Grange Drive

    Decided 11 Aug 2026 Advertising
  • 26/0067 Awaiting decision

    Land At Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

    Modification Of Planning Obligation Under Section 106A To Vary The Affordable Housing/Social Rent Split

    Submitted 10 Feb 2026 Conditions
  • 26/0017 Awaiting decision

    Land At Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

    Discharge Of Conditions 5 (Details Of Dwellings Plots 692 To 711); 7 (Landscape Plan) & 8 (Boundary Treatments) Of Previously Approved Application 21/0351

    Submitted 13 Jan 2026 Conditions
  • 14/0008 Granted

    Land At Morton Bounded by Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

    Certificate Of Existing Lawfulness Of The Demolition Of Cummersdale Grange Farm Complex

    Decided 28 Feb 2014 Lawful development
  • 13/0756 Granted

    Land at Morton bounded by Wigton Road, Peter Lane and Dalston Road, Carlisle, Cumbria

    Discharge Of Conditions 17 (Construction Method Statement); 19 (ON-SITE Noise Mitigation); 20 (Barriers) And 25 (Tree Protection Barriers) Of Previously Approved Application 09/0413

    Decided 16 Oct 2013 Conditions
  • 13/0207 Granted

    Land At Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

    Development Of Land At South Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, For Residential (Maximum 825 Dwellings), Employment (40,000m2 Floorspace), And Public Open Space Purposes As Well As Associated Works (Reserved Matters For Phase 1a Works Comprising Site Drainage Network; Construction Of Foul Pumping Station With Associated Access; Construction Of A Section Of Spine Road And Demolition Of Cummersdale Grange Farm Complex; And Information Submitted To Part Discharge Conditions 3 (Parameter Plans); 8 (Highway Works); 13 (Programme Of Archaeological Work); 15 (Scheme For Site Contamination); 22 (Hedgreows); 23 (Landscaping); 27 (Details Of Earthworks); 28 (Surface Water Drainage) And 29 (Foul Drainage) Pursuant To Outline Permission 09/0413)

    Decided 23 Jul 2013 Reserved matters
  • 12/0692 Granted

    Land At Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

    Development Of Land At South Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, For Residential (Maximum 825 Dwellings), Employment (40,000m2 Floorspace), And Public Open Space Purposes As Well As Associated Works (Reserved Matters For Infrastructure Development Including Vehicular Access, Drainage, Services And Landscaping Pursuant To Outline Permission 09/0413)

    Decided 19 Jul 2013 Reserved matters
  • 09/0413 Granted

    Land At Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

    Development Of Land At South Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, For Residential (Maximum 825 Dwellings), Employment (40,000m2 Floorspace), And Public Open Space Purposes As Well As Associated Works

    Decided 23 Nov 2010 Outline

Timeline

Dates from the published record

  1. 7 Aug 2025

    Received by Cumberland

  2. 18 Aug 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 2 October 2025, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Cumberland took a median of 56 days over the applications it decided in the last year.

Cases linked to this one on the register

  • Application: 09/0413 (Decided)

Documents

Plans, drawings, consultee responses and the officer's report

104 documents on file for this application

  • 0001 highways response 06072026 Consultee Comment · 06 Jul 2026
  • Rising main profile 05062026 Drawing · 05 Jun 2026
  • Drainage masterplan 05062026 Drawing · 05 Jun 2026
  • 0006 united utilities response 21042026 Consultee Comment · 21 Apr 2026
  • 0001 highways 25032026 Consultee Comment · 25 Mar 2026
  • 23 highway sections sheet 1 11112025 Drawing · 11 Nov 2025
  • 24 highway sections sheet 2 11112025 Drawing · 11 Nov 2025
  • 25 highway sections sheet 3 11112025 Drawing · 11 Nov 2025
  • 26 highway sections sheet 4 11112025 Drawing · 11 Nov 2025
  • 27 traffic signs and road markings sheet 1 11112025 Drawing · 11 Nov 2025
  • 28 traffic signs and road markings sheet 2 11112025 Drawing · 11 Nov 2025
  • 29 traffic signs and road markings sheet 3 11112025 Drawing · 11 Nov 2025
  • 30 traffic signs and road markings sheet 4 11112025 Drawing · 11 Nov 2025
  • 31 kerb and surfacing spine and link road sheet 1 11112025 Drawing · 11 Nov 2025
  • 32 kerb and surfacing spine and link road sheet 2 11112025 Drawing · 11 Nov 2025
  • 33 kerb and surfacing spine and link road sheet 3 11112025 Drawing · 11 Nov 2025
  • 34 kerb and surfacing spine and link road sheet 4 11112025 Drawing · 11 Nov 2025
  • 35 road setting out tables spine and link road sheet 1 11112025 Drawing · 11 Nov 2025
  • 36 road setting out tables spine and link road sheet 2 11112025 Drawing · 11 Nov 2025
  • 37 road setting out spine and link road sheet 1 11112025 Drawing · 11 Nov 2025
  • 38 road setting out spine and link road sheet 2 11112025 Drawing · 11 Nov 2025
  • 39 road setting out spine and link road sheet 3 11112025 Drawing · 11 Nov 2025
  • 40 road setting out spine and link road sheet 4 11112025 Drawing · 11 Nov 2025
  • 41 highway alignments sheet 2 11112025 Drawing · 11 Nov 2025
  • 42 highway alignments sheet 3 11112025 Drawing · 11 Nov 2025
  • 43 highway alignments sheet 4 11112025 Drawing · 11 Nov 2025
  • 45 highway alignments sheet 5 11112025 Drawing · 11 Nov 2025
  • 46 manhole schedules spine and link road 11112025 Drawing · 11 Nov 2025
  • 47 crossover culvert details sheet 1 11112025 Drawing · 11 Nov 2025
  • 48 longitudinal sections spine and link road sheet 2 11112025 Drawing · 11 Nov 2025
  • 49 longitudinal sections spine and link road sheet 3 11112025 Drawing · 11 Nov 2025
  • 50 longitudinal sections spine and link road sheet 3 11112025 Drawing · 11 Nov 2025
  • 51 pond general arrangement sheet 1 11112025 Drawing · 11 Nov 2025
  • 52 pond general arrangement sheet 2 11112025 Drawing · 11 Nov 2025
  • 53 drainage layout spine and link road sheet 1 11112025 Drawing · 11 Nov 2025
  • 54 drainage layout spine and link road sheet 2 11112025 Drawing · 11 Nov 2025
  • 55 drainage layout spine and link road sheet 3 11112025 Drawing · 11 Nov 2025
  • 56 drainage layout spine and link road sheet 4 11112025 Drawing · 11 Nov 2025
  • 57 culvert opening works sheet 1 11112025 Drawing · 11 Nov 2025
  • 58 kerb and surfacing phase 2 11112025 Drawing · 11 Nov 2025
  • 59 road setting out tables phase 2 11112025 Drawing · 11 Nov 2025
  • 60 road setting out phase 2 11112025 Drawing · 11 Nov 2025
  • 61 long sections phase 2 sheet 1 11112025 Drawing · 11 Nov 2025
  • 62 long sections phase 2 sheet 2 11112025 Drawing · 11 Nov 2025
  • 63 manhole schedules phase 2 11112025 Drawing · 11 Nov 2025
  • 64 road setting out tables phase 1 11112025 Drawing · 11 Nov 2025
  • 65 longitudinal sections phase 1 sheet 1 11112025 Drawing · 11 Nov 2025
  • 66 drainage layout phase 1 11112025 Drawing · 11 Nov 2025
  • 67 drainage layout phase 2 11112025 Drawing · 11 Nov 2025
  • 68 plot drainage sheet 1 11112025 Drawing · 11 Nov 2025
  • 69 plot drainage sheet 2 11112025 Drawing · 11 Nov 2025
  • 70 plot drainage sheet 3 11112025 Drawing · 11 Nov 2025
  • 71 plot drainage sheet 1 11112025 Drawing · 11 Nov 2025
  • 72 plot drainage sheet 2 11112025 Drawing · 11 Nov 2025
  • 73 plot drainage sheet 3 11112025 Drawing · 11 Nov 2025
  • 74 plot drainage sheet 4 11112025 Drawing · 11 Nov 2025
  • Appendix iii logs final 11112025 BackGround Papers · 11 Nov 2025
  • 75 road crossings 11112025 Drawing · 11 Nov 2025
  • Additional ground investigation 11112025 BackGround Papers · 11 Nov 2025
  • Surface water management plan persimmon 11112025 BackGround Papers · 11 Nov 2025
  • Surface water management plan charles church 11112025 BackGround Papers · 11 Nov 2025
  • Project environmental plan charles church 11112025 BackGround Papers · 11 Nov 2025
  • Project environmental plan persimmon 11112025 BackGround Papers · 11 Nov 2025
  • 76 tree survey sheet 1 of 5 11112025 Drawing · 11 Nov 2025
  • 77 tree survey sheet 2 of 5 11112025 Drawing · 11 Nov 2025
  • 78 tree survey sheet 3 of 5 11112025 Drawing · 11 Nov 2025
  • 79 tree survey sheet 4 of 5 11112025 Drawing · 11 Nov 2025
  • 80 tree survey sheet 5 of 5 11112025 Drawing · 11 Nov 2025
  • Tree survey 11112025 BackGround Papers · 11 Nov 2025
  • 0004 environment agency response 29082025 Consultee Comment · 29 Aug 2025
  • 0001 highways response 28082025 Consultee Comment · 28 Aug 2025
  • 0006 united utilities response 19082025 Consultee Comment · 19 Aug 2025
  • 0002 historic environment officer response 14082025 Consultee Comment · 14 Aug 2025
  • Application form redacted 07082025 Application Form · 12 Aug 2025
  • 23 existing services layout 07082025 Drawing · 12 Aug 2025
  • 24 phasing plan 07082024 Drawing · 12 Aug 2025
  • Noise impact assessment 07082025 BackGround Papers · 12 Aug 2025
  • Tree survey 07082025 BackGround Papers · 12 Aug 2025
  • Construction environmental management plan 07082025 BackGround Papers · 12 Aug 2025
  • 01 detailed landscape proposals 1 of 7 07082025 Drawing · 12 Aug 2025
  • 02 detailed landscape proposals 2 of 7 07082025 Drawing · 12 Aug 2025
  • 03 detailed landscape proposals 3 of 7 07082025 Drawing · 12 Aug 2025
  • 04 detailed landscape proposals 4 of 7 07082025 Drawing · 12 Aug 2025
  • 05 detailed landscape proposals 5 of 7 07082025 Drawing · 12 Aug 2025
  • 06 detailed landscape proposals 6 of 7 07082025 Drawing · 12 Aug 2025
  • 07 detailed landscape proposals 7 of 7 07082025 Drawing · 12 Aug 2025
  • 08 survey of existing trees 1 of 5 07082025 Drawing · 12 Aug 2025
  • 09 survey of existing trees 2 of 5 07082025 Drawing · 12 Aug 2025
  • 10 survey of existing trees 3 of 5 07082025 Drawing · 12 Aug 2025
  • 11 survey of existing trees 4 of 5 07082025 Drawing · 12 Aug 2025
  • 12 survey of existing trees 5 of 5 07082025 Drawing · 12 Aug 2025
  • 13 drainage layout spine and link road sheet 4 07082025 Drawing · 12 Aug 2025
  • 13 drainage layout phase 1 07082025 Drawing · 12 Aug 2025
  • 14 road setting out phase 1 sheet 2 07082025 Drawing · 12 Aug 2025
  • 15 traffic signs and road markings phase 1 07082025 Drawing · 12 Aug 2025
  • 16 kerb and surfacing phase 1 07082025 Drawing · 12 Aug 2025
  • 17 road setting out tables phase 1 07082025 Drawing · 12 Aug 2025
  • 18 road setting out phase 1 sheet 1 07082025 Drawing · 12 Aug 2025
  • Superseded 19 longitudinal sections phase 1 sheet 1 07082025 Drawing · 12 Aug 2025
  • 20 manhole schedules 07082025 Drawing · 12 Aug 2025
  • 21 manhole schedules phase 1 07082025 Drawing · 12 Aug 2025
  • 22 school link phasing 07082025 Drawing · 12 Aug 2025
  • Biodiversity enhancement and protection plan 07082025 BackGround Papers · 12 Aug 2025
  • Ground investigation 07082025 BackGround Papers · 12 Aug 2025

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Cumberland for determination, against a statutory target of eight weeks. Over the last year Cumberland decided condition discharge and variation applications in a median of 56 days. More in our guide to how long planning decisions take.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Land At Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

    13/0207 Submitted 14 Mar 2013 50 yards away

    Development Of Land At South Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, For Residential (Maximum 825 Dwellings), Employment (40,000m2 Floorspace), And Public Open Space Purposes As Well As Associated Works (Reserved Matters For Phase 1a Works Comprising Site Drainage Network; Construction Of Foul Pumping Station With Associated Access; Construction Of A Section Of Spine Road And Demolition Of Cummersdale Grange Farm Complex; And Information Submitted To Part Discharge Conditions 3 (Parameter Plans); 8 (Highway Works); 13 (Programme Of Archaeological Work); 15 (Scheme For Site Contamination); 22 (Hedgreows); 23 (Landscaping); 27 (Details Of Earthworks); 28 (Surface Water Drainage) And 29 (Foul Drainage) Pursuant To Outline Permission 09/0413)

    Granted Reserved matters Demolition 42 docs
    Major scheme
  • Land south of Morton Park bounded by Garden Village and Peter Lane, Dalston Road, Carlisle

    26/0080 Submitted 19 Feb 2026 50 yards away

    Non Material Amendment Of Previously Approved Permission 21/0351 To Reword Condition 9 (Construction Traffic)

    Decided Amendments 4 docs
  • Land at Morton bound by, Wigton Road, Peter Lane And, Dalston Road, Cumbria

    26/0077 Submitted 17 Feb 2026 50 yards away

    Non Material Amendment Of Previously Approved Permission 21/0351

    Decided Amendments 31 docs
  • Land At Morton Bounded By Wigton Road, Peter Lane And Dalston Road, Carlisle, Cumbria

    26/0067 Submitted 10 Feb 2026 50 yards away

    100% historically approved · decision due ~11 Jun

    Modification Of Planning Obligation Under Section 106A To Vary The Affordable Housing/Social Rent Split

    Awaiting decision Conditions 4 docs
  • Land at Morton bounded by Wigton Road, Peter Lane and Dalston Road, Carlisle, Cumbria

    13/0756 Submitted 19 Sep 2013 50 yards away

    Discharge Of Conditions 17 (Construction Method Statement); 19 (ON-SITE Noise Mitigation); 20 (Barriers) And 25 (Tree Protection Barriers) Of Previously Approved Application 09/0413

    Granted Conditions Trees 11 docs
  • Land at Morton bound by, Wigton Road, Peter Lane And, Dalston Road, Cumbria

    26/0198 Submitted 2 Apr 2026 50 yards away

    Continued Display Of 4no. Flag Poles And Banners Within The Layby Area Consisting Of Both Persimmon Homes And Charles Church Advertising, And 'V' Stack Signage; Display Of 5no. Flag Poles And Banners To Be Erected Surrounding The Temporary Construction Access Road And The Temporary Sales Cabins And Associated Car Parking Area On Dalston Road Frontage

    Granted Advertising 9 docs

In Cumberland

  • 26/0465 Granted

    Orton Hall, Great Orton, Carlisle, CA5 6NA

    Discharge Of Condition 3 (Surface Water Drainage Works) Of Previously Approved Permission 26/0277

    Received 19 Aug, published by the council 27 Aug 2026 Conditions
  • 26/0553 Awaiting decision

    First & Second Floors, 18-24 Lonsdale Street, Carlisle, CA1 1DB

    Discharge Of Condition 6 (Window & External Door Details); 7 (Details Of Roof Vents, Venitilation Grilles, Flues & Soil Pipes) & 9 (Construction Environmental Management Plan) Of Previously Approved Application 26/0061

    Received 6 Oct, published by the council 9 Oct 2026 Conditions
  • 4/26/2255/0B1 Granted

    NEW HOUSE FARM, DRIGG

    VARIATION OF CONDITION 2 (PLANS) OF PLANNING APPLICATION 4/26/2048/0R1 - APPLICATION FOR APPROVAL OF RESERVED MATTERS RELATING TO APPEARANCE, LANDSCAPING, LAYOUT & SCALE PURSUANT TO OUTLINE PLANNING APPROVAL 4/24/2281/0O1

    Received 10 Aug, published by the council 14 Aug 2026 Conditions
  • 4/26/2254/0B1 Granted

    LAND BETWEEN GRIFFIN CLOSE & GREENVALE COURT, FRIZINGTON

    VARIATION OF CONDITION 2 (PLANS) OF PLANNING APPLICATION 4/24/2252/0F1 - ERECTION OF 17 NO. 2 BEDROOM DWELLINGS AND ASSOCIATED EXTERNAL WORKS

    Received 6 Aug, published by the council 14 Aug 2026 Conditions
  • 4/26/2273/DOC Granted

    LAND OFF DALZELL STREET, MOOR ROW, EGREMONT

    DISCHARGE OF CONDITION 9 (iii) OF PLANNING APPROVAL 4/23/2076/0O1 FOR PLOTS 17, 18 AND 49

    Received 2 Sep, published by the council 6 Oct 2026 Conditions