Planning application

Land To The North West Of Ludwell Eastgate DL13 2LG

Awaiting decision County Durham DM/26/02338/MIN

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Installation of abstraction boreholes, reinjection boreholes and lithium processing plant to enable lithium production for a period of 40 years followed by decommissioning and restoration

As published by the council, reference DM/26/02338/MIN

Application record

Reference
DM/26/02338/MIN
Status
Pending Consideration
Received
4 Sep 2026
Validated
23 Sep 2026
Ward
Weardale
Parish
Stanhope
Decision by
Committee
Postcode
DL13 2LG

Timeline

Dates from the published record

  1. 4 Sep 2026

    Received by County Durham

  2. 23 Sep 2026

    Validated

    Checked as complete and ready for consideration.

  3. 2 Oct 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 18 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    County Durham took a median of 58 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

Zetland Group Limited Agent, registered in Redcar

Active · incorporated 2006 · Redcar

3 applications on PlanIndex · across 3 councils

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

97 documents on file for this application

  • NEIGHBOUR NOTIFICATION LIST Neighbour Notification List · 02 Oct 2026
  • ENVIRONMENTAL STATEMENT - MAIN TEXT Supporting Information · 22 Sep 2026
  • AGRICULTURAL HOLDINGS CERTIFICATE Supporting Information · 22 Sep 2026
  • PLANNING STATEMENT AND ENVIRONMENTAL REPORTS Supporting Information · 22 Sep 2026
  • PLANNING STATEMENT - APP 11 - AGRICULTURAL LAND CLASSIFICATION AND SOIL MANAGEME Supporting Information · 22 Sep 2026
  • PLANNING STATEMENT - APP 12 - STATEMENT OF COMMUNITY INVOLVEMENT Supporting Information · 22 Sep 2026
  • PLANNING STATEMENT - APP 2 - PRELIMINARY DESIGN AND ACCESS REPORT Supporting Information · 22 Sep 2026
  • PLANNING STATEMENT - APP 10 - AIR EMISSIONS Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 4.B2 - BNG METRIC CALC TOOL (MAC-OFF) Supporting Information · 04 Sep 2026
  • MINERALS APPLICATION FORM (M1) Supporting Information · 04 Sep 2026
  • COVER LETTER Supporting Information · 04 Sep 2026
  • PHASE 2 LITHIUM PRODUCTION (40 YEARS): PROPOSED LAYOUT PLAN 4 OF 4 - REINJECTION Drawing · 04 Sep 2026
  • PHASE 2 LITHIUM PRODUCTION (40 YEARS): PROPOSED LAYOUT PLAN 2 OF 4 - ABSTRACTION Drawing · 04 Sep 2026
  • PHASE 2 LITHIUM PRODUCTION (40 YEARS): PROPOSED SECTION PLAN 2 OF 4 - ABSTRACTI Drawing · 04 Sep 2026
  • PHASE 2 LITHIUM PRODUCTION (40 YEARS): PROPOSED SECTION PLAN 1 OF 4 - PRODUCTIO Drawing · 04 Sep 2026
  • PHASE 2 LITHIUM PRODUCTION (40 YEARS): PROPOSED LAYOUT PLAN 3 OF 4 - ABSTRACTION Drawing · 04 Sep 2026
  • PHASE 3 BOREHOLE PLUGGING, ABANDONMENT AND SITE DECOMMISSIONING: PROPOSED LAYOUT Drawing · 04 Sep 2026
  • PHASE 3 BOREHOLE PLUGGING, ABANDONMENT AND SITE DECOMMISSIONING: PROPOSED LAYOUT Drawing · 04 Sep 2026
  • PHASE 3 BOREHOLE PLUGGING, ABANDONMENT AND SITE DECOMMISSIONING: PROPOSED SECTIO Drawing · 04 Sep 2026
  • PHASE 3 BOREHOLE PLUGGING, ABANDONMENT AND SITE DECOMMISSIONING: PROPOSED LAYOUT Drawing · 04 Sep 2026
  • PHASE 3 BOREHOLE PLUGGING, ABANDONMENT AND SITE DECOMMISSIONING: PROPOSED SECTIO Drawing · 04 Sep 2026
  • PHASE 3 BOREHOLE PLUGGING, ABANDONMENT AND SITE DECOMMISSIONING: PROPOSED LAYOUT Drawing · 04 Sep 2026
  • PHASE 3 BOREHOLE PLUGGING, ABANDONMENT AND SITE DECOMMISSIONING: PROPOSED SECTIO Drawing · 04 Sep 2026
  • PHASE 3 BOREHOLE PLUGGING, ABANDONMENT AND SITE DECOMMISSIONING: PROPOSED SECTIO Drawing · 04 Sep 2026
  • PHASE 3 BOREHOLE PLUGGING, ABANDONMENT AND SITE DECOMMISSIONING: PROPOSED LAYOUT Drawing · 04 Sep 2026
  • ADDITONAL DETAILS - PROPOSED BOUNDARY ENCLOSURE FENCING Drawing · 04 Sep 2026
  • ADDITONAL DETAILS - TYPICAL PIPELINE DESIGN AND SECTIONS Drawing · 04 Sep 2026
  • ADDITONAL DETAILS - PROPOSED MAIN ACCESS GATE ARRANGEMENT Drawing · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - NON-TECH SUMMARY Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 4 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 3 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 5 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 1 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 2 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 6.A - PART 3 - LVIA APP 2 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 6.A - PART 4 - LVIA APP 3 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 6.A - PART 1 - LVIA MAIN TEXT Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 6.A - PART 2 - LVIA APP 1 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 6.A - PART 5 - LVIA APP 4.1 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 6.A - PART 6 - LVIA APP 4.2 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 7 AND END Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 6.A - PART 7 - LVIA APP 5 Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 6.A - PART 8 - PLANS Supporting Information · 04 Sep 2026
  • ENVIRONMENTAL STATEMENT - APPENDIX 6.B Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 1 - GROUND INVESTIGATIONS Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 3 - DESIGN AND ACCESS REPORT Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 4.A - PART 2 - ECOLOGY APPENDICES Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 4.B1 - ECOLOGY BNG ASSESSMENT Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 4.A - PART 1 - ECOLOGY MAIN TEXT AND DRAWINGS Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 4.C - ECOLOGY HMMP Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 5 - NOISE Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 7 - ARBORICULTURE Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 6.B - LIGHTING DRAWINGS Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 6.C - LIGHTING PLANS Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 6.A - LIGHTING - MAIN TEXT Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 8 - CULTURAL HERITAGE Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 9.A - PART 2 - TRANSPORT STATEMENT - APPENDICES Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 9.A - PART 1 - TRANSPORT STATEMENT MAIN TEXT Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 9.B - PART 2 - TRAFFIC MGMT PLAN - APPENDICES Supporting Information · 04 Sep 2026
  • PLANNING STATEMENT - APP 9.B - PART 1 - TRAFFIC MGMT PLAN - MAIN TEXT Supporting Information · 04 Sep 2026
  • PHASE 1 - PROPOSED LAYOUT PLAN 2 OF 4 - ABSTRACTION BORE Drawing · 04 Sep 2026
  • PHASE 1 ENABLING WORKS, BOREHOLE INSTALLATION AND PROCESSING PLANT CONSTRUCTION: Drawing · 04 Sep 2026
  • PHASE 1 ENABLING WORKS, BOREHOLE INSTALLATION AND PROCESSING PLANT CONSTRUCTION: Drawing · 04 Sep 2026
  • PHASE 1 ENABLING WORKS, BOREHOLE INSTALLATION AND PROCESSING PLANT CONSTRUCTION: Drawing · 04 Sep 2026
  • PHASE 1 ENABLING WORKS, BOREHOLE INSTALLATION AND PROCESSING PLANT CONSTRUCTION: Drawing · 04 Sep 2026
  • PHASE 1 ENABLING WORKS, BOREHOLE INSTALLATION AND PROCESSING PLANT CONSTRUCTION: Drawing · 04 Sep 2026
  • PHASE 1 ENABLING WORKS, BOREHOLE INSTALLATION AND PROCESSING PLANT CONSTRUCTION: Drawing · 04 Sep 2026
  • LANDSCAPE AND ENVIRONMENTAL ENHANCEMENT Drawing · 04 Sep 2026
  • FRONT END PROCESSING BUILDING - ELEVATIONS Drawing · 04 Sep 2026
  • MAIN PROCESS BUILDING - ROOF PLAN Drawing · 04 Sep 2026
  • OFFICE AND CONTROL ROOM BUILDING - ELEVATIONS Drawing · 04 Sep 2026
  • FRONT END PROCESSING BUILDING - ROOF PLAN Drawing · 04 Sep 2026
  • MAIN BLOCK - SOUTH ELEVATION B Drawing · 04 Sep 2026
  • OFFICE AND CONTROL ROOM BUILDING - ROOF PLAN Drawing · 04 Sep 2026
  • MAIN BLOCK - NORTH ELEVATION B Drawing · 04 Sep 2026
  • PHASE 2 LITHIUM PRODUCTION (40 YEARS): PROPOSED LAYOUT PLAN - COMPOSITE Drawing · 04 Sep 2026
  • MAIN BLOCK - EXTRACTION DEVELOPMENT Drawing · 04 Sep 2026
  • MAIN BLOCK - SOUTH ELEVATION A Drawing · 04 Sep 2026
  • PHASE 2 LITHIUM PRODUCTION (40 YEARS): PROPOSED LAYOUT PLAN 1 OF 4 - PRODUCTION Drawing · 04 Sep 2026
  • PHASE 2 LITHIUM PRODUCTION (40 YEARS): PROPOSED ROOF PLAN - MAIN PRODUCTION BUIL Drawing · 04 Sep 2026
  • MAIN BLOCK - EAST AND WEST ELEVATION Drawing · 04 Sep 2026
  • PHASE 2 LITHIUM PRODUCTION (40 YEARS): PROPOSED SECTION PLAN 3 OF 4 - ABSTRACTI Drawing · 04 Sep 2026
  • PHASE 2 LITHIUM PRODUCTION (40 YEARS): PROPOSED SECTION PLAN 4 OF 4 - REINJECTI Drawing · 04 Sep 2026
  • EXISTING LAYOUT PLAN 1 OF 4 - PRODUCTION FACILITY AREA 5 Drawing · 04 Sep 2026
  • EXISTING LAYOUT PLAN 2 OF 4 - ABSTRACTION BOREHOLE SITE #1 Drawing · 04 Sep 2026
  • EXISTING SECTIONS 1 OF 4 - PRODUCTION FACILITY AREA 500 Drawing · 04 Sep 2026
  • EXISTING LAYOUT PLAN 3 OF 4 - ABSTRACTION BOREHOLE SITE #2 Drawing · 04 Sep 2026
  • EXISTING LAYOUT PLAN 4 OF 4 - REINJECTION BOREHOLE SITE Drawing · 04 Sep 2026
  • EXISTING SECTIONS 3 OF 4 - ABSTRACTION BOREHOLE SITE 2 5 #2 Drawing · 04 Sep 2026
  • EXISTING SECTIONS 4 OF 4 - REINJECTION BOREHOLE SITE 500 Drawing · 04 Sep 2026
  • EXISTING SECTIONS 2 OF 4 - ABSTRACTION BOREHOLE SITE 1 5 #1 Drawing · 04 Sep 2026
  • PHASE 1 ? ENABLING WORKS, BOREHOLE INSTALLATION & PROCESSING PLANT CONSTRUCTION: Drawing · 04 Sep 2026
  • PHASE 1 ? ENABLING WORKS, BOREHOLE INSTALLATION & PROCESSING PLANT CONSTRUCTION: Drawing · 04 Sep 2026
  • APPLICATIONFORMREDACTED Application Form · 04 Sep 2026
  • LOCATION PLAN (SITE OF APPLICATION) OS Extract · 04 Sep 2026
  • LOCATION PLAN (SITE OF APPLICATION) OS Extract · 04 Sep 2026
  • EXISTING LAYOUT PLAN - COMPOSITE 2500 SCALE A2 Drawing · 04 Sep 2026

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with County Durham for determination, against a statutory target of eight weeks. Over the last year County Durham's median decision took 58 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on County Durham's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles