Skip to content
PlanIndex Get alerts
Menu

Planning application

Trenithon Farm Trenithon Lane Summercourt Newquay Cornwall TR8 5BJ

Awaiting decision Cornwall PA26/06205 Overhead Electricity Lines

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Overhead Electricity Lines application to add a third wire to be erected on a section of existing high voltage network

As published by the council, reference PA26/06205

Application record

Reference
PA26/06205
Type
Overhead Electricity Lines
Status
Awaiting decision
Received
7 Sep 2026
Validated
7 Sep 2026
Ward
St Dennis And St Enoder
Parish
St. Enoder
Postcode
TR8 5BJ

Site history

Applications at this address on the Cornwall register

This site has had 2 applications since 2021.

  • Trenithon Farm Trenithon Lane Summercourt Newquay Cornwall TR8 5BJ

    Pre application advice to demolish existing house and replace with 3 modern houses

    Decided 29 Apr 2021 Outline

Timeline

Dates from the published record

  1. 7 Sep 2026

    Received by Cornwall

  2. 17 Sep 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 2 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Cornwall took a median of 49 days over the applications it decided in the last year.

Documents

Plans, drawings, consultee responses and the officer's report

4 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Cornwall for determination, against a statutory target of eight weeks. Over the last year Cornwall decided less common application types in a median of 35 days. More in our guide to how long planning decisions take.

About less common application types

This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.

Nearby applications

Within 500 metres

In Cornwall

  • PA26/06019 Awaiting decision

    Treago Mill Treago Road Crantock Newquay Cornwall TR8 5QS

    NGED have received a connection request and three phase. To enable this connection there is a requirement to add a third wire to the overhead high voltage network from pole number 43AAE7 to 43AAF6, over 6 spans and a total of 381M, highlighted in green on the plan CE6038598SECT37. The existing high voltage overhead network from pole 43AAF6 to 43AAF8, over 2 spans and a total of 171M will be dismantled, highlighted in blue on the plan and replaced by an underground high voltage cable shown as the brown line on the plan. There is also a requirement to erect a lazy leg pole alongside pole number 43AAF8 to support the larger three phase transformer, highlighted in pink on the plan

    28 Aug 2026 Other
  • PA26/04973 Granted

    Truthan Manor Truthan St Erme Truro Cornwall TR4 9BB

    Overhead Electricity Lines application to add a 3rd wire to an existing 11kv overhead line

    16 Jul 2026 Other
  • PA26/05516 Decided

    Little Trethellan Trethellan Lanner Redruth Cornwall TR16 6BP

    Notification of change of use under Class R from agricultural building to a flexible commercial use consisting of storage or distribution (Class B8) and offices (Class E)

    7 Aug 2026 Other
  • PA26/04833 Granted

    Shelton Farm Delabole Cornwall PL33 9DA

    -Erect new terminal pole at 43LC4 add a back stay to support OHL and install new underground cable pole termination -Install new HV underground cable from 43LC4 to new H-Pole at 43LC5. -Install new H-pole at 43LC5 new position as per plan and installed new HV and LV earth wires as required. Reconnect existing low voltage network via new underground cables as shown on attached plan -Install new HV cable from new poles at 43LC5 to 43LC9 with associated earth wires as necessary. -Install new terminal pole at 43LC9 and backstay to support OHL and install new underground cable pole termination -Dismantle all redundant equipment between 43LC4 and 43LC9 as shown highlighted blue on plan. Existing underground cable to be disconnected from network, made safe and abandoned in situ

    10 Jul 2026 Other
  • PA26/05569 Awaiting decision

    Lower Tolcarne Farm St Allen Truro Cornwall TR4 9QX

    Overhead Electricity Lines to add a 3rd wire to an existing 11kv overhead line

    10 Aug 2026 Other