Planning application
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Relates to 25/00459/FULL
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Submission of details of Construction Management Plan pursuant to condition 2 of Planning Permission 25/00459/FULL dated 30.01.2026.
As published by the council, reference 26/01572/MDC
Application record
- Reference
- 26/01572/MDC
- Status
- Under Consideration
- Received
- 3 Nov 2026
- Validated
- 3 Nov 2026
- Postcode
- EC2Y 8BB
Site history
Applications at this address on the City of London register
This site has had 15 applications since 2023: 12 approved, 0 refused.
-
26/00527/MDC Granted
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Submission of details of proposed fencing around ductwork; and details of external ductwork and ASHP enclosure including colour and finish pursuant to condition 6 of planning permission 25/00459/FULL dated 30/01/2026.
-
25/01616/MDC Awaiting decision
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Submission of a scheme of protective works; details relating to mounting of mechanical plant to minimise transmission of structure borne sound or vibration; and details of plant noise, installation and maintenance pursuant to conditions 4, 5 and 7 of planning permission 25/00461/FULL dated 02/10/2025.
-
25/01567/MDC Awaiting decision
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Submission of details and material samples of the proposed replacement paviours to be installed in the case of any paviours irreplaceably damaged during construction pursuant to condition 3 of Listed Building Consent 25/00462/LBC dated 02/10/2025.
-
25/00462/LBC Granted
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Various repair and improvement works to the City of London School for girls building to include; High Level windows - full replacement of high-level clerestory windows onto new upstand, remedial repair and re-waterproofing works to flat roof immediately in front of windows. Facade windows - remedial repair works to replace damaged seals, stays, replace missing ironmongery and localised planing to window frames to relieve stuck windows. Main Roof - Re-waterproofing to areas of roof where previous coating has failed, new lead flashing to perimeter of roof light eaves, and renewed waterproofing junction at base of lantern louvres. Prep Block Roof - Repair damaged surrounds to rainwater pipes, repair damaged brick tiles to match existing, replacement of temporary flashing repair with new lead flashing around steps. Bridges - New structural steel beams to foot bridges on south elevation, introduction of air bricks and ventilation cowls and insulation to ceiling void. New waterproofing to concrete slab. Physics Classrooms - Conversion of three existing classrooms and cloakroom into two physics labs and a prep room. Medical Room - Refurbishment of existing medical room and adjacent accessible WC. Switchgear - Removal of redundant cables, replacement doors.
-
25/00461/FULL Granted
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Various repair and improvement works to the City of London School for girls building to include; High Level windows - full replacement of high-level clerestory windows onto new upstand, repair and waterproofing works to adjacent roof; Facade windows - repair works and alteration to physics lab window on northern elevation; Main Roof - Waterproofing to areas of roof where previous coating has failed, new lead flashing to perimeter of roof light eaves and renewed waterproofing junction at base of lantern louvres; Prep Block Roof - Repair damaged surrounds to rainwater pipes, replacement of temporary flashing repair with new lead flashing around steps; Bridges - New structural steel beams to foot bridges on south elevation, introduction of air bricks and ventilation cowls and insulation to ceiling void. New waterproofing to concrete slab; and associated works.
-
25/00460/LBC Granted
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Removal of existing ventilation provisions to swimming pool. New ventilation and associated plant equipment to be installed including new air source heat pump.
-
25/00459/FULL Granted
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Removal of existing ventilation provisions to swimming pool. New ventilation and associated plant equipment to be installed including new air source heat pump.
-
25/00366/FULL Granted
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Removal of existing weighted man-safe system and fixed safety lines to roof, and installation of new free standing safety railings.
-
25/00367/LBC Granted
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Removal of existing weighted man-safe system and fixed safety lines to roof, and installation of new free standing safety railings.
-
24/00447/LBC Granted
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Proposed design relating to internal remodelling of Level C Dining Hall and Kitchen. The application includes proposed alterations to the internal partitions, mechanical services, ceilings and floors within the East end of Level C.
Timeline
Dates from the published record
-
3 Nov 2026
Received by City of London
-
16 Nov 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 29 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
City of London took a median of 86 days over the applications it decided in the last year.
Related applications
Cases linked to this one on the register
-
25/00459/FULL Granted
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Removal of existing ventilation provisions to swimming pool. New ventilation and associated plant equipment to be installed including new air source heat pump.
Documents
The council has not published drawings yet. We check again and tell you when they appear.
2 documents on file for this application
- APPLICATIONFORMREDACTED
- CLSG PLAN SUMMER 2026 V4 (002)
Watch members (£5 a month) open the document list from here.
Open the documentsWorking a patch? Trade sends you every new job in your area each morning. 14 days free.
What happens while it is decided
This application is with City of London for determination, against a statutory target of eight weeks. Over the last year City of London's median decision took 86 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on City of London's portal will say. Our guide explains the common types.
Nearby applications
Within 0.3 miles
-
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Retrospective application for internal works within Level A including: (i) demolition and refurbishment of existing reception area fit-out; (ii) remodelling of administration suite; (iii) refurbishment of existing bathrooms, cloakroom and headmistress office into new bathrooms, teapoint, school office, various alterations to headteachers office and a new cleaners store, and other associated works.
-
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Submission of details of proposed fencing around ductwork; and details of external ductwork and ASHP enclosure including colour and finish pursuant to condition 6 of planning permission 25/00459/FULL dated 30/01/2026.
-
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Various repair and improvement works to the City of London School for girls building to include; High Level windows - full replacement of high-level clerestory windows onto new upstand, remedial repair and re-waterproofing works to flat roof immediately in front of windows. Facade windows - remedial repair works to replace damaged seals, stays, replace missing ironmongery and localised planing to window frames to relieve stuck windows. Main Roof - Re-waterproofing to areas of roof where previous coating has failed, new lead flashing to perimeter of roof light eaves, and renewed waterproofing junction at base of lantern louvres. Prep Block Roof - Repair damaged surrounds to rainwater pipes, repair damaged brick tiles to match existing, replacement of temporary flashing repair with new lead flashing around steps. Bridges - New structural steel beams to foot bridges on south elevation, introduction of air bricks and ventilation cowls and insulation to ceiling void. New waterproofing to concrete slab. Physics Classrooms - Conversion of three existing classrooms and cloakroom into two physics labs and a prep room. Medical Room - Refurbishment of existing medical room and adjacent accessible WC. Switchgear - Removal of redundant cables, replacement doors.
-
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Removal of existing weighted man-safe system and fixed safety lines to roof, and installation of new free standing safety railings.
-
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Removal of existing weighted man-safe system and fixed safety lines to roof, and installation of new free standing safety railings.
-
City of London School For Girls St Giles' Terrace Barbican London EC2Y 8BB
Various repair and improvement works to the City of London School for girls building to include; High Level windows - full replacement of high-level clerestory windows onto new upstand, repair and waterproofing works to adjacent roof; Facade windows - repair works and alteration to physics lab window on northern elevation; Main Roof - Waterproofing to areas of roof where previous coating has failed, new lead flashing to perimeter of roof light eaves and renewed waterproofing junction at base of lantern louvres; Prep Block Roof - Repair damaged surrounds to rainwater pipes, replacement of temporary flashing repair with new lead flashing around steps; Bridges - New structural steel beams to foot bridges on south elevation, introduction of air bricks and ventilation cowls and insulation to ceiling void. New waterproofing to concrete slab; and associated works.