Skip to content
PlanIndex Get alerts
Menu

Planning application

Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

Awaiting decision City of London 26/01406/LBC Heritage and listed buildings

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Strengthening works to existing corbels at the Barbican Centre, and associated works.

As published by the council, reference 26/01406/LBC

Application record

Reference
26/01406/LBC
Category
Heritage and listed buildings
Status
Under Consideration
Received
6 Oct 2026
Validated
6 Oct 2026
Postcode
EC2Y 8DS

Site history

Applications at this address on the City of London register

This site has had 14 applications since 2022: 11 approved, 0 refused.

  • 26/01139/LBC Granted

    Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    Upgrade of existing and installation of additional evacuation signage and downlights within the Concert Hall, and associated works.

    Decided 24 Sep 2026 Heritage and listed buildings
  • 26/00612/FULL Granted

    Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    New hard and soft landscaping for the sculpture court to include removal and replacement of all paving with new waterproofing below, new ramps and steps, new raised planting beds, seating, and lighting, proposed parameters for temporary structures and artworks to facilitate continued use of the sculpture court for art installations, works to the staff spaces facades to upgrade glazing and frames to level 2 and other associated works.

    Decided 18 Sep 2026 Full applications
  • 26/00613/LBC Granted

    Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    New hard and soft landscaping for the sculpture court to include removal and replacement of all paving with new waterproofing below, new ramps and steps, new raised planting beds, seating, lighting, and drinking water fountain. Works to the staff spaces to include internal reconfiguration, new WCs, showers, and kitchenette, works to the facades to upgrade glazing and frames at level 2. Upgrade and replacement fixtures, fittings and finishes and other associated works.

    Decided 18 Sep 2026 Heritage and listed buildings
  • 25/01071/LBC Granted

    Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    Application under Section 19 of the Planning (Listed Buildings and Conservation Areas) Act 1990 to vary Condition 3 of Listed Building Consent 22/00895/LBC dated 2nd December 2022 to refer to a revised list of drawings amended to reflect design alterations and to discharge Condition 4 relating to detailed design elements of the proposal.

    Decided 21 Nov 2025 Heritage and listed buildings
  • 24/00496/FULL Granted

    Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    Temporary permission until September 2024 for seating, two pergola structures and a kiosk shed, for the serving of non-alcoholic refreshments, at the Barbican lakeside terrace area associated with the summer "pop-up" Picnic Garden (rebranded this year as Lakeside Lounge).

    Decided 4 Jul 2024 Full applications
  • 23/01363/LBC Granted

    Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    Replacement of existing house lighting fixtures within the Theatre with new LED fixtures. Introduction of new fittings to supplement existing lighting in the front rows of the circle, upper circle and gallery.

    Decided 10 Oct 2024 Heritage and listed buildings
  • 23/01236/LBC Granted

    Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    Removal of foot pumps and installation of hand sensors to operate taps in the Level -1.5 toilets.

    Decided 18 Jul 2024 Heritage and listed buildings
  • 23/01195/LBC Granted

    Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    Temporary installation of a fabric woven artwork for a temporary period between February 2024 and August 2024 , titled: 'Purple Hibiscus' by Ibrahim Mahama

    Decided 23 Jan 2024 Heritage and listed buildings
  • 23/01194/FULL Granted

    Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    Temporary installation of a fabric woven artwork, for a temporary period between February 2024 and August 2024, titled: 'Purple Hibiscus' by Ibrahim Mahama.

    Decided 23 Jan 2024 Full applications
  • 23/00672/FULL Awaiting decision

    Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    An application under Section 73 of the Town and Country Planning Act 1990 (as amended) to amend Condition 6 (Approved Documents) of planning permission 22/00942/FULL dated 27 January 2023 to allow for the removal of the approved bulkheads and the insertion of timber louvres.

    Submitted 27 Jun 2023 Full applications

Timeline

Dates from the published record

  1. 6 Oct 2026

    Received by City of London

  2. 13 Oct 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 1 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    City of London took a median of 84 days over the applications it decided in the last year.

What happens while it is decided

This application is with City of London for determination, against a statutory target of eight weeks. Over the last year City of London decided heritage and listed building applications in a median of 94 days. More in our guide to how long planning decisions take.

About heritage and listed building applications

Listed building consent is needed for works that affect the special interest of a listed building, and carrying out such works without it is a criminal offence. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Art Gallery Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    26/00707/LBC Submitted 15 May 2026 50 yards away

    Reconfiguration and upgrade of the concert hall backstage areas to include the amalgamation of smaller dressing rooms, changing spaces and support spaces; the reconfiguration of the artist lounge and bar ; rationalisation of showers to provide a wheelchair accessible dressing room with an en-suite WC and shower; fire safety upgrades, update layout of a rehearsal spaces, and provision of fire rated storage space and other associated works throughout.

    Granted Heritage and listed buildings 51 docs
  • Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    26/00612/FULL Submitted 27 Apr 2026 50 yards away

    New hard and soft landscaping for the sculpture court to include removal and replacement of all paving with new waterproofing below, new ramps and steps, new raised planting beds, seating, and lighting, proposed parameters for temporary structures and artworks to facilitate continued use of the sculpture court for art installations, works to the staff spaces facades to upgrade glazing and frames to level 2 and other associated works.

    Granted Full applications Windows or glazing 133 docs
  • Library Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    25/01774/LBC Submitted 16 Dec 2025 50 yards away

    Internal refurbishment works to the Library, comprising: a) Removal and storage of original joinery items to Children's Library b) Removal of non-original joinery and floor finishes c) Alterations to original bookshelves d) Additional joinery to complement existing e) Installation of new mesh security screen and door access controls f) Additional power provision and cabinet g) Alterations to signage h) Alterations to non-original lighting built into joinery i) New floor finishes throughout public areas of the Library

    Granted Heritage and listed buildings 36 docs
  • Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    26/00613/LBC Submitted 27 Apr 2026 50 yards away

    New hard and soft landscaping for the sculpture court to include removal and replacement of all paving with new waterproofing below, new ramps and steps, new raised planting beds, seating, lighting, and drinking water fountain. Works to the staff spaces to include internal reconfiguration, new WCs, showers, and kitchenette, works to the facades to upgrade glazing and frames at level 2. Upgrade and replacement fixtures, fittings and finishes and other associated works.

    Granted Heritage and listed buildings Windows or glazing 133 docs
  • Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    26/01139/LBC Submitted 7 Aug 2026 50 yards away

    Upgrade of existing and installation of additional evacuation signage and downlights within the Concert Hall, and associated works.

    Granted Heritage and listed buildings 40 docs
  • Arts Centre Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    26/01407/LBC Submitted 6 Oct 2026 50 yards away

    100% historically approved · decision due ~1 Dec

    Installation of new ceiling mounted sprinkler systems and associated pipework at Levels -1, 0, 1 and 2 across the Arts Centre main Foyers and Library spaces; replacement and installation of sprinklers within the Staff Spaces; replacement of sprinklers within the Curve Gallery; installation of sprinkler mains within Shafts 13 and 17; ventilation and ductwork to the GSMD lightwell and associated works.

    Awaiting decision Heritage and listed buildings 42 docs

In City of London

  • 24/01057/LBC Withdrawn

    Snow Hill Police Station 5 Snow Hill London EC1A 2DP

    Installation of 2x lanterns with hub branding and one internally illuminated sign.

    Received 2 Oct, published by the council 21 Oct 2026 Heritage and listed buildings
  • 26/01222/LBC Granted

    Rising Sun Public House 61 Carter Lane London EC4V 5DY

    Installation of 2no. eyebolt fixings to northern elevation to hold catenary wires to facilitate festive lighting and decoration displays

    Received 27 Aug, published by the council 8 Sep 2026 Heritage and listed buildings
  • 26/01179/LBC Granted

    Shaws Booksellers Public House 31 - 34 St Andrew's Hill London EC4V 5DE

    Alterations to a Listed building including: (i) installation of externally illuminated fascia signage, projecting signage and menu signs (ii) installation of nine awnings.

    Received 17 Aug, published by the council 26 Aug 2026 Heritage and listed buildings
  • 26/01167/LBC Granted

    4 Frederick's Place London EC2R 8AB

    1 x wall mounted non illuminated polished brass plaque.

    Received 13 Aug, published by the council 19 Aug 2026 Heritage and listed buildings
  • 26/00489/LBC Granted

    391 Cromwell Tower Barbican London EC2Y 8NB

    Replacement of timber service door with an aluminium framed glazed door at penthouse levels 39 - 40.

    Received 2 Apr, published by the council 24 Jul 2026 Heritage and listed buildings