Leadenhall Court 1 Leadenhall Street London EC3V 1PP

Awaiting decision City of London 26/00552/PODC Planning Obligations

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Submission of the Local Procurement Strategy Final Report pursuant to Schedule 3 Paragraph 2.8 of the S106 Agreement dated 28th March 2019 (Planning Application Reference: 18/00740/FULEIA).

As published by the council, reference 26/00552/PODC

Application record

Reference
26/00552/PODC
Type
Planning Obligations
Status
Under Consideration
Received
17 Apr 2026
Validated
22 Apr 2026
Ward
Lime Street
Decision by
Delegated
Postcode
EC3V 1PP

Site history

Applications at this address on the City of London register

This site has had 16 applications since 2021: 15 approved, 0 refused.

  • 26/00397/MDC Granted

    Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    Submission of details of Level 32 Terrace Landscape Details Report and Wind Microclimate Technical Memorandum pursuant to conditions 23 and 27 of Planning permission 18/00740/FULEIA dated 28.03.2019.

    Decided 15 Apr 2026 Conditions
  • 26/00251/MDC Granted

    Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    Submission of detail of BREEAM Certificate pursuant to condition 41 of Planning permission 18/00740/FULEIA dated 28.03.2019.

    Decided 10 Apr 2026 Conditions
  • 25/01699/MDC Granted

    Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    Submission of details of plant noise, installation and maintenance pursuant to condition 28 of planning permission 18/00740/FULEIA dated 28/03/2019.

    Decided 29 Jan 2026 Conditions
  • 25/01563/MDC Granted

    Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    Submission of details pertaining to sound insulation and the resistance to the transmission of sound pursuant to condition 24 of planning permission 18/00740/FULEIA dated 28/03/2019.

    Decided 24 Aug 2026
  • 25/01413/MDC Granted

    Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    Submission of details relating to mounting of mechanical plant to minimise transmission of structure borne sound or vibration pursuant to condition 29 of planning permission 18/00740/FULEIA dated 28/03/2019.

    Decided 13 Nov 2025 Conditions
  • 25/01519/PODC Granted

    Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    Submission of the Interim Travel Plan pursuant to Schedule 3 Paragraph 9.1 of the S106 Agreement dated 28th March 2019 (Planning Application Reference: 18/00740/FULEIA).

    Decided 12 Nov 2025
  • 25/01335/PODC Granted

    Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    Submission of a Delivery and Servicing Management Plan pursuant to Schedule 3, Paragraph 10.1 of the Section 106 agreement associated with planning application ref. no. 18/00740/FULEIA dated 28th March 2019.

    Decided 17 Feb 2026
  • 25/01193/PODC Granted

    Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    Submission of details of public terrace management plan pursuant to schedule 3, paragraph 12.2 of the Section 106 agreement dated 28th March 2019 (18/00740/FULEIA).

    Decided 9 Dec 2025
  • 25/01134/MDC Granted

    Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    Submission of Level 32 Terrace Landscape Details Report and Wind Microclimate Technical Memorandum pursuant to partial discharge (relating to the level 32 terrace only) of conditions 23 and 27 of planning permission 18/00740/FULEIA dated 27.03.2019.

    Decided 27 Nov 2025 Conditions
  • 25/00980/MDC Granted

    Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    Submission of Environmental Verification Report pursuant to discharge of Condition 13c of Planning Permission 18/00740/FULEIA dated 27.03.2019.

    Decided 4 Aug 2025 Conditions

Timeline

Dates from the published record

  1. 17 Apr 2026

    Received by City of London

  2. 22 Apr 2026

    Validated

    Checked as complete and ready for consideration.

  3. 24 Jul 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 17 June 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    City of London took a median of 78 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

DP9 Ltd Applicant

Active · incorporated 2004

2,256 applications on PlanIndex · across 37 councils · 98% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

2 documents on file for this application

  • APPLICATION EMAIL Application Form · 17 Apr 2026
  • FINAL MONITORING REPORT Other · 17 Apr 2026

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with City of London for determination, against a statutory target of eight weeks. Over the last year City of London's median decision took 78 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on City of London's portal will say. Our guide explains the common types.

Nearby applications

Within 500 metres

  • Leadenhall Court 1 Leadenhall Street London

    21/00090/MDC Submitted 10 Feb 2021 0m away

    Submission of details of sewer vents pursuant to condition 12 of planning permission 18/00740/FULEIA dated 28th March 2019.

    Granted Conditions 5 docs
  • Leadenhall Court 1 Leadenhall Street London

    21/00089/MDC Submitted 10 Feb 2021 0m away

    Submission of Construction Environmental Management Plan pursuant to condition 11 of planning permission 18/00740/FULEIA dated 28th March 2019.

    Granted Conditions 18 docs
  • Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    21/00464/PODC Submitted 2 Jun 2021 0m away

    Submission of the Utility Connection Requirements and Draft Programme pursuant to Schedule 3 Paragraph 13.1 of the Section 106 Agreement dated 28 March 2019 (Planning Application Reference 18/00740/FULEIA).

    Granted 8 docs
  • Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    25/01699/MDC Submitted 4 Dec 2025 0m away

    Submission of details of plant noise, installation and maintenance pursuant to condition 28 of planning permission 18/00740/FULEIA dated 28/03/2019.

    Granted Conditions 5 docs
  • Leadenhall Court 1 Leadenhall Street London EC3V 1PP

    21/00332/MDC Submitted 30 Apr 2021 0m away

    Submission of details of water saving measures pursuant to condition 15 of planning permission 18/00740/FULEIA dated 28th March 2019.

    Granted Conditions 25 docs
  • Leadenhall Court 1 Leadenhall Street London

    21/00219/MDC Submitted 23 Mar 2021 0m away

    Details of a Construction Logistics Plan pursuant to Condition 10 of planning permission dated 28.03.2019 (18/00740/FULEIA).

    Granted Conditions 35 docs